Procurement & Tendering (based on Summary of Experience) Flashcards
What is traditional procurement? Pros and Cons
- Fully developing the design prior to tendering to a main contractor.
- Client retains design team as well as the risk of the design.
Ads:
•Retains control of the design/quality
•Most economical at tender stage (contractor is provided with full outline of client requirements)
•Quicker than D&B for tender review as scope of work is clear and can easily be compared.
Dis:
•Long program duration (long pre-contract period)
•No engagement with contractor on the design (design and construction are separate)
•Dual point of contact for the client; contractor and design team
•Client retain risk for the design (cost certainty depends on design adequacy)
Contracts:
JCT minor building contract
Intermediate BC
Standard BC with / without Quantities
What is D&B? Pros and Cons? Novation
- Client Develops Design typically to Stage 3
- Employer’s Requirements details how remaining aspects of design should be developed.
- The Contractor takes over the design (remaining) and build it with their own (or novated) design team.
Ads:
•Cost certainty – design risk is passed to the Contractor
•Single point responsibility for design and construction
•Quicker start on site than traditional (design doesn’t have to be fully developed for tender)
Dis:
•Slower tender analysis compared to traditional
•Harder to compare tender’s dependent on the degree to which the design has been developed
•Contractor is prone to look at ways to reduce costs for the ER proposals – issues with quality dependent on design and ER’s
•Less competition at tender so higher pricing (compared to traditional where the design is fully developed). (Typical number of contractors at tender -Traditional; 5/6, D&B 3/4)
Novation?
A contract which transfers the rights and obligations of one contractual party to a new third party
i.e. design rights and obligations of architect transferred from the client to the contractor.
What is Construction Management? Pros and Cons? What does the CM do?
- Similar to MC but key difference is the Client will enter into Contracts with trade Contractors directly
- Client coordinates trades with their own in-house team - e.g. House builders undertaking similar type of works (i.e. repetitive with low risk designs)
Ads - Economic (existing trade contract relationships)
- Control program
Dis:
Risk of trade performance
Hold programme risk
CM Does:
- Similar to MC but key difference is the Client will enter into Contracts with trade Contractors directly
- Client coordinates trades with their own in-house team - e.g. House builders undertaking similar type of works (i.e. repetitive with low risk designs)
What is Management Contracting? Pros and Cons
- Management Contractor appointed on a fixed management fee (usually a percentage based of the prime cost of the project)
- Early to advise on design, programming & buildability.
- Programme, package and obtain tenders for the works.
- Trade Contractors are in Contract with the Management Contractor.
- Typically associated with complex (untested design) and/or high value projects that may be perceived as too risky for a sole main contractor
Ads:
•Quick program as design and construction overlaps
•MC technical input alongside design
•Flexibility in making changes to the design before trade packages are let (unlike a lump sum contract)
Dis:
•High level of cost uncertainty until all the packages are let
•Little incentive for MC to reduce costs
Contracts:
JCT Management Contract
JCT Trade Contract agreements
How is MC appointed?
- Client appoints MC
- MC develops programme
- MC directs design
- MC selects the trade contractors through competitive tender (direct contractual relationship).
What is single stage tendering? Pros and Cons
Single:
Cost is agreed prior to entering into contract
What is two stage tendering? Pros and Cons
Two Stage:
No cost certainty and increased pre contract costs
Separates process of selecting a contractor and determining a price for works.
First stage; quality of team, prelims price, OHP.
Second stage; PCSA to complete design as consultant. Trade contractors make up contract price
What is important to do prior to entering into a two stage tender with a contractor?
Define the process for either party withdrawing should negotiations lead to abortment.
It should be agreed what payments should become due
What is a negotiated tender route? Pros and Cons? Key downside?
a. Negotiation is where a suitable contractor is identified, and the contract sum is negotiated directly
a. If client has previously engaged with a contractor and believes they are suited to the project, subject to price. For example, they may have recently completed on a very similar project with the client and a good relationship has been established.
b. Client trusts contractor (no competition once selected) also trusts that QS can provide assessment on costs with no other contractors to review against.
