Project Finance Flashcards

1
Q

What is loss and expense ?

A

A contractors claim for loss and expense at the same time as an extension of time. It is the money required for delay and disruption, inefficient working and/or employing more resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

“What are common heads of loss and expense?

What are common heads of Claims? (HASAN)

A

“1. Additional cost: inflation, additional work, prolongation
2. Site office overhead / Prelims
3. Head office overhead: formulas?
4. Disruption
5. Loss of profit/business opportunity
6. Finance charges”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

“What are the Claims particulars ?

A

“1. Notices, preconditions, timebars, EWN
2. Contractual entitlement
3. Cause and effect
4. Records of costs incurred”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How to avoid claims ?

A

“1. Balanced risk allocation.
2. Enough design info and specs.
3. Good faith and partnering.
4. Right procurment route for level of design maturity.
5. Clear contract documents without ambiguities.
6. Challenge baseline program at earliest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

“Having advised the client and established the change control procedure on Project X, how was this then implemented?

How do you implement change control procedure? (HASAN)

How do you manage Change? (HASAN)”

A

”- Communicate Procedure as narrative and flow chart to the team and explain in a meeting. Include in PEP.
- Change control forms issued to the team.
- Setting regular change control meetings with the team.
- Maintain Register/tracker of change control.
- Ensure adherence to procedure before costing and send to client for approval.
- Ensure full impact of change captured and instruction issued after client signature only.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

“Your final assessment record states that you established the cost reporting protocol on project X. What approach did you take to this?

How to establish cost reporting protocol? (HASAN)”

A

”- Consider Procurement route,
- Report content and format,
- Frequency and timing/cut-off date of issue,
- Distribution list and means of issue,
- Interface with Client Finance team,
- Additional requirements by stakeholders/funders”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

“Key issues to consider when designing change control procedures?

I see from your summary of experience that you advised the client and implemented a change control procedure on your project X. Can you tell me the key issues you considered in advising the client upon the procedure to be adopted?

How do you establish/design change control procedure? (HASAN)”

A

“1. Project procurement route and impact during design and construction
2. identify key decision makers to approve changes
3. Client’s priorities from monitoring change?
4. change control procedure process and forms
5. evaluation and measuring change
6. costs to include in evaluating change, finance, professional fees, vat
7. responsibility and communication matrices for raising changes
8. the contract mechanism to administer the change control management system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

“What measures can be taken to effectively control costs during the construction phase of a project?

Post-contract cost control tools? (Hasan)”

A

“Regular cost reporting which is also forward looking
Proactive risk and contingency management
Implementing a robust change control process
Management of provisional sums within budget
Final Account”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is RIBA Plan of Work stages? (2013), for 2020 change developed design by spatial coordination

A

“Stage 00 – Strategic Definition
Stage 01 – Preparation and Brief
Stage 02 – Concept Design
Stage 03 – Developed Design
Stage 04 – Technical Design
Stage 05 – Construction
Stage 06 – Handover and Close Out
Stage 07 – In Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Cost control? and Procedures you undertake to cost control?

A

“Process of controlling costs of activity, process or company. includes procedures to:
1) detect variance between budgeted and actual cost.
2) detect cause of cost variance.
3) Corrective measure to re-align actual cost with budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the cost control tools?

A

“Pre-Contract: Cost Plan, PTE
Post-Contract:
1. Cost Report,
2. Risk Management
3. Provisional Sum
4. Change Control
5. Final Account”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Finance control? What is it about?

A

“Financial management of activities to achieve desired ROI. Involves:
1) Capital investment of project,
2) Professional/legal fees,
3) Finance charges,
4) Lifecycle cost (operation and maintenance).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Finance Control tools?

A

Financial statements (budget, income, balance, cashflow, equity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Monitoring?

A

Proactive continuous monitor of cost impact o: changes and risks, and, items in design, and instructions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Provisional Sum ?

A

“NRM2: Sum of money set aside to carry out work that cannot be described and given in quantified items (in accordance with the tabulated rules of measurement). Types: defined and undefined.
Defined: Nature of work, quantity indicate scope and extent, How and where to be fixed to building, Restrictions/limitations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Impact of defined and undefined provisional sum?

A

Defined PS allow Contractor to Price for PS in time related Preliminaries and allow time in programme. Undefined contractor cannot price for Prelim and allow time in programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

PC Rate/ Prime Cost Sum

A

NRM 2 definition is a sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g. supply only ceramic wall tiles at £36.00/m2) no OHP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

I am client in Fidic RB 99. I want to fix specific floor finish what mechanism allow me to do so in contract?

