Project finance control and reporting (L3) Flashcards

1
Q

What measures can be taken to effectively control costs during the construction phase of a project?

A
  • Proactive risk and contingency management
  • Implementing a robust change control process
  • Management of provisional sums within a budget
  • Regular cost reporting which is also forward looking
  • Rolling day 1 final accounts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of change control on a construction project?

A

To provide a method of identifying, assessing and managing change, giving details of cost and programme impact. Helping safeguard the client’s investment and the contractor’s profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of a financial report?

A

To report against budgeted values and act as a working cost check on the total project budget.
To report on the contract progress against the pre-contract predictions
For internal use to identify cash shortfalls
To present financial accounts at year end on CH
To avoid surprises for the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you include in a financial report for a client?

A

The contract sum
Instructed variations
Potential future variations as advanced warnings
Claims
Anticipated final account total
Cost to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information is included within Contract Review forms?

A

Current cost, value and margin
Estimated final cost, value and margin
Cash flow
Certified to date position
Risk and opportunites
Subcontract liabilities
Progress of works against the contract programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are contract liabilities?

A

The amount owed on the contract if the account was final accounted at the present point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What two things does an earned value analysis tell you?

A

Will work cost more or less than planned?
Will work finish before or behind schedule?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you set up a Change Control system on a project?

A

Communicate the contract baseline to the project team against which changes will be measured and what constitutes a change
Establish change control meetings with the team to assist in quantifying, valuing and actioning changes.
Establish the change register.
Once a change is identified it should be added to the register and either actioned or an instruction requested.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Difference between value management and value engineering?

A

Value engineering is a systematic approach that seeks to enhance value by eliminating unnecessary cost whilst maintaining function.
Value management is a systematic review of essential project functions or performance, focused on achieving the best value for the money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is your understanding of Project Financial Control?

A

This covers the financial management of a project during the construction phase. Reports on: Staff, Labour, Materials, Plant, Sundries & Sub-Contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does financial management of construction projects entail?

A

The main areas are:
Cost and Value analysis
Cost and Cash flow analysis
Commercial decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of cost reporting?

A

To inform the client in a construction project the likely outturn cost of the construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does a construction cost report capture?

A

Cost to date and costs to come under a construction contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are fixed costs?

A

The costs that have been agreed to be paid for the known work or services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Provisional Sum?

A

A financial allowance, included within the Contract Sum, for work which is not sufficiently designed to allow the contractor to offer a firm price at tender stage, and/or work that the employer may or may not wish to be carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How are provisional sums expended?

A

The contract administrator (JCT) should issue an instruction for its expenditure.
Prov sum omitted and replaced with the actual cost of work.

17
Q

How are prov sums dealt with in the final account?

A

By the time the project has reached final account stage, the contract administrator will have issued instructions to expend all provisional sums - these are then accounted for in the usual way.

18
Q

Explain the difference between defined and undefined provisional sums

A

For defined prov sums, the contractor is deemed to have allowed for programming and preliminaries within the contract. For undefined prov sums, the contractor does not allow for programming or preliminaries due to unknown design information.

19
Q

What are provisional quantities?

A

Provisional quantities for work where the specification is known, but the exact quantity is yet to be determined.

20
Q

What are prime cost sums?

A

A sum of money included in a unit rate to be expended on materials or goods from suppliers. It is a supply-only rate where the precise specification is TBC. Often used in conjunction with Nominated/Named Sub-Contractors.

21
Q

What is an interim certificate?

A

An assessment of the value of work done to date, to allow the contracting organisation to be paid for the work done.

22
Q

How do you value works for the purposes of interim valuation?

A

Revalue the whole work (not just the work done since last month)

23
Q

What are the two categories of contingency?

A

Allocated contingency - an allowance of likely cost, over and above estimated costs that can be allocated to a specific element or activity.

Unallocated contingency - an allowance for additional costs that have not been specifically identified, but which experience has shown ‘may happen’ and cannot be accurately predicted.

24
Q

What is an accrual?

A

A charge for work that has been done but not yet paid, for which provision is made at the end of a financial period.
Difference between the total liability and the amount already paid.