What is serial tendering? Pros and Cons
a. Similar work that is required on an ongoing basis such as re-surfacing road or large estates (e.g. universities) that require ongoing maintenance and repairs
What is a tender analysis?
Checking for errors - not included items or including as provisional when should be firm
Raising tender queries
Equalisation/normalisation
Why is it important to analyse tenders impartially? (e.g. Local Authority)
As projects are publicly funded special consideration should be given to ensure tender awards can not be accused of allowing collusion
Ultimately the process should seek to achieve best value and this should be able to be clearly demonstrated
When should OJEU be adopted and what is it’s purpose?
Official Journal of the European Union.
In essence it is a website which promotes public contracts that have to be tendered through the OJEU process
£4.7m+ work contracts
What are the two ways in dealing with tender errors as outlined in the JCT Practice note? Pros and cons.
This was stipulated in the tender instructions.
For JCT alternative 1 allows the contractor either to confirm the error or withdraw their tender.
Alternative 2 allows the contractor to confirm, amend or withdraw.
Alternative 1 does not allow the contractor to amend their submission which could be considered to be inflexible.
An alternative perspective could be that given the formality of the process, an error should not be made given that a significant amount of time should be put into the process including internal reviews of the submission.
Why was a traditional procurement route appropriate on the UPS distribution centre?
The Client was an owner occupier who was undertaking a new approach within their business in the way the parcels were organised over the space.
UPS had design input from variou departments which internally created a confused decision making process.
The client held the design control and was able to discuss changes directly with the design team
What was important to UPS in terms of cost, quality and time?
Quality - This was the most important as the client wished to hold control of the design team
Cost - This was secondary to quality
Programme - There was a deadline but again, time was secondary to achieving the exact design
What sort of changes was the client making?
- Extension to existing unit
2. Additional office space
What is the benefit of traditional vs D&B in terms of implementing post contract design changes?
Traditional - the design team is employed directly by the client and with D&B the contractor employs them.
Why was the CM route adopted on the housing scheme? (Heyford?)
Quick start
Design flexibility
Client control of quality and programme
Although there is little cost certainty the client benefits from cost saving from procuring the trade packages directly
Why wasn’t say D&B adopted?
Re-tendering over phases would have been inefficient i.e.
Client loses client control over construction and design
e.g. Material procurement issues meant that the client could be more flexible without having to make instructions via a Main Contractor
Why wasn’t say traditional adopted? Meole Brace
Design would have to be fully developed prior to tendering (slow)
Why wasn’t say MC adopted?
As a housebuilding company the client had “in house” expertise i.e. site managers, Commercial managers so Construction Managment enabled them to get directly into contract with trade contractors.
Appointing an MC would have been unnecessary as they did not require external expertise and the appointment process would have been slower
Why did the client type suit the CM approach?
The client was a housebuilder
- In house expertise
- Direct control of trade packages
What would you of recommended if the client was inexperienced or only an occasional developer?
MC - Benefit from expertise and flexibility in design change and quick start
Slower than CM and MC not incentives to reduce costs
Why did the extent and repetitive design of the scheme impact on the procurement route?
The client being experienced was the primary driver for using a CM route and as the design was repetitive as opposed to being complex the client was comfortable with taking on the design risk.
Why did you use a single stage tendering rather than two stage on the demolition project?
The client wanted cost certainty prior to entering into contract. Two stage could have quickened the programme but there would not be cost certainty.
Loss of competition would make it difficult to establish that value for money was being achieved.
Why did you use an open tender? How was it implemented?
Whilst the tender was not subject to OJEU (less than £5.3m) it was still a requirement to adopt an open tender.
Open tendering removes selection bias, allowing any contractor to be considered.
The client posted the tender opportunity on the OJEU website inviting contractors to take the PQQ for consideration.