PROJECT FINANCE Flashcards

1
Q

Why do you think project financial control and reporting is important?

A

It is key to a projects financial success.
It’s important to keep the client up to date with expenditure/any additional costs within the project as well as making sure yourself and the team are aware of changes or potential costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is change control?

A

A process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do you include within a cost report?

A

I would expect to see the contract sum included alongside instructed variation, early warnings and expenditure of provisional sums.
I also include a cash flow in my cost plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

You mention a standard change control procedure, can you talk me through this?

A

CRF (Change Request Form)
Review of CRF by EA and Client team
EA issues instruction if approved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a final account

A

Final Statement that settles all outstanding costs of a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is construction cashflow usually a S-Curve?

A

Follows the payment procedures, valuation of works after a month
Slow expenditure at the beginning then picks up when substructure is complete and superstructure is constructed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What might a cashflow falling behind imply?

A

Delay

Problems on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens at Practical Completion?

A
  1. Half of the retention is released
  2. LD’s can no longer be levied
  3. Insurance responsibility transfers to the Employer
  4. rectification period starts
  5. H&S file is passed over to Employer
  6. Possession
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the final account procedure in the D&B contract?

A
  1. Contractor submits final statement following award of PC
    (If FS not received within 3 months, employer can give notice that Contractor must submit FS within 2 months or Employer can submit FS)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is included in a Final Account?

A

Final Statement of contract sum and the variance (If there is one)
Schedule of instructions with costs
Schedule of previous interim payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is work valued after PC?

A

On a monthly basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is the due date for Final Payment?

A

One month after the following (Whichever occurs last):

  1. End of rectification period
  2. Date stated in notice of completion of making good
  3. Date of issue of final statement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does a QS cost control in the Pre Construction Phase?

A

Outline budget updates in cost plans and cost reconciliations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is a provisional sum expended?

A

Contractor quotation
recommendation
instruction to proceed
PS omitted and new cost added to CS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What should you consider with regards to time in a cost report?

A

Should track time and if there is a delay if the the differing parties are entitled to:

  1. Contractor - EoT
  2. Employer - LDs

Should be an advanced warning in cost report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are prolongation costs?

A

Additional costs due to a delay that was caused by another party.
Typically these are:
time related resources such as site management, site accommodation and key items of plant and machinery.

17
Q

What would you say to a Contractor that had fallen behind on programme?

A
  • Understand why
  • Identify to the client that if they fail to proceed “regularly and diligently” it could be grounds for terminations
  • Ask for a recovery programme
    Pro-rata prelims payments based on level of work complete rather than weeks complete