Project Cost Management Flashcards
Actual Cost (AC)
The actual amount of monies the project as spent to date.
Analogous Estimating
An approach that relies on historical information to predict the cost of the current project. It is also known as topdown estimating and is the least reliable of all the cost-estimating approaches.
Bottom-up Estimating
An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time consuming and most reliable methods to predict project costs.
Budget Estimate
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
Commercial Database
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Contingency Reserve
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
Included in Cost BL
Cost Aggregation
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
Cost Baseline
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.
Cost Budgeting
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
Cost Change Control System
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
Cost Management Plan
The cost management plan dictates how
cost variances will be managed.
Cost of Poor Quality
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.
Cost of Quality
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
Cost Performance Index (CPI)
Measures the project based on its financial performance. The formula is CPI = EV/AC.
Cost Variance (CV)
The difference of the earned value amount and the cumulative actual costs of the project. The formula is CV = EV – AC.
Definitive Estimate
This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate.
The range of variance for the estimate can be from –5 percent to +10 percent.
Direct Costs
Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on).
Earned Value (EV)
Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
Estimate at Completion (EAC)
These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project.