Project Cost Management Flashcards
How is Schedule Performance Index (SPI) calculated and what does it mean?
Formula: SPI = EV/PV EV = Earned Value PV = Planned Value Meaning: Measures project progress against the rate originally planned 1 Project is on schedule 1 Project is ahead of schedule
How is Cost Performance Index (CPI) calculated and what does it mean?
Formula: CPI = EV/AC EV = Earned Value AC = Actual Cost Meaning: $ worth of work for every $ spent 1 On budget 1 Ahead of budget
How is Schedule Variance (SV) calculated and what does it mean?
Formula: SV = EV - PV
EV = Earned Value
PV = Planned Value
Negative = Behind schedule
Zero = On schedule
Positive = Ahead of schedule
How is Planned Value (PV) determined?
Authorized budget of the work to be accomplished for an activity.
Total planned value for the project is also known as Budget at Completion (BAC)
How is Earned Value (EV) determined?
Value of the work that has been actually completed.
How is Actual Cost (AC) determined?
Actual cost incurred for the work completed.
What is Budget at Completion (BAC)?
Total budget for the project
How is Cost Variance (CV) calculated and what does it mean?
Formula: EV - AC EV = Earned Value AC = Actual Cost If negative, project is over budget If positive, project is under budget
How is Variance at Completion (VAC) calculated and what does it mean?
Formula: BAC - EAC
BAC = Budget at Completion
EAC = Estimate at Completion
As of today, how much over or under budget is the project expected to be
How is Estimate to Complete (ETC) determined and what does it mean?
How much more will the project cost
Formula: EAC - AC
OR
Re-estimate remaining work from the bottom up
What is Estimate at Completion (EAC) used for?
To determine how much the total project is expected to cost, as of today
What are the four formulas for EAC and when are they used?
- BAC/CPI
Use if no variances from BAC have occurred or project will continue at the same rate of spending (based on cumulative CPI or trends in current CPI) - AC + Bottom-up ETC
Use when original estimate was inaccurate and project needs to be re-baselined - AC + (BAC - EV)
Use when one-time variances have occurred that will not occur again or are thought to be atypical for the future - AC + (BAC - EV)/(CPI x SPI)
Use when current variances are thought to be typical for the future and when schedule constraints will influence the remaining work, for example when cumulative CPI is less than one and a firm completion date must be met.
What is To-Complete Performance Index (TCPI)?
Answers the question, in order to stay within budget, what rate must be met for the remaining work
Formula: (BAC - EV) / (BAC - AC)
What is a Rough Order of Magnitude (ROM) estimate?
Used during project initiation, typical range is -25% to + 75% but can vary depending on how much is known about the project
What is a Budget estimate?
Used during project planning, typical range is -10% to + 25%