A

PS, PC, or NSC?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How do you administer the cost during the post contract stage?

A

”* Through cost report.
* Breakdown costs into elements then compare elemental actual cost against budgeted.
* then monitor and report variance, variance root cause, and possible corrective measures/source of fund, address any risk of cost-overrun after projection final contract amount.
* Example- Main works > Tower A, Podium, basement > Tower A Structural/MEP/Finishes > Tower A structural > Masonry, Concrete, Metal > Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is change control management? Variation?

A

“Change control management: method to assess and manage changes in terms of scope, cost, and program to allow the client to make informed decision.
Variation: alternation to scope, size, quantity, quality, dimension of works or sequence of events”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is Cardinal Change? why its important?

A

Major change over and beyond project scope of work. provide relief to contractors in some juridiction from being bound to change instruction not relevant to scope of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Reasons for Variations ?

A

“client instructions, design error/omission, site conditions.
Driven by: technological, VE, cost saving, revised drawing, social, environmental, regulations/legal, aesthetics, unforseen issues”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is BIM? How it benefits Change control management?

A

“BIM: Process for creating and managing information on a construction project across its life cycle.

BIM benefits: Reduce waste and improve efficiency
enable swift assessment of alternative design proposals
Help visualize changes”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

PEP?

A

Project execution plan (PEP): An overarching document that provides the framework to execute, monitor, and assess and control the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Scope creep?

A

unauthorized/controlled changes to project scope without considerations for implications on time, budget, resources, and final deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are change control forms?

A

RFC, ARF, EI, AVI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

“What do you include in RFC document?

Where you have initiated a change yourself, can you tell me the information that you included on the Change
Proposal (RFC) prior to presenting to the client?”

A

”- Change description and reason
- cost impact
- time/program impact ( coordinated with planning )
- functionality/quality impact (coordinated with design team)
- attach relevant drawings and specs
- impact on professional fees
- Source of funding (budget contigency, Provisional Sum, additional fund)
- Date required for approval
- consequence of late approval/rejection
- relevant risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How do you establish/design change control procedure? (HASAN)

A

“1. Procurement route? How it will impact
2. Contract Change Mechanism
3. Process and forms
4. Client priorities
5. Key decision makers, approvers
6. Responsibility and communication matrices
7. Costs to include, finance, vat, etc..
8. Evaluation and assessment”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

“How have you managed Change procedure in your project?
How have you implemented change control procedure?”

A

“1. Process Flow chart
2. Meetings
3. Register/log.
4. Scope control of Contract and previous variations.
5. KPIs for turnaround of documents and ensure instructions issued only after Client’s sign.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

“What is change control mechanism in your project?
Talk about FIDIC 99 Change procedure?”

A

“Cost conultant raise RFC to Engineer. If Engineer/Client approve then:
Route-1 13.1 ARF prepared by QS based on estimation no proposal, This is for direct intiaitng VO Engineer instructs or request Contractor (via EI or RFP under 13.1) to perform VO without waiting contractor proposal, Contractor bound to do VO before submiting proposal. Fast start. Contractor bound unless cannot readily obtain goods send notice to Eng.

Right to vary: Engineer Intiate Variation by EI or RFP under 13.1, Contractor bound to perfom VO without dealy unless give notice cannot readily obtain GOODS (Engineer must repsond by confirm, vary, or cancel).

Route-2 13.3 Engineer submit RFP, Contractor respond with RFP or reasons why cannot comply, QS do ARF based on RFP, if Engineer approve ARF and Proposal issue EI, or Engineer dissapprove with comment. (Route -2 EI issued after Proposal approval).

Variation procedure: Engineer intiate RFP, Contractor respond as soon as practicable either reasons for not complying or with proposal include 1) proposed work decription and duration 2) modification to programe/time for completion, 3) evaluation proposal. Engineer then respond by apporve or disapproval with comment.

In both routes final value AVI assessed and agreed after assessement of varied works. Mesurment and evaluation under Clause 12.

