Proj Management Sample test 2 Flashcards
Who does the senior user represent when making decisions?
The people or organizations that benefit from using the project’s product
What is an output?
Any of the project’s specialist products
What is established within the ‘initiating a project’ process?
The formats for communicating project information to stakeholders
Which roles CANNOT be combined with the role of project assurance?
- Project manager.
- Project support.
What must the project board do, as a minimum requirement for applying the change theme?
Define a change authority
Which statement describes a threat to a project?
An uncertain event that could have a negative impact on objectives
Which aