Contract Administration Flashcards
- What are the standard contract forms and when might each be appropriate?
Lump Sum – Building where design is complete
Measured – Infrastructure work or ongoing work where the scope is known but not quantity
Cost Reimbursable – Early start required e.g. emergency works
Design and Build – Partial design where contractor takes over responsibility
Management – Trade packages are managed directly (no MC) – early start
- What obligations does the quantity surveyor have under D&B?
Only EA (no QS role D&B) Undertake valuations L&E Final Account Value variations
- What obligations does a CA/EA have?
Only EA D&B Chair meetings Instructions EoT Issue Certificates Certify Completion
- What is the difference between CA & EA?
CA – SBC EA – D&B
EA typically also undertakes QS duties but this is not assumed contractually i.e. could be different party but no formal QS role under D&B
- Why is it important to take meeting minutes?
Clearly outlines key discussion; agreements or issues, actions by when and by who
- What is the order of a typical progress meeting?
Intro’s actions from previous contractor report progress & issues change future meetings
- What certificates might be issued and why?
Completion certificate – ensure time is not at large
Interim valuation certificate – Confirm agreed valuation between EA and MC
- What is the RfP/valuation?
Gross valuation, less retention, less previous payments.
Agreed with the contractor and issued as “RfP” to the client (only “advice”) by EA/CA.
- What are the implications of completion?
Implications; Rectification period begins - Half retention released - Client insures - LDs are not applicable
Employer must accept building early if it is actually complete
- What impact does the Local Development Economic Co Act impose on a contract?
- Payment notice must be issued 5 days after due date
- If no payment notice after 5 days, then contractor can issue their own
- Pay less notice must be issued if employer is to pay less than the the notice
- Entitled to Adjudication
- What were your duties on the EA contract?
Take meeting minutes
Issue Instructions
Issue Certificates
Certify Completion
- Was there not a QS on the project?
I undertook QS duties as well
- What change requests did you receive? Park
Re-fitting of guttering pipes to adjacent delipated building as water was seaping onto the site and not into drain
- What was included in your change request form?
Outline of works inc. rates & quantity#
Any impact on programme . date for instructions
- Give an example of when you priced a variation?
UPS steps
- How long does a contractor have to respond to a variation request?cD&B
D&B 14 days of instruction
Employer has 10 days to instruct
Contractor can object e.g. H&S issue
Employer pays for design work if not instructed
- Does the time change for a contractor to respond to a variation request on SBC differ?
21 days SBC (14 days D&B)
Employer 7 days to instruct (10 D&B)
- What happens if they do not respond or refuse?
The employer can employ someone else to undertake the work:
- Employer must give written notice to comply
- 7 days must elapse after this notice to commence works
- What did you issue when the contractor failed to achieve the completion date and why did you do this?
Non- completion notice – ensure time was not at large to allow the client to issue LD’s if needed
- What was stated in the non completion notice?
States that on the date of the contract completion the works was had not satisfied the completion requirements
- There was a dispute between the client and the contractor as progress was slow and the contract completion date had passed? How did you deal with the issue?
I considered both parties perspectives:
Contractor representative was faced with a difficult situation as it was clear he was not being provided with sufficient resource to complete project
Client – Had not issued LD’s and had aided the MC with the project but was not seeing much improvement
- I suggested that parties work together on a completion countdown programme to completion that could be agreed.
- If works continued to not progress then further action would have to be considered.
How does D&B differ to SBC contractually?
Contractor responsible for design No listed subcontractors, No architect/CA/QS (EA only), No clerk of works, No payment certification – contractor applies and employer decides how much
Roles/Responsibilities of: Client COntractor QS CA EA
Client - Pay, Possession, Insure, Not obstruct, Pay Less if does not agree/LDs
Contractors – Complete Work & Design, Comply, Inform EA of discrepancies
QS – Only EA (no QS role D&B), Undertake valuations, Confidential, L&E, Final Account, Value variations
CA – Only EA D&B), Chair meetings, Inspect work, Instructions, EoT, Issue Certificates, Certify Completion
EA – As CA but for D&B, typically QS but contractually is assumed as different party
Contractors Estimate - D&B process?
- Contractor must provide a quotation within 14 days of the instruction (SBC 21)
- Employer then has 10 days to accept the quotation or withdraw instruction (7 days SBC)
- Contractor can object on reasonable grounds within 10 days of instruction
- Employer will pay for specific design work required to produce the estimate if rejected
Employer Liability;
Required by all firms employing staff, Pays out if employee is injured or ill
Public Liability;
Covers injury or death to public, also covers loss or damage to 3rd parties