Route-3 13.6 Dayworks - FASTEST/incidnet/minor, For minor works and incidental in nature. If no dayworks schedule in appendix to tender this clause not valid. Engineer may instruct under this subclause. Contractor submit quotation before ordering goods for approval, and for payment submit invoice/receipts. everyday contractor submit records (3Ms) of previous day, Contract must submit priced statement of 3ms records before inserting in application for interim payment 14.3

13.2 Value Engineering: Contractor at any time may submit proposal for VE, if accelerate work, reduce cost, improve effiecncy, other benefit to client. FIDIC provide incetive to contractor by 50% of cost saving of such excercise subject to engineer approval and considering quality and operational requirements.

13.5 Provisional Sum: No details for defined and undefined in fidic and no details for impact on prgramme. Provisional sum can be expended only by Engineer, Through instruction VO (13.1), or Nominated Subcontractor (5). Price adjusted by Engineer based on actual cost of contractor + OHP from BOQ/Schedule or Appendix to tender.

13.7 Adjustment Change in Legislation: Contractor entitled for Time and Cost for change in laws after basedate. should submit claim notice 20.1

13.4 and 13.8?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

When contractor entitled for new rate?

A

“12.3 (b) Test When works instructed as VO under 13 and no specified rate, and no similar item in contract because work performed under different circumstances
OR12.3(a) test for measured works if all 4 below are met
1. When change in QTY > 10%, AND
2. Change in Qty x rate > 0.01% Accepted Contract Amount AND
3. Change in QTY changes cost per unit > 1%, AND
4. Items not specified as fixed rate.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is Basedate?

A

28 days before last day for tender submission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

If Contractor submit VE proposal and its contain elements designed by Contractor at his own Cost What is your advise?

A

Must have PII for CDP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

If you are a Contractor and received verbal instruction by Engineer what you will do?

A

Must I write within 2 working day to Engineer to confirm in writing the verbal instruction, if no respond from Engineer within 2 working days then my writing to engineer is the written instruction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

When Engineer right to issue VO cease?

A

After TOC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

do you know significance of TOC? what you advise your client before TOC issued?

A

“1. Engineer right to vary cease
2. DLP begin
3. First half or 40% Retention release
4. Delay damages cease
5, Insurance and works protection transfer to client
6. Performance bond may decrease by 50%”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is Value Engineering? and Value Management ?

A

“Definition:
VE: Systematic approach to deliver the required function at required quality with least cost. or increase Performance for same cost.
VM: Proactive multi-disciplinary approach performed at strategic definition of the project to define what value means to all stakeholders and maximize value for money.
Why: VM To for strategic decisions (right project for objectives). VE: Right delivery strategy for performance/function.
When: VM Proactive at earliest to maximize value
VE preferable at outset put usually reactive
Report to VM report to Client/stakeholders VE report to project technical team”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Cost reduction vs VE?

A

“Value engineering: Maintain same performance with less costl alternatives OR increase performance with the same cost, sometimes it will increase overall cost put performance cost ration will be more than before.
Cost reduction: cutting costs by reducing quantum or performance requirements of the works.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Value engineering steps?

A

“1. Info
2. Function Analysis
3. Creative Thinking
4. Evaluation
5. Development
6. Implementation “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Value Engineering techniques

A
  1. Function analysis i.e. value tree and mind map, 2. FAST diagram, 3. Function performance specification, 4. weighing and evaluation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

VE report contents

A

“1. executive summary
2. shortlist options considered
3. Value assessment of options
4. Conclusion and recommendation
5. Appendices.”

42
Q

How would you advise the client on which items to be value engineered? items cannot be value engineered?

A

“Value engineer: Slabs systems, Pavement system, Building envelope, HVAC System.
Not to value engineer: Steel requirement, concrete grade, other structural requirements”

43
Q

If the cost is already exceeding the budget during post contract stage and the Employer cannot find additional finance how you would advise him?

A

“Value Engineer / Re-design
Consider omission of some works and agree with same contractor to re-schedule as phase 2 when funds can be obtained.
Partnership/alliance/JV with funders/developers or existing contractor.
Consider mortgage loan by mortgaging what have been built so far.
Terminate the contract.

44
Q

What is the report the consultant / client required to control the cost

A

the cost planning in the pre contract and the cost report in the post-contract

45
Q

What is the report the contractor required to control the cost

A

CRV and CTC

46
Q

what is the cost control ?

A

The process of controlling costs associated with an activity, process or company. Cost control typically includes

47
Q

What is the Financial control?

A

Management control of financial activities aimed at achieving desired return on investment. Managers use financial statements (a budget being the primary one), operating ratios, and other financial tools to exercise financial control.

