Project Finance (control and reporting) Flashcards

1
Q

What is post contract cost control?

A

It is the process of implementing change to the contract and communicating this to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Financial Control?

A
  • Current financial position

- Future position (forecast final account)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How have you demonstrated financial control on a project?

A
  1. Clear cost control process

2. Cost reporting - clear communication to client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a construction cash flow forecast?

A

Identifies the likely monthly figure the client is likely to be liable to pay the contractor over the course of the contract

Contract Sum - S Curve split over the construction programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you create a cashflow?

A

Identify the construction cost,
length of programme
input into excel to create an s graph to show actual vs forecast expenditure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an S-curve?

A

An s curve illustrates that:

  1. Expenditure is slow initially while the site is made ready,
  2. Increases for most of the programme with trade crossover
  3. Tapers off to the end of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How might you use a cashflow forecast on a project?

A

Benchmark forecast progress actual against actual progress.
E.g. progress may be in line with the forecast or it may be falling behind and the current rate of progress might indicate that the contractor is unlikely to complete the works until 3 months after the completion date.

L2 Wrexham - Project fallen behind- used rate of progress to asess likelihood of contractor achieving the revised programme. Identified that the programme was overly stacked and progress had not improved = unlikely to achieve PC date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What might you look out for at the start of a project on a contractors cash flow forecast?

A

Check to see if the programme had been front loaded i.e. they were not claiming a disproportionate amount at the start of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of financial reporting?

A

Forecast the final account based on variations:
Prov sums
Under negotiation and
likely to arise/ at risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What would you include in a Cost Report?

A
  1. Contract Sum
  2. Agreed/instructed variations
  3. Under negotiation
  4. Risk item
  5. Claims
  6. Contract Completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why / how could you include a risk item?

A

L2 - Demolition Project - £50k Provisional Sum for underground petrol tanks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Would you prefer to agree costs quickly or slowly with a contractor?

A

Assuming there was enough time (i.e. no impact on programme)
I would take my time to agree costs rather than agree costs ASAP.
Demonstrate fair price has been agreed rather than agree contractor price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why would you avoid agreeing costs quickly?

A

Once a variation has been instructed the contract is formally varied.
By taking time you can fully understand what changes are required and interrogate the costs to ensure they in line with the market.

L2 - UPS - Level Change - Inital rates were inflated - I aligned with CSA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is it good practice to include a cost for a potential variation even with limited information?

A

If a variation is likely to occur then it is better to attribute a cost as soon as possible making sure the assumption is based on limited information.

Further information should be sought to increase the accuracy of the cost working towards formal instruction

Inform the client ASAP rather than spring costs at the last minute - better to start high and work down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What should a financial report consist of?

A
Contract sum
Variations - outlining changes within the period
anticipated change
prov sum expenditure
claims
cash flow (anticipated vs actual)
contingency
risks and opportunities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why is it important to establish an accurate valuation of the works on an ongoing basis?

A

If the contractor became insolvent then fund over above the value of the measured works would be at risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is cost control?

How might this help the client

A
  1. Having clear processes for proposing and agreeing changes.
  2. Clearly communicating changes in a cost report to present to the client
  3. Help with instructed change i.e. does it fall within the budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Provide an example of a provisional sum that was included on UPS?

A

Tea Points/kitchens as location/layouts were not complete at time of contract but were agreed post contract.

Once fully detailed the MC provided SC costs plus their OHP

Prov Sum figure £35k was ommitted and replaced with new figure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How did you advise the client when the contractor approached the client to agree the final account early?

A

I advised that agreeing a final account figure early would likely be in the contractors favour as costs hadn’t been agreed as information from the contractor was still outstanding.
By spending more time scrutinizing costs submitted by the contractor, the cost were likely to decrease over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Could there be any issues (other than commercial) with agreeing the final account early?

A

There would likely be issues in clarifying what would be included which again would only prove to complicate the process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How did you prepare the final account?

A

Agreement all of the outstanding financial matters of the projects including:
variations
loss and expense claims
provisional sums

  1. Reviewed the outstanding variations
  2. Split into our cost vs contractor cost
    e. g. £100k vs £150k
  3. Discussed with client that worse case figure compared to where I believed the figure should be
  4. Agreed a figure acceptable to client (Happy to split at £125k
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What made agreeing the final account easier?

A

Financial reports as they identified all the changes that had arisen on the project.
Whilst negotiation continued on the final account, the process was made easier by knowing what had been agreed as well as what hadn’t.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How did you manage the final account process with the client? Were they involved?

A

The client had to be involved as they needed to indicate what figure would be acceptable for agreeing the works.

I identified the estimated final account and identified the amount which was yet to be agreed and what AECOM’s assessments outlined.

