Project Cost Management Terms Flashcards
Actual Cost (AC)
The actual amount of monies the project has spent to date
Analagous Estimating
An approach that relies on historical information to predict the cost of the current project. It is also known as top down estimating and is the least reliable of all the cost-estimating approaches
Bottom-up estimating
Estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. One of the most releaible methods to predict project costs
Budget Estimate
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
Commercial Database
A cost estimating approach that uses a database, typically software-driven, to create the cost estimate for a project
Contingency Reserve
Contingency allowance to account for overruns in costs. They are used at the PM’s discretion and with managements approval
Cost aggregation
Costs are parrallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts.
Cost baseline
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project
Cost budgeting
Cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS.
Cost change control system
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost
Cost Management Plan
This dictates how cost variances will be managed
Cost of poor quality
The monies spent to recover from not adhering to the expected level of quality. Examples : rework, defect repair, loss of life
Cost of quality
The monies spent to attain the expected level of quality within a project. Examples : Training, safety, testing
Cost Performance Index (CPI)
Measures the project based on its financial performance. Formula is EV/AC
Cost variance (CV)
Difference of the earned value and the cumulative actual costs of the project. Formula is EV-AC
Definitive Estimate
This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create this estimate. Range of variance from -5 to +10 percent
Direct Costs
Costs are attributed directly to the project work and cannot be shared among projects (for example airfare, hotels, long-distance phone charges)
Earned value (EV)
The physical work completed to date and the authorized budget for that work. It is the percentage of BAC that represents the actual work completed in the project
Estimate at Completion (EAC)
These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project
Estimate to complete (ETC)
An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.
Fixed Costs
Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).
Funding limit reconciliation
An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints.
Indirect Costs
Costs that are representative of more than one project
Known Unknown
An event that will likely happen within the project, but when it will happen and to what degree is unknown