1
Q

Scope Baseline

A

Approved version of Scope Statement, WBS, WBS Dictionary.

Includes: Project Scope Statement
                WBS, 
                Planning Packages, 
                Control Accounts, 
                Work Packages, 
                WBS Dictionary
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Baseline

A

The approved version of a schedule model that can be changed using formal change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Baseline

A

The approved version of the time-phased project budget, excluding any management reserves, which
can be changed only through formal change control procedures and is used as a basis for comparison to actual results.