Project Management Flashcards

1
Q

What activities carry out a project?

A

Defining and organizing
Planning
Executing
Monitoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What activities belongs to the project planning phase?

A

Work structure
Making the Schedule
Assessing risks
Analyzing cost-time trade-offs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What activities belong to the project defining and organizing phase?

A

Defining objectives and organizing resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What activities belong to the project executing phase?

A

Manage resources
Implement risk response
Manage project knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What activities belong to the project monitoring phase?

A

Compare
Revise
Action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Project?

A

A related set of activities that come together to form a unique outcome with a definite starting and end point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are examples of a project?

A

Making a rocket
Making a movie
Organizing a wedding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you compute the slack time?

A

Latest Start Time - Earliest Start Time

Latest Finish Time - Earliest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can there be slack time in the Critical Path without delaying the project?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an activity’s Earliest Start time when it has only 1 predecessor?

A

Its ES equals the Earliest Finish Time (EF) of its predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an activity’s Earliest Start time when it has many predecessors?

A

Its ES equals the Maximum earliest finish time of all its predecessors (activity begins after the last predecessor ends)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an activity’s earliest finish time?

A

Its EF equals the earliest start time plus its activity time (ES + Activity Time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly