CAPM Risk Responses Flashcards

1
Q

The risk is outside of the project scope and is escalated to management

A

Escalate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Avoid the risk

A

Avoidance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Mitigation

A

Reduce the probability of the risk event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The risk may be small so the risk may be allowed

A

Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk ownership is transferred to a 3rd party, usually for a fee

A

Transference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A positive risk strategy to increase the probability/ impact of the opportunity of the project

A

Enhance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A positive risk that a project wants to take advantage of

A

Exploit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A positive risk that can be shared within the organization or other projects

A

Share