Project Cost Management Terms Flashcards

1
Q

Actual Cost (AC)

A

The actual amount of monies the project has spent to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analagous Estimating

A

An approach that relies on historical information to predict the cost of the current project. It is also known as top down estimating and is the least reliable of all the cost-estimating approaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottom-up estimating

A

Estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. One of the most releaible methods to predict project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget Estimate

A

This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Commercial Database

A

A cost estimating approach that uses a database, typically software-driven, to create the cost estimate for a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contingency Reserve

A

Contingency allowance to account for overruns in costs. They are used at the PM’s discretion and with managements approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost aggregation

A

Costs are parrallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost baseline

A

A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost budgeting

A

Cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost change control system

A

A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost Management Plan

A

This dictates how cost variances will be managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost of poor quality

A

The monies spent to recover from not adhering to the expected level of quality. Examples : rework, defect repair, loss of life

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost of quality

A

The monies spent to attain the expected level of quality within a project. Examples : Training, safety, testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Performance Index (CPI)

A

Measures the project based on its financial performance. Formula is EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost variance (CV)

A

Difference of the earned value and the cumulative actual costs of the project. Formula is EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Definitive Estimate

A

This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create this estimate. Range of variance from -5 to +10 percent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Direct Costs

A

Costs are attributed directly to the project work and cannot be shared among projects (for example airfare, hotels, long-distance phone charges)

18
Q

Earned value (EV)

A

The physical work completed to date and the authorized budget for that work. It is the percentage of BAC that represents the actual work completed in the project

19
Q

Estimate at Completion (EAC)

A

These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project

20
Q

Estimate to complete (ETC)

A

An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.

21
Q

Fixed Costs

A

Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).

22
Q

Funding limit reconciliation

A

An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints.

23
Q

Indirect Costs

A

Costs that are representative of more than one project

24
Q

Known Unknown

A

An event that will likely happen within the project, but when it will happen and to what degree is unknown

25
Q

Learning Curve

A

An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work

26
Q

Oligopoly

A

A market condition where the market is so tight that the actions of one vendor affect the actions all the others

27
Q

Opportunity Cost

A

The total cost of the opportunity that is refused to realize an opposing opportunity

28
Q

Parametric Estimating

A

Estimating approach that uses a model to extrapolate what costs will be needed. For ex : Cost per hour and cost per unit

29
Q

Planned Value (PV)

A

The work scheduled and the budget authorized to accomplish that work. It is the % of the BAC that reflects where the project should be at that point in time

30
Q

Project variance

A

The final variance, which is discovered only at the project’s completion. The formula is VAR = BAC – AC.

31
Q

Regression analysis

A

This is a statistical approach to predicting what future values may be, based on historical values. Regression analysis creates quantitative predictions based on variables within one value to predict variables in another. This form of estimating relies solely on pure statistical math to reveal relationships between variables and to predict future values.

32
Q

Reserve analysis

A

Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but is included as part of the project budget.

33
Q

Rough order of magnitude

A

This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from –25 percent to +75 percent.

34
Q

Schedule Performance Index (SPI)

A

Measures the project based on its schedule performance. Formula is SPI = EV/ PV

35
Q

Schedule Variance (SV)

A

The difference between the earned value and the planned value. Formula is SV = EV - PV

36
Q

Single Source

A

Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor

37
Q

Sole Source

A

Only one vendor can provide what your project needs to purchase.

38
Q

Sunk Costs

A

Monies that have already been invested in a project

39
Q

To-Complete Performance Index

A

A formula to forecast the likelihood of a project to achieve its goals based on what’s happening in the project right now. There are two different flavors for the TCPI, depending on what you want to accomplish. If you want to see if your project can meet the budget at completion, you’ll use this formula: TCPI = (BAC – EV)/(BAC – AC). If you want to see if your project can meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC – EV)/(EAC – AC).

40
Q

Variable Costs

A

Costs that change based on the conditions applied in the project (# of meeting participants, supply and demand of materials, and so on)

41
Q

Variance

A

The difference between what was expected and what was experienced

42
Q

Variance at Completion (VAC)

A

Forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. Formula is VAC= BAC -EAC