48
Q

what is the procedures to cost control

A

“(1) Investigative procedures to detect variance of actual costs from budgeted costs,
(2) Diagnostic procedures to ascertain the cause(s) of variance, and
(3) Corrective procedures to effect re-alignment between actual and budgeted costs.”

49
Q

What is monthly cost report

A

It is a report prepared by the Engineer/ Consultant QS in order to report the financial status of the report at the end of a particular month.

50
Q

What is the purpose of Cost report?

A

“1-Identify the changes to original budget / cost over runs.
2-Identify the possible/potential changes to the contract price.
3-Forecast the final contract price.
4-Identify the changes in the particular period.
5-Employer can identify anticipated final contract price, he can arrange finance
Identify the changes in the particular period.
6-cost saving proposals.”

51
Q

What is the information mentioned in the monthly cost report ?

A

“1- Description of the project / project name and brief of the project
2- Employer information
3- Consultant information
4- Reporting Date
5- Budget: is an estimate of planned future expenditure.
6- Budget Transfer: fund move from one project to another or one element of work to another.
7- Employer change: control the budget by CCM
8- Current Budget: financial plan for a defined period
9- Accepted contract amount
10- Approved variations and claims
11- Pending variations and claims
12- Potential variations and claims
13- Forecasted final amount
14- Certificated amount
15- Previous payments
16- Any risk and opportunity
17- Cash flow forecast

52
Q

How do you administer the cost during the post contract stage?

A

“i will adminstrate it In elements level .then I’ll compare the actual cost against the budget allocation.
If there is any changes/ Variations/ anticipated VOs then I’ll incorporate them. Then if there is any changes I’ll monitor/ report through cost reports.”

53
Q

What are the objectives of financial control & Reporting?

A

“(1) To manage project costs within the approved limits.
(2) To provide a ‘decision support’ advice for use by the Client/Employer.
(3) To provide the Client/ Employer better value for money.
4) To develop the financial information relating to the project in agreed stages against which change can be controlled and regularly monitored.
(5) To achieve balance of expenditure over various elements of the building.”

54
Q

What is being controlled in financial control?

A

“(1) Capital Cost of the Project.
(2) Professional Fees.
(3) Finance Charges, loss of interest on capital used to finance the project.(4) Running cost of the building.
(5) Cost of refurbishment, alteration and disposal”

55
Q

Examples of tools used for Cost Control Process ?

A

“CCS (Construction Candy Software)
Build Smart
Microsoft Excel “

56
Q

What are the qualities of a good report?

A

“Easily understandable by the Employer (or the relevant party).
Overall view should be given of the project. (Past, present, deviations of data).”

57
Q

How do you establish a cost reporting protocol?

A

“1-Depends on the Procurement Method.
2-Depends on who do you report to.
3-Content and format of the cost report.
4-Method of presentation of report.
5-Timing and frequency of issue of report.
6-Distribution list and means of issue.
7-Interfaces with other parties, such as the contractor and client’s finance team.
8-Any additional requirements of stakeholders, such as funders”

58
Q

What is IFRS?

A

International Financial Reporting Standards (IFRS) are designed as a common global language for business affairs so that company accounts are understandable and comparable across international boundaries.

59
Q

What is Risk ?

A

As per the RICS Guidance Notes on Management of Risk, an uncertainity of outcome (whether positive or negative threat). It is the chance of an event and its consequences

60
Q

How is Risk measured ?

A

Risk is measured in terms of a combination of the consequences of an event and their likelihood.

61
Q

What is Risk Management?

A

Risk management is the proactive exercise of identifying, assessing and controlling financial, legal, strategic and security risks to an organization’s capital and earnings. Its recognised concerning with both opportunities and threats

62
Q

Classify the risks under NRM1?

A

“1) Design Development Risk (3rd party risks, changes in estimate, design risks, risk of delay in tendering, environmental, legal, procurement route, undeveloped design 2) Construction Risks ( Mainly site conditions related but not limited to such as delay by statuary undertakers, existing underground issues, exisiting buildings/occupants, etc) 3) Employer’s Change Risk (Cover design, construction and includes employer oriented changes) 4) Employer’s Other Risk (Allowance for early handover, funds management, Liquidated Damages, Partial Taking Over Certificate works, etc)
Risk Allowance: Under NRM1 an amount set aside as a precaution against uncertain outcomes”

63
Q

If u identify risk in your project how will perform risk management with that?