The client identified a figure in the middle of the contractor’s final account and the AECOM final account that would be acceptable to them.

This provided a clear aim to achieve on behalf of the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How were the M&E works managed on UPS?

A

M&E was reviewed by a specialist QS who commented on the report submitted by the contractor. Following on from this negotiation took place over a period of time with reviews of drawings and quotations to agree costs.

L2 - What M&E was used. Why were there variations?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Why is project financial reporting important?

A

Illustrate what the current financial liability of the project is.
By informing the client of the cost implications of changes to the contract aids them in being able to manage these within the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How can you control costs on a project?

A
  • Change control Process
  • Management of prov sums (dates for instruction, design lead in time)
  • Monthly cost reporting / rolling final account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

How can financial control help project performance / understanding?

A

Identifies who is responsible for risk / change
Client understands making changes can increase project costs
Clarifies which party is responsible for rather than argue at the end when it is difficult to remember details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How can financial reporting help project performance / understanding?

A

Communicates to client how risk has been apportioned

Used as basis for ongoing negotiation with contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  1. What are contract mechanisms for change?
A

Formal change request managed by CA
e.g. Level issue on UPS – build up of ramp to door
or level issue on Wrexham
1. Description of change
2. Responsible – design issue, changed by client, contractor
3. Cost and time implications
4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

How would you implement contract change for D&B?

A

Wrexham – Mezzanine floor – Client wished to add floor over GF
Change from ER’s; Design, Quality or Quantity or Imposition (site access, working hours, reduced working area)
Employer makes EA aware – Instruction/EAI (if immediate) or Estimate – Employer Proceed? – Change Proposal to Contractor – Contractor Price – Accepted or Negotiated
Instruction by EA – Contractor confirms within 7 days – takes effect from 7 days of confirmation
If Contractor does not comply Employer/EA can give notice – 7 days post notice 3rd party can be appointed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is risk allocation?

A

D&B Contractor hold risk for design

Traditional Client holds risk for design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Who holds the risk for a traditional contract?

A

e.g. UPS Level had been incorrectly designed meaning a ramp had to be built up to an entrance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Who holds the risk on a design and build contract?

A

e.g. Wrexham – Side access had to have gabion walls for level difference – Contractor responsible for adequacy of Design

34
Q

Who holds the risk on a construction management contract?

A

Client holds risk

35
Q

How can construction costs be reported to clients?

A
Cost report; 
Contract Sum, 
Variations:
agreed, 
under negotiation 
potential/risk
Provisional Sum Expenditure
Claims
Actual and Anticipated Cashflow
risk and opportunities.
36
Q

How can costs be forecasted on a project?

A

Financial report inc. rolling final account – agreed – negotiation – risk potential
Agreed = instructed
Negotiated = Quantity, Rates to be agreed (Use higher figure)
Risk = Identifying design issue prior to communication with parties e.g. level difference

37
Q

Why are risk allowances used on projects?

A

Identify aspects that are unknown

e.g. Ground adequacy – Client change – Design adequacy

38
Q

How do risk allowances ensure project costs are controlled?

A

Define aspects of the project which may require further costs

39
Q

How would you communicate risk allowances to a client over the course of a project?

A

Financial reporting

40
Q

How did you prepare the financial report every month on UPS?

A
Financial report; 
Contract Sum, 
Variations 
agreed
under negotiation
potential/risk
Provisional Sum Expenditure
Claims
Actual and Anticipated Cashflow
risk and opportunities.
41
Q

How did you communicate the financial report to the client?

A

Sent via email. Identified changes in the month. New risks. Variations agreed.

42
Q

Example of a variation?

A

UPS level difference

43
Q

Example of a defined provisional sum?

A

Kitchen layouts to be confirmed

44
Q

Example of an undefined provisional sum?

A

Petrol tanks

45
Q

Example of a claim?

A

EoT UPS - HV cable

L&E UPS

46
Q

Who held the risk on UPS?

A

Contractor – Programme
Client - Design
Employer CHange - 5%
Construction - 5%

47
Q

Was there a risk allowance? Who held it?

A

The client managed any risk allowances directly.
5% EMployer Change
5% Construction

48
Q

Give an example of where you effectively managed risk?

A

As the project was progressing I reviewed the remaining prov sum which outlined that kitchen designs had to be finalised in order for the contractor to order thecomponents. I raised this with the client to ensure the design progressed in line with the contrcators deadline to avoid any delays or claims from the contractor.

49
Q

What were the key risks on the UPS project?

A

Procurement of the LV caused project delay

Client change caused delay and cost

50
Q

What the financial implications of the risk (UPS)?

