Project Finance & Quantification and Costing (L3) Flashcards
What are the responsibilities of a cost manager?
Manage risk allowances expenditure
Prepare pricing documents for tendering
Evaluate and analyse tender bids
Prepare interim valuations
Value variations
Assess the contractors claims
Negotiate and agree final accounts
Issue financial reports or statements
Prepare and maintain cost and cash flow forecasts
Which measurement rules represent industry best practice for capital building and building maintenance works in the UK?
New Rules of Measurement (NRM)
Can you provide an overview of the NRM documents?
NRM1 - Order of cost estimating and cost planning for capital building works
NRM2 - Detailed measurement for building works
NRM3 - Order of cost estimating and cost planning for building maintenance works
Why is it important to measure works according to industry standards?
To provide consistency and greater accuracy in pricing
To ensure that all parties price on the same basis and therefore reduce the risk of dispute
Is it mandatory for Chartered Surveyors to follow the procedures set out in NRM?
Following NRM is not a mandatory requirement. However, when an allegation of professional negligence is made, the adjudicator or court is likely to take account of any relevant guidance (such as NRM) to ascertain whether or not the surveyor acted with reasonable competence
How is risk dealt with under NRM?
NRM recommends that risk allowances are not a standard percentage, but a properly considered assessment of the risk, considering the completeness of the design and other uncertainties such as the extent of site investigation undertaken
Can you tell me the four risk categories defined under NRM?
Employer Change Risks (programme impact)
Employer Other Risks (availability of funds / delay to PC)
Design Development Risks (planning requirements)
Construction Risks (ground conditions)
How does NRM define the ‘cost limit’ for the project?
The maximum expenditure the client is prepared to make in relation to the completed building.
It includes construction costs, professional services, other costs, and risk allowances
How does NRM define the ‘base cost estimate’ for the project?
An evolving estimate of known factors without any allowances for risk and uncertainty, or inflation
What is an ‘order of cost estimate’?
An estimate based on benchmark data for a similar type of project based on the clients strategic definition or initial brief. Its purpose is to establish the affordability of a proposed development for a client
Which RIBA stage does an order of cost estimate take place?
RIBA Stage 1 - Preparation and Briefing
Difference between an order of cost estimate and cost plan?
An estimate provides a possible cost based on the ER’s and is the initial stage of the process - usually based on m2 areas or functional units. A cost plan is a more detailed elemental breakdown that shows how costs are distributed across the project - it is an estimate based on a specific design
Can you explain the term ‘cost per functional unit’?
The unit rate that, when multiplied by the number of functional units (e.g. nr of beds) gives the total building works estimate.
What typical info should accompany an order of cost estimate?
Cover letter
Executive summary
Cost limit
Specification notes
Assumptions
Exclusions
Drawings
Risk register
Cash flow info
What is a cost plan?
An estimate based on a specific design
Other than predicting the final cost, what other benefits does a cost plan provide?
Helps inform designers of the cost implications of their proposals, allowing for practical and balanced design
Do you need a programme to complete the cost plan?
Yes, a programme or some high level dates will be required to price preliminaries
Key information includes:
- Design and tendering periods
- Start on site date
- Construction period
- Completion date
What sources of info are available when preparing a new estimate or cost plan?
Information produced by the BCIS is available
Published pricing books such as Spon’s (may need adjusting for inflation)
Pricing documents from previous similar projects
Speaking directly to the supply chain for current information
How do you take account of location within estimates?
A location factor is usually applied to recognise differences in prices. For example, a project in London is usually more expensive than a project in Nottingham.
What is a cost plan risk allowance?
A quantitative allowance set aside as a precaution against risks and future requirements
What component fees may be included within an estimate?
Consultant fees, Contractor fees and Other fees
What benefit does the client get out of accurate cost planning?
Allows informed commercial decisions to be made
Including whether or not the project is affordable
Or whether or not certain changes are affordable
How do you deal with a cost plan that is over budget?
Communicate the matter to the client and project team in a clear and concise way
Review the specification to identify potential areas where savings could be made (if any)