A

First, identify the type of risks and their source classify the risk parameters with their effects Would perform Risk Analysis (Evaluate and assess the impact of risks) Risk Attitude (How it affects the company/individual) Risk Response/Mitigation Strategy (Risk Avoidance, Risk Reduction, Risk Acceptance, Risk Sharing, Risk Transfer)

64
Q

What are the risks encountered in the cost planning??

A

Internal Cost Risks : Incorrect budget forecast, Delay in delivery of work, Outsource of Contractor, Not checking the site and soil conditions External Cost Risks: Change in the material price, Banking fees and charges amendments, Working regulations change

65
Q

As you are commercial manager how will you manage the financial risk in your firm?

A

“Allocate Contingency/Risk Allowance Prioritize.
Buy Insurance.
Limit Liability.
Implement a Quality Assurance Program.
Limit High-Risk Clients.
Control Growth.
Appoint a Risk Management Team.”

66
Q

What is meant by interrelationship of risks?

A

They are also known as consequential risks.

67
Q

How does risk impact on procurement strategy?

A

The procurement strategy entails measuring the risks, benefits, Cost, Time, Quality constraints to conclude and establish procurement route. The procurement strategy should reflect the client objectives, which would include but are not limited to cost, time and quality risks from an early stage.

68
Q

What is the Difference Between Qualitative and Quantitative Risk Assessment ?

A

The purpose of Qualitative risk analysis is to prioritize the risks in terms of importance, without quantifying them where the assessment is subjective and carried out by an individual or group based on the likelihood that risk will occur and magnitude of its potential impact. Quantitative risk analysis is a numeric estimate of the overall effect of risk on the project objectives such as cost and schedule objectives. The results provide insight into the likelihood of project success and is used to develop contingency reserves.

69
Q

How do you measure risks in Qualitative and Quantitative Risk Assessments ?

A

In Qualitative risk analysis there are typically categorised using the scale between likelihoods and impacts. (Eg: Delphi) In Quantitative risk analysis there are methods like Central Limit Theorem, Monte Carlo Techniques, Fault Tree Analysis, Event Tree Analysis, Percentage Addition, Simple Method of Assessment, Probabilistic Method, Sensivity Analysis. (Eg: EMV)

70
Q

What are the reasons for quantification of risks?

A

Build a risk allowance that could be a part of project contingency Client needs to report upward within an organization or third party(Investors) Where project forms part of larger programme of projects To motivate people into following through management actions When Client is having capped funds When Client insists as the part of the procedure Where its desirable to link risk to contingency

71
Q

When to use probability tress to manage the risk?

A

A probability tree is a technique determining the overall risk associated with a series of related risks

72
Q

Who use risk register ?

A

Design Team and Main Contractor

73
Q

What you do when identified a major risk ?

A

Record the event in the risk register, Perform risk assessment workshop , Prepare Respond Mechanism, responsibility matrix, Monitor, review and update the status of risk

74
Q

How do you take into account the output of a risk management workshop?

A

“Allocate Contingency/Risk Allowance
Take Insurance.
Risk Allocation.
Action Plan.
Responsibility Matrix.”

75
Q

How did you assess the risks on your project X?

A

I have identified risks through regular risk management meetings, and qualitatively assessed the risks outcome with the team. then I perform my analysis to advice about most favorable option to overcome those risks.

76
Q

What were the major risks identified on your project X?

A
77
Q

What is Cash flow ?

A

Report to show the cash in and out of the construction project during the project duration.

78
Q

Who is responsible for cashflow preparing? Contractor or Employer?

A

Both parties, the Contractor based on the programme submitted contractually and the Employer as per the payment terms

79
Q

Why Cash flow report is important for the client ?

A

“1- Allows Employer to gain an understanding of their financial commitments over the project duration
2- It acts as a check against valuations
3- can give early indication of financial difficulties
4- Help company remain solvent ( by knowing when the money will go out and when its required to have money in)
Help client the plan expenditure.”

80
Q

Why Cash flow report is important for the contractor ?

A

“He can have an idea of the cash in and out in project duration
Identify possible negative cash flow situations to take the necessary precautions in advance.”

81
Q

How do you identify the negative cashflow?

A

By preparing cash flow forecast.

82
Q

How do you prepare cash flow forecast ?