A

LV – EoT and L&E for prolongation of prelims

51
Q

Why did you find the UPS project to be more involved (OO vs Com. Client)

A

Lots of change from client

Commerical client – little change post contract

52
Q

Why did the contractor need to submit a recovery programme (carehome)?

A

Works had become delay and the client was keen to recover the loss. Recovery programme illustrated the contractors plan to recover the time

53
Q

How did you identify if their recovery programme was realistic?

A

IN the coming months I reviewed the revised cashflow forecast vs actual progress. Trajectory of the actual expenditure indicated when they would likely complete on the basis of current thei rate of progress

54
Q

What did you advise the client?

A

Whilst progress had improved the trajectory of their progress illustrated that they would likely finish 8 weeks post contractual completion.

55
Q

When have you managed a provisional sum? What was it?

Why was it a provision sum?

A

UPS kitchens
There were to be 5 kitchens over the warehouse/offices but the design had not been completed. Including it as a prov sum allowed for its likely expenditure subject to exact/design/ayout

£10k x 5 = £50k

56
Q

How did you manage its expenditure?

A

Upon receipt of the actual design this provided to the contractor. The cost was agreed. I omitted the prov sum and replaced it with the actual cost.

57
Q

How have you managed a risk allowance?

A

Same as provisional sum – develop as more information is provided.

58
Q

What was the change protocol on UPS?

A
Change reported to CA 
CA advises QS
QS reviews issue
INstruct Designer
QS cost - negotiate with MC
Once agreed CA issues instruction
59
Q

How would change control differ from traditional vs D&B?

A

Traditional client responsible for design team
Client has double interface with DT and MC

D&B - Main Contractor in control of design team
Loss of control for client

60
Q

Why did you think it was best to wait to the end of the project to agree the final account?

A

Many outstanding variations – contractor was suggesting a deal was agreed based on lots of uncertain costs.

I suggested more time should be spent on agreeing variations.

61
Q

How did you approach the negotiation of the final account?

A

The use of my monthly financial report was key. Say Contract Sum £8m

I identified the contractor cost vs mycost.
E.g. Contractor £11m vs my costs £9m

Clients confirmed they would accept £10m

We agreed 50% of the costs that hadn’t been agreed.

62
Q

How did you keep up to date with project costs?

What risks were there on UPS?

A
  1. Contact with CA who was in dialogue with all parties.

2. Issues on site that could arise as a risk

63
Q

What was the CA’s role?

A

Administer the contract. Issue instructions

64
Q

What was the Design team’s role?

A

Make amendments to the design as required by client

65
Q

Was there a clark of works?

A

Check works arebeing constructed in accordance with the contract / design

66
Q

How would you create a cash flow forecast?

A

Inputted the contract value and attributed this over the length of the progreamme creating an s curve

67
Q

Why would you use one?

A

Indicates the likely monthly expenditure on the project.

68
Q

Did you have value change on UPS?

A

Level change example

69
Q

Value change for dayworks?

A

Urban Splash – obstructions

Dayworks sheet outlining works required to complete work with OH&P

70
Q

What is a prime cost sum and why would you use one?

A

Allowance for material only with other costs being included – e.g. tiling. Cost of tile is unknown but labour, OHP are accounted for. Gives accurate indication of cost subject to confirmation of exact material to firm up cost.

71
Q

How would you carry out an interim valuation?

A
  • Review contractor application
  • Attend site to review progress, taking photos
  • Review actual progress vs application
  • Discuss with contractor
  • Issue payment recommendation to CA
72
Q

Give an example of when you have implemented value engineering?

A

Retail project – reduced floor to ceiling height

73
Q

Give an example fo when you have had to asses an EoT claim?

A

UPS

74
Q

Give an example fo when you have had to asses an EoT claim?

A

UPS

75
Q

L&E claim example?

A

UPS

76
Q

When could you be entitled to an EoT claim but not an L*E claim?

A

TBC

77
Q

What are the Relevant Events?

A

time)– Change (scope, quality etc),
Instruction (early use),
Deferment of Possession (start 2 weeks later),
Antiquities (archaeology discovered), Suspension (Coronavirus),
Act or Omission (UPS HV power),
Statutory undertakers (services),
Weather (slows/stops work),
Loss/damage by a specified peril (civil commotion, riot, fire, lighting, explosion), terrorism, strike, statutory powers, approval delay (e.g. noted in change request response to client),
force majeure (Coronavirus) (14)

78
Q

What are Relevant Matters?

A

Change (to existing completed work), Instruction (early use – disruption), Deferment of possession, act or omission.

79
Q

Give an example of when you have had to authenticate costs?

A

TBC

80
Q

How have you used risk management?

A

TBC