PROCUREMENT & TENDERING Flashcards
What are the advantages and disadvantages of single stage tendering?
Advantages:
- Maintains competition throughout the process.
- Can reduce the cost of the overall construction.
Disadvantages:
- Doesn’t enable early contractor involvement.
- Dependent on the market – contractors may be more keen on two stages.
What are the advantages and disadvantages of two stage tendering?
Advantages:
- Enables early contractor involvement.
- Encourages collaboration.
- Contractor can help identify and manage risks.
Disadvantages:
- Additional fees involved with the PCSA.
- Contractor gains leverage as they continue to second stage – reduced competitiveness.
- Potential that parties may not agree to contract sum – leads to additional costs to retender.
How do you evaluate tender returns and how do you then make your recommendation to the client?
- Tender Evaluation:
o Tender opening.
o Tender returns checked for compliance with the invitation to tender.
o Arithmetical checks carried out on cost components.
o Any non-compliant tenders treated in accordance with the conditions outlined in the
Invitation to Tender.
o All tenders aligned on a like for like basis and compared with each other and the pre-tender estimate.
o Analysis undertaken of resource levels committed by each contractor and on the merits of the team proposed.
o Post-tender interviews carried out with short listed tenderers.
o Tenders scored against the pre-determined selection criteria. - Tender Recommendation Report:
Prepared and presented to client, including:
o Tender history.
o Summary of tender returns.
o Aligned tenders.
o Scoring of tenders against technical and commercial criteria.
o Recommendation on what tender represents overall best value for money.
o Outline of future actions and contracting approach.
What is a letter of intent?
- Expression of intention to enter into a contract at a future date.
- Does not create a contractual relationship (it is not an agreement to agree).
What are the dangers of using an LOI?
- They do not cover all eventualities set out in a buildings contract (e.g. Ampleforth v T&T – Client not entitled to LDs and T&T found negligent for failing to warn them of the risks of not getting into contract).
- Allow the contractor a position of back negotiation from a position of strength.
- May act as a disincentive to execute the formal contract.
Benefits of Traditional Route?
- Control of design
- Cost certainty at point of tender
- Competitively Tendered
- Priced BoQ allows for easy assessment of interim valuations & variations
Disadvantages of Traditional Route?
- No Contractor engagement in Design
- Separation of Design team and Contractor can lead to adversarial atmosphere
- Client bares risk of design not being completed
- Client must finish the technical design before tender
Advantages of D&B?
- Contractor’s input on Design and Buildability
- Overlap of Design & Construction phase (Early mobilisation)
- Single point responsibility - risk allocation on the Contractor
Disadvantages of D&B?
- Client does not have control of Design
- Client’s ERs need to be defined earlier
- CPs must be reviewed and agreed (CPs have precedence over ERs
Cost implications of two stage tendering?
- Can be more expensive with the additional PCSA costs & Design fees
(Contractor’s buildability input can reduce likelihood of post-contract change)
Name a key risk on a D&B project?
CP’s take precedence to ER’s
How do you ensure quality on a D&B project?
- Detailed ER’s
- Novated Design team
- Take the level of design by Design team to adequate level before entering into D&B Contract
- Key Performance Indicators
What do the ER’s usually include?
- Site Details
- Project Info / Design Info
- Specifications
- Design Submission Requirements
- Prov sums
- Planning restraints
- Form of contract
- Method of presentation of CP’s
What are the different types of LOI?
- Comfort - Intention to act in a certain way (No contractual obligation)
- Consent to Spent - Works to proceed up to a certain value (Legally binding)
- Recognition of contract
What do you need in place for a Letter of Intent?
Parties Agreement
Contract form / amendments
Intended Contract sum
Limitation of Liability
Procedures (refer to Contract - Payment , dispute, termination)
Confirmation that LOI will terminate on execution of Main Contract