A

“There are three methods to prepare the cash flow forecast:
1- Assume a series of equal payments
2-Dividing the constrution period into three thirds (1/3), where the first third of project duration you require 1/4 of the total cost,
for the second third you require half of the total cost
for the last third you require the remaining quarter of the total cost.
3- Common used method which you need to Cost loaded programme, COCm material delivery programme and subcontractor and suppliers payments terms “

83
Q

What are the document required to prepare cash flow forecast?

A

“1- Cost loaded programme ( BOQ/Prics/Programme)
2- Condition of contract to check the payment terms
3- Material delivery programme
Subcontractor and Suppliers payment terms”

84
Q

Can you brief how do you prepared Cash flow ?

A

“1- Cost loaded programme ( BOQ/Prics/Programme)
2- Condition of contract to check the payment terms
3- Material delivery programme
Subcontractor and Suppliers payment terms”

85
Q

What is negative cash flow ?

A

When the cash out is more than Cash in at particular time

86
Q

What are the reasons of the Contractor negative cash flow?

A

“1. Under estimate.
2. Site conditions
3. Adverse weather
4. re-sequencing of works(perhaps due to procurement ofsub-contractors)
5. Materials being stored off site(and not claimed for)
6. Project progressing slower than anticipated
7. Materials not being delivered on time, and
8. Cash flow not being accurate in the first place.
9.Payment delay.
10.Progress delay(Fixed cost have to pay).
11.Subcontractor payments not adjusted according to main contract terms.”

87
Q

What are the reasons of the Employer negative cash flow?

A

It cant be negative cash flow for the Employer, because he is the one paying and Funding the construction work, there is no cash in.

88
Q

How do you manage the negative cash flow situation? How do you avoid negative cash flow ?

A

“1.Can ask for an advance payment from the client.
2. Letter of Credit
3. Negotiate with the Employer regarding Payment terms.
4. Negotiate with Subcontractors/ Suppliers regarding payment terms. (Credit terms)5. Can ask from the suppliers to give some concession to pay dues.
6. Inform financial department and arrange finance through other projects or through bank loans.
7. Can start some activities which give more value in the payment certificate.”

89
Q

What are the reasons for being ahead of cash flow?

A

“1. Front-end loading
2. Contractor being ahead of programme by working faster than envisaged
3. Re-sequencing of works meaning that higher value works are carried out earlier
4. Materials being stock-piled on site far before they are required
5. Materials off site not taken into account when producing cash flow forecast
6. the inclusion of variations
7. Contractor purposely accelerating the works to complete earlier (and therefore expending less preliminaries)
8. Cash flow not being accurate in the first place”

90
Q

What is the difference between Cash flow and cash flow Estimate ?

A

“Cash Estimate is the cash flow proposed using program and its bar charts. It is so simple anddoes not address the real situation. For an instance, supply of materials/ Delivery/ Lead time
The cash flow is based on real programme and cash out.”

91
Q

What Adjustments do you do for cost estimate in preparing cash flow ?

A

“1- Adjustment as per payment terms
2- Advance payment and Advance payment recovery
Adjustment for retention.”

92
Q

What are the the 5M’s management framework in construction ?

A

“1- Manpower
2- Machinery
3-Money
4- Management
5-Materials”

93
Q

What a final account is?

A

Financial statement of all adjustments to the contract sum that forms the total amount that the employer needs to pay

94
Q

Purpose of final account

A

”- To enable the final certification To be issued
- Conclude the financial position of the project”

95
Q

What final accounts shows

A

”- Total adjusted contract sum
- Total of all additions / omissions
- Total of all previous payments made to the contractor in interim certificates”

96
Q

Process of getting final account agreed

A

”- Practical completion should be issued and the engineer should evaluate the work
- Ones prepared, all details and supporting documents are sent to the contractor
- any point of disagreement should be discussed and negotiated so that both parties should sign the summary of their agreement”

97
Q

Adjustment of the final account in FIDIC

A

“FIDIC states that 56 days after receiving the
performance certificate the contractors submits their draft final account to the engineer.”

98
Q

What is benchmarking

A

“Benchmarking is a process of continuously measuring and comparing business processes against other business process leaders to gain information to help improve performance.
In other words, Benchmarking is the process of collecting and comparing data within an organisation or external to an organisation to identify the ‘best in class’”

99
Q

What is KPI

A

It is the indicator to measure the quality, performances or any other characteristics which is necessary for the specific works.

100
Q

Process of benchmarking

A

”- Data collection
- Data comparision
- Data analysis
- Action
- Repeat