Project Schedule Management Flashcards

1
Q

What are the key inputs for define activity

A
  1. Project management plan
    a. Schedule Management Plan
    b. Scope Baseline (WBS, WBS dictionary, project scope statement)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the key tools & technique for define activity

A
  1. Decomposition (breaking down work packages into smaller activities)
  2. Rolling wave planning (progressive elaboration)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s activity list

A
  1. list of all scheduled activities to complete work package

Note: each activity should map to one work package and should have identifier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s activity attribute

A

resources needed to complete activity, location of activity, cost, assumption, constraints, leads and lags, relationship with other activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Milestone List

A

milestone = major accomplishment or event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is sequence activity

A

Take list of activity and put them in order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key inputs for scheduling activities

A
  1. Project Management Plan
    a. Schedule Management Plan
    b. Scope Baseline
  2. Project Documents
    a. Activity list
    b. Activity attributes
    c. Milestone list
    d. Assumption log
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the tools & techniques to sequence activities

A
  1. Precedence Diagramming Method
  2. Dependency Determination
    3, Leads & Lags
  3. Project Management Information System
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What’re FS, FF, SS, SF

A
  1. Finish-to-Start (FS): finish activity A then can start activity B
  2. Finish-to-Finish (FF): finish both activities simultaneously
  3. Start-to-Start (SS): start activity A first before starting activity B
  4. Start-to-Finish (SF): cannot finish until activity A starts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s mandatory dependency

A

Have to finish one activity to start next activity (hard logic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Discretionary dependencies

A

activities do not need to get done in specific order (soft logic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External dependencies

A

dependent on activities outside of project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Internal dependencies

A

depend on activities within the control of project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What’s the output of sequencing activity

A

Project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What’s the output of sequencing activity

A

Project schedule network diagram

project document update (those inputs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the examples of input of estimating activity duration

A
  1. Project Management Plan (e.g. schedule management plan, scope baseline)
  2. Project document list
    a. activities: activity list, attributes, milestone
    b. resource: resource breakdown structure, calendar, requirement
17
Q

What are the examples of input of estimating activity duration

A
  1. Project Management Plan (e.g. schedule management plan, scope baseline)
  2. Project document list
    a. activities: activity list, attributes, milestone
    b. resource: resource breakdown structure, calendar, requirement
18
Q

What’s Analogous estimating? What’s the advantage and drawback

A
  1. Historical information to assign current duration
  2. Quick to do
  3. Less accurate
19
Q

What’s parametric estimating

A

based on historical data and variable to estimate activity duration

20
Q

Three point estimate (Beta distribution)

A

(optimistic +4 * realistic + pessimistic)/4

21
Q

What’s the formula to calculate std dev

A

(pess-opt)/6

22
Q

What’s triangular distribution

A

(opt + realistic + pess)/3

23
Q

Critical path activities have float

A

False

24
Q

What is float

A

The amount of time that can delay activity without delaying project end date

25
Q

What is resource levelling? What’s the solution and impact?

A
  1. Overallocated resources that is working on two or more activities
  2. Arrange in sequential order instead of parallel. might lengthen critical path
26
Q

Resource Smoothing

A

Change the schedule without affecting critical path

27
Q

What is Monte Carlo Simulation

A

What if scenario testing

28
Q

What are two types of schedule compression

A
  1. Crashing: add more resources to activities to complete them faster
  2. Fast tracking: do activities in parallel instead of sequentially
29
Q

Schedule Baseline

A
  1. can only be changed with approval

2. measure the progress of project schedule

30
Q

Project schedule

A
  1. include start date and end date for all activities
    a. Bar Chart (Gantt Chart)
    b. Milestone chart: only show major deliverable
    c. Project schedule network diagram
31
Q

Formula of calculating float

A

LS-ES
OR
LF-EF

32
Q

Calculation of EF

A

ES + Duration -1

33
Q

Calculation of LS

A