Project Risk Management Flashcards
1
Q
What are the six sequential risk management processes?
A
- Plan Risk Management
- Identify Risks
- Perform Qualitative Risk Management
- Perform Quantitative Risk Management
- Plan Risk Responses
- Control Risks
2
Q
What is Expected Monetary Value (EMV)?
A
Calculation used to determine an overall ranking of risks EMV = P x I where P = probability I = impact