PROJECT FINANCE Flashcards
Why do you think project financial control and reporting is important?
It is key to a projects financial success.
It’s important to keep the client up to date with expenditure/any additional costs within the project as well as making sure yourself and the team are aware of changes or potential costs.
What is change control?
A process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed.
What do you include within a cost report?
I would expect to see the contract sum included alongside instructed variation, early warnings and expenditure of provisional sums.
I also include a cash flow in my cost plans.
You mention a standard change control procedure, can you talk me through this?
CRF (Change Request Form)
Review of CRF by EA and Client team
EA issues instruction if approved
What is a final account
Final Statement that settles all outstanding costs of a construction project
Why is construction cashflow usually a S-Curve?
Follows the payment procedures, valuation of works after a month
Slow expenditure at the beginning then picks up when substructure is complete and superstructure is constructed
What might a cashflow falling behind imply?
Delay
Problems on site
What happens at Practical Completion?
- Half of the retention is released
- LD’s can no longer be levied
- Insurance responsibility transfers to the Employer
- rectification period starts
- H&S file is passed over to Employer
- Possession
What is the final account procedure in the D&B contract?
- Contractor submits final statement following award of PC
(If FS not received within 3 months, employer can give notice that Contractor must submit FS within 2 months or Employer can submit FS)
What is included in a Final Account?
Final Statement of contract sum and the variance (If there is one)
Schedule of instructions with costs
Schedule of previous interim payments
When is work valued after PC?
On a monthly basis
When is the due date for Final Payment?
One month after the following (Whichever occurs last):
- End of rectification period
- Date stated in notice of completion of making good
- Date of issue of final statement
How does a QS cost control in the Pre Construction Phase?
Outline budget updates in cost plans and cost reconciliations
How is a provisional sum expended?
Contractor quotation
recommendation
instruction to proceed
PS omitted and new cost added to CS
What should you consider with regards to time in a cost report?
Should track time and if there is a delay if the the differing parties are entitled to:
- Contractor - EoT
- Employer - LDs
Should be an advanced warning in cost report