What is Point of Total Assumption (PTA)?

A

Applies only to Fixed Price Incentive Fee (FPIF) contracts and refers to the amount above which the seller bears all the loss of a cost overrun

(Ceiling price - Target price/Buyer’s share ratio) + Target cost