Which of the following is NOT a major cause of project delays?

A. A lack of performance standards
B. The student syndrome
C. Misplaced safety
D. None of the above

A

None of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Which of the following is a major cause of project delays?

A

The student syndrome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following is critical to performance reporting success?

A

Measuring progress using the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following is not tracked in earned value?
A. Are the right deliverables being done?
B. How much has been spent?
C. How much has been accomplished?
D. How long did it take to achieve the results?

A

Are the right deliverables being done?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned value purports to be able to accurately predict final project performance with only how much of the project completed?

A

10-15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
Which of the following is NOT required to use the earned value method?
A. A WBS
B. A schedule for each work package
C. Accurate resource time reporting 
D. Completed project use cases
A

Completed project use cases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following terms represents the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or WBS component?

A

Actual costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If the project has completed $6 worth of work, had $10 in expenses, and planned on spending $7 what is the project’s cost variance?

A

-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the project has completed $6 worth of work, had $10 in expenses, and planned on spending $7 what is the project’s cost performance index?

A

0.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the project has completed $6 worth of work, had $10 in expenses and planned on spending $7 what is the project’s schedule variance?

A

-1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If the project has completed $6 worth of work, has $10 in expenses and planned on spending $7 what is the project’s schedule performance index?

A

.86

How well did you know this?
1
Not at all
2
3
4
5
Perfectly