Project finance control and reporting (L3) Flashcards
What measures can be taken to effectively control costs during the construction phase of a project?
- Proactive risk and contingency management
- Implementing a robust change control process
- Management of provisional sums within a budget
- Regular cost reporting which is also forward looking
- Rolling day 1 final accounts
What is the purpose of change control on a construction project?
To provide a method of identifying, assessing and managing change, giving details of cost and programme impact. Helping safeguard the client’s investment and the contractor’s profit.
What is the purpose of a financial report?
To report against budgeted values and act as a working cost check on the total project budget.
To report on the contract progress against the pre-contract predictions
For internal use to identify cash shortfalls
To present financial accounts at year end on CH
To avoid surprises for the client
What would you include in a financial report for a client?
The contract sum
Instructed variations
Potential future variations as advanced warnings
Claims
Anticipated final account total
Cost to complete
What information is included within Contract Review forms?
Current cost, value and margin
Estimated final cost, value and margin
Cash flow
Certified to date position
Risk and opportunites
Subcontract liabilities
Progress of works against the contract programme
What are contract liabilities?
The amount owed on the contract if the account was final accounted at the present point in time
What two things does an earned value analysis tell you?
Will work cost more or less than planned?
Will work finish before or behind schedule?
How would you set up a Change Control system on a project?
Communicate the contract baseline to the project team against which changes will be measured and what constitutes a change
Establish change control meetings with the team to assist in quantifying, valuing and actioning changes.
Establish the change register.
Once a change is identified it should be added to the register and either actioned or an instruction requested.
Difference between value management and value engineering?
Value engineering is a systematic approach that seeks to enhance value by eliminating unnecessary cost whilst maintaining function.
Value management is a systematic review of essential project functions or performance, focused on achieving the best value for the money.
What is your understanding of Project Financial Control?
This covers the financial management of a project during the construction phase. Reports on: Staff, Labour, Materials, Plant, Sundries & Sub-Contractors.
What does financial management of construction projects entail?
The main areas are:
Cost and Value analysis
Cost and Cash flow analysis
Commercial decision making
What is the purpose of cost reporting?
To inform the client in a construction project the likely outturn cost of the construction project.
What does a construction cost report capture?
Cost to date and costs to come under a construction contract
What are fixed costs?
The costs that have been agreed to be paid for the known work or services
What is a Provisional Sum?
A financial allowance, included within the Contract Sum, for work which is not sufficiently designed to allow the contractor to offer a firm price at tender stage, and/or work that the employer may or may not wish to be carried out.