Project Management Flashcards
Retainage at substantial completion is often equal to what?
Contractor’s profit (5-20%, commonly 10%)
Components of the Contract Documents
Contracts, Gen Conditions, Supplemental Conditions, Drawings, Specs, Addenda and Modifications to the contract (Change order, CCD, ASI). Anything to do with bidding is NOT included.
Procedures for submitting shop drawings are included in what spec section?
Division 01 Gen Requirements
Supplemental Conditions
A503, prepared by owner. Includes legal rights and responsibilities that may vary from one project to another including insurance, indemnification, liquidated damages, legal requirements of the jurisdiction, fiduciary obligations.
What items does the IBC require in the drawings?
Fire Protection shop drawings (submitted after permit)
Structural live loads
Site Plan
Exterior Wall envelope
What items does the IECC require in the drawings?
Mechanical system design criteria
Insulation materials and their R-values
Easiest type of spec to write
Proprietary or Base bid w/ alternates /Closed, followed by base bid with alternates
Hardest type of spec to write
Descriptive or Reference /Open (requires knowing all the attributes)
Types of closed specs
aka Prescriptive
Proprietary
Base bid with alternates
Base bid or approved equal
Types of open specs
aka Performance
Descriptive specification
Reference standard specification
Which types of projects use open specs?
Public projects to encourage competitive bidding
Project with tight budget that needs to find the lowest cost for each spec
Design-build project that allows for contractor choice to fit in budget
Spec section for Communications
27
Spec section for Fire Protection
21
Spec section for integrated automation
24
Spec section for plumbing
22