Design Economics & Cost Planning Flashcards
Net and Gross Areas
Net Area – Sale or lettable area
Gross Area – Circulation, Plant, Entrance, Toilets (communal), Gym
Data Sources
In House Data / Tender returns
SPONS
BCIS
Composite Elemental Rate
Ground floor slab represents as cumulative £/m2 to include: excavate compaction harcdcore blinding DPM Insulation Concrete
Inflation
Tender Price Index; Cost Plan Date - Tender return date
Construction Price Index; Tender return date - Construction mid-point date
Cost Plan NRM1
0 Facilitating works 1-8 Building Works 9 Preliminaries 10 OH&P WORKS COST ESTIMATE 11 Project Design Team Fee 12 Other Project Costs BASE COST ESTIMATE 13 Risk Allowances COST LIMIT EXC. INFLATION 14 Tender Inflation & Construction Inflation COST LIMIT INC INFLATION
Calculating unit rates from first principles
Tiling 10m2 Labour; 16 hours @ £15ph= £240 Materials; Tiles, grout, adhesive = £300 Total £540 + 5% OHP= £567 / 10= £57/m2
Building Works
1 Substructure
Foundations, Ground Floor Slab, Piling
2 Superstructure
Frame, Roof, Upper Floors, External & Internal Walls, External & Internal Doors,
3 Finishes
Wall, Floor, Ceiling
4 Fittings, Furnishings and Equipment (FFE)
Kitchens, Bathrooms, Furniture
5 Services
Heating, Electrics, Ventilation, Lighting, Waste
6 Prefabricated Buildings
Guard House, bath pods (student resi/budget hotel)
7 Work to Existing Buildings
Support to adjacent buildings
8 External Works
Roads, Paving, Planting, External Services (Utilities), Drainage
Preliminaries
Items that cannot be attributed to a specific element above e.g: Staff welfare temp. services security, safety site records completion requirements cleaning
OH&P
Head office admin
Return on capital investment.
Design Team Fees
PM QS CA/EA Arch M&E C&S CDM
Other Project Costs
Land acquisition finance planning fees oversailing party wall highway adoption section 106 insurances marketing
Design Development Risk
Risks associate with DD:
planning change
tender delays e.g. design novelty (untested)
inadequate/unclear info (site investigation)
use of provisional sums
Construction Risk
Risks associated with: site conditions existing buildings ground conditions existing services statutory delay archaeological remains underground obstructions contaminated ground asbestos site access
Employer Change Risk
Design and scope change during design and construction: scope creep quality increase increased time change of existing work when onsite
Employer Other Risk
Acceleration
postponement
funding issues
Typical Cost Plan Exclusion
VAT Land acquisition Professional fees insurances finance costs Planning costs S106
New Rules of Measurement Series
NRM
1; Order of cost estimating and Cost Planning
2; Detailed measurement for building works
3; Building maintenance works
RIBA Stages & Costing Approach
0 Strategic
Identify Client requirements, feasibility (budget and risks)
Cost Model (£/m2)
1 Preparation
Project brief & outcomes, quality aspirations, further feasibility, site info and surveys, programme, project execution plan Order of Cost Estimate
2 Concept - Arch concept design, outline specification
Formal Cost Plan 1
3 Spatial - Developed design and costing
Formal Cost Plan 2
4 Technical - Developed arc, eng, civil design, building systems
PTE
5 Construction
6 Handover
7 In Use
Cost Plan Delivery
Standard format comp checked peer review emailed inc letter phone call review meeting
Technical Design Detail Stage 4
Building services (electric, heating, waste etc) detailed foundation
Cost Planning Purpose
Feasibility - Proceed?
Facilitate Design Choice
Cost management (Budget limit each element)
Cost Plan Contents
Executive Summary Cost Reconciliation Elemental Summary Elemental Breakdown Basis/Assumptions/Exclusions Inflation Statement
Meole Brace - Cost Plan Overview Overall cost inc £/m2 Site Costs Site infrastructure Programme On Costs
£1620/m2 - £4.3m Site Wide Costs; £1.4m £7m OVERALL 12-month programme 12% prelims 5% OHP
Value Engineering vs Value Management
VE - Process that seeks to deliver the same requirements but at a lower cost.
