Project Baselines Flashcards
1
Q
Scope Baseline
A
Approved version of Scope Statement, WBS, WBS Dictionary.
Includes: Project Scope Statement WBS, Planning Packages, Control Accounts, Work Packages, WBS Dictionary
2
Q
Schedule Baseline
A
The approved version of a schedule model that can be changed using formal change control
3
Q
Cost Baseline
A
The approved version of the time-phased project budget, excluding any management reserves, which
can be changed only through formal change control procedures and is used as a basis for comparison to actual results.