Formulas for PMP Exam Flashcards

1
Q

# of Communication Channels

A

of Communication Channels =

n (n-1) / 2

  • n = number of members in the team
  • n should include the project manager
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Performance Index (SPI)

A

Shows overall schedule adherance.

Schedule Performance Index

SPI = EV / PV

  • EV = Earned Value
  • PV = Planned Value
    • SPI < 1 behind schedule
  • *SPI = 1** on schedule
  • *SPI > 1** ahead of schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Performance Index (CPI)

A

Shows overall cost efficiency on the project.

Cost Performance Index

CPI = EV / AC

  • EV = Earned Value
  • AC = Actual Cost
    • CPI < 1 Over budget
  • *CPI = 1** On budget
  • *CPI > 1** Under budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Management Process Groups

A

Initiating Planning Executing Monitor & Control Closing

( 2 ) ( 24 ) ( 10 ) ( 12 ) ( 1 )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Management Knowledge Areas

A

ISS CQR CRPS (766) 436-3734

Integration Resource

Scope Communications

Schedule Risk

Cost Procurement

Quality Stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance (SV)

A

The difference between Earned Value, and Planned Value

Schedule Variance

SV = EV – PV

  • EV = Earned Value
  • PV = Planned Value
    • SV < 0 Behind schedule
  • *SV = 0** On schedule
  • *SV > 0** Ahead of schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Variance (CV)

A

The difference between earned value and the actual costs

Cost Variance

CV = EV – AC

  • EV = Earned Value
  • AC = Actual Cost
    • CV < 0 Over budget
  • *CV = 0** On budget
  • *CV > 0** Within budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate at Completion (EAC)

if original is flawed

1 of 4 EAC Formulas

A

Forecasts final project costs based on work performed & new estimate

Estimate at Completion

EAC = AC + New ETC

  • AC = Actual Costs
  • New ETC = New Estimate to Completion
  • If the original estimate is:
    • Based on wrong data/assumptions, or
    • Circumstances have changed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

if BAC remains the same

2 of 4 EAC Formulas​

A

Forecasts final project costs based on current performance

Estimate at Completion

EAC = AC + BAC – EV

  • AC = Actual Cost
  • BAC = Budget at completion
  • EV = Earned Value
  • If the variance is:
    • Caused by a one-time event, and
    • Is not likely to happen again
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

if CPI remains the same

3 of 4 EAC Formulas​

A

Forecasts final project costs based on current performance

Estimate at Completion

EAC = BAC/CPI

  • BAC = Budget at completion
  • CPI = Cost performance index
  • if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion (EAC)

if substandard performance continues

4 of 4 EAC Formulas​

A

Forecasts final project costs based on current performance

AC = AC + [(BAC -EV) / (CPI*SPI)]

  • AC = Actual Cost
  • BAC = Budget at completion
  • EV = Earned Value
  • CPI = Cost Performance Index
  • SPI = Schedule Performance Index
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index (TCPI)

  • Utilizing BAC*
  • 1 of 2 TCPI Formulas*
A

Predicts liklihood of reaching Budget at Completion

To-Complete Performance Index

TCPI = (BAC – EV) / (BAC – AC)

  • BAC = Budget at completion
  • EV = Earned value
  • AC = Actual Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

To-Complete Performance Index (TCPI)

Utilizing EAC

2 of 2 TCPI Formulas

A

Predicts liklihood of reaching Estimate at Completion

To-Complete Performance Index

TCPI = (BAC - EV) / (EAC - AC)

  • BAC = Budget at completion
  • EAC = Estimate as completion
  • EV = Earned value
  • AC = Actual cost
  • < 1 Under budget

= 1 On budget

> 1 Over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to Completion

A

Predicts how much more the remainder of the project will cost

Estimate to Completion

ETC = EAC - AC

  • EAC = Estimate at Completion
  • AC = Actual Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance at Completion

A

Projection of being over/under budget based on current performance

Variance at Completion

VAC = BAC – EAC

  • BAC = Budget at completion
  • EAC = Estimate at Completion
  • < 0 Over budget
  • = 0 On budget
  • > 0 Under budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PERT Estimation

A

PERT = (O + 4M + P) / 6

  • O = Optimistic estimate
  • M = Most Likely estimate
  • P = Pessimistic estimate
17
Q

Standard Deviation

A

Standard Deviation = (P – O) / 6

  • P = Pessimistic estimate
  • O = Optimistic estimate
18
Q

Float/Slack

A

Float/Slack

From Start: LS – ES

  • LS = Late start
  • ES = Early start
    • = 0 On critical path
    • < 0 Behind schedule

From Finish: LF – EF

  • LF = Late finish
  • EF = Early finish
19
Q

Integration Management Processes

A