VM - Clearly communicates the clients requirements by identifying what is a need and what is a want and aligning these with the budget. Needs first wants second.
VE Example
Façade Glazed Elements – Omit Glazed walling; curtain walling; unitised – (£900m2) E/O for stone banding; pre-cast concrete panels; reconstituted stone faced (£800m2)) ADD Double storey glazed units set in pre-cast concrete (acid etch finish) vertical / horizontal framing £650 = £1m saving (2700m2)
Windows - Omit Anodised aluminium framed (£700) – ADD PPC aluminium framed £450 = £200k (1260m2)
Juliet Balconies – Omit – Juliet Balconies £2000 ADD – Windows with top hung opening vents £1000 = £400k saving
Glazing to staircore
Kings Tower Cost Overview GIA NIA Net to gross Units Floors
£31m - £2100/m2
15k (GIA) 11k (NIA) Net to gross = 75%
Units 195
Floors = 36 inc. mezz. and basement
Building Height Increase Implications
More expensive due to:
Foundation capacity increases
M&E more complex
firefighting lifts & pressurised water for firefighting
resistance to wind (material quality increase)
working at height (cranes and difficulty of moving/storing materials)
adding several floors may require larger lifts and reception/circulation areas (reduces net/gross).
- How should cost planning be approached under NRM1?
Facilitating works, Building Works, Preliminaries, OH&P - WORKS COST ESTIMATE
Project Design Team Fee, Other Project Costs
BASE COST ESTIMATE - Design Development Risk, Construction Risk, Employer Change risk, Employer other risk
COST LIMIT EXC. INFLATION - Tender Inflation, Construction Inflation
COST LIMIT INC INFLATION
- What is the basis?
Drawings, specifications, surveys, email
- Assumptions?
e.g. type of frame, external wall build up, floor type, ground strength
- Exclusions?
VAT, Land acquisition, Land remediation tax relief, Professional fees, insurances, finance costs
- What is design economics?
Assesses the cost efficiency of the design
- What is the wall to floor ratio?
Compares the quantity of wall to floor. Floor is the key metric in identifying the size of a building. The less wall relative to floorspace makes the building more efficient.
- What could be a negative impact of having a very good wall to floor ratio?
If the building was too “efficient” i.e. it had little wall area relative to the floor area it might lack in natural light.
- What building types might this be an issue for and not?
This might be an issue for office space i.e. many desks would be far away from windows which would be less desirable.
For a warehouse this would might not be an issue
- What is the net to gross ratio?
Net Area – Sale or lettable area Gross Area – Circulation, Plant, Entrance, Toilets (communal), Gym
- What is site density?
Proportion of a site that is occupied by buildings. For example, a high-rise office in a city centre location would have a high site density as relative to the plot size there is a high gross floor area. At the other end of the spectrum a warehouse would have a lower site density with the building taking up typically 40% of the site with the service yard and car park taking up the rest of the site area.
- How does cost planning aid in financial control as design develops?
As the design changes cost planning enables an understanding of the associated cost implications.
- What are the RIBA cost planning stages?
RIBA stages -
0; Strategic
1; Preparation
2; Concept
3; Spatial
4; Technical
5; Construction
6; Handover
7; In-use.
0 Strategic - Identify Client requirements, feasibility (budget and risks) Cost Model (£/m2)
1 Preparation - Project brief & outcomes, quality aspirations, further feasibility, site info and surveys, programme, project execution plan Order of Cost Estimate
2 Concept - Arch concept design, outline specification Formal Cost Plan 1
3 Spatial - Developed design and costing Formal Cost Plan 2
4 Technical - Developed arc, eng, civil design, building systems PTE
5 Construction
6 Handover
7 In Use
- Why would a traditional procurement cost plan vary to a D&B cost plan? (at tender stage)
Traditional procurement route fully develops the design to stage 4. D&B is typically developed to stage 3/4 so is less detailed.
- How would you use internal cost data?
Internal cost data can be used to inform the cost of similar schemes at early stages.
- What is SPONS?
Wide range of construction cost data; sector cost models, material & labour cost