Cost Management Flashcards

1
Q

What is value engineering

A

Find the less costly way of doing work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the difference between direct vs indirect cost

A

Direct: billed directly to project
Indirect: shared & allocated among several projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan cost management

A

How project costs is estimated, budgeted, managed, monitored, and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What cost management plan includes

A
How costs is planned, structured, controlled
unit of measure
level of accuracy
reporting format
control threshold
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Accuracy of cost estimation would increase as the project progresses through project lifecycle (T/F)?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Examples of cost estimates

A

labor, material, equipement, service, facility
inflation allowance,
cost of financing
contingency cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Rough order of magnitude

A

-25% <= X <= +75% (initating)

most inaccurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

budget estimate

A

-10% <= X <= +25%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

definitive estimate

A

-5% <= X <= +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is analogous estimating

A

top down estimating (based on previous projects) and inaccurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Parametric estimating

A

Mathematical estimation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bottom up estimating

A

breakdown of work and identify its pieces and aggregate back up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the ways of cost estimation

A

Analogous estimating
Parametric estimating
bottom up
three point estimation (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reserve analysis

A

add reserve time to over work risks

Risk register indicates how to respond to risk (e.g. adding more costs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Difference between contingency reserve and management reserve

A
Contingency reserve (known unknown): include in cost baseline and within control of PM
Management reserve: extra money allocated by management in case needs more funding; not included in cost baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the key outputs of estimating costs

A
  1. Cost estimates (associated with each activity)
  2. Basis of estimates
    a. Range of estimates
    b. Confidence level of estimates
17
Q

What is determine budget

A

Aggregate activity cost to project cost

18
Q

Key inputs of budgeting

A
  1. Project Management Plan
    a. Cost Management Plan
    b. Scope baseline
    c. Resource Management Plan
  2. Project documents
    a. Cost estimates
    b. basis of estimation
    c. risk register
  3. Business Documents
    a. Biz case
    b. Benefit Managemetn Plan
  4. Agreement
19
Q

Key T&T of budgeting

A
  1. Cost aggregation (scheduled activity)
  2. Data analysis
    a. Contingency reserve
    b. Management reserve
  3. Historical information review
    a. Analogous
    b. Parametric
  4. Funding limit reconciliation
  5. Financing
20
Q

Key outputs of budgeting

A

Cost Baseline

21
Q

What is the purpose of controlling cost

A
  1. Planned vs actual work

2. Investigative and take corrective/preventive action

22
Q

What’s the key input of controlling cost

A
  1. PMP: Cost management plan; cost baseline
  2. Funding requirement: how much funding
  3. Work performance data: actual cost
23
Q

T&T

A
  1. Earned value analysis: calculation to give stat about project performance
  2. Reserve analysis: ensure risk has correct response
  3. variance analysis
  4. trend analysis
24
Q

Output of control cost

A
  1. Work performance info
  2. Cost forecast
  3. Change request
25
Q

Burn rate cost

A

average cost per hour person used for agile

cost /person X hours X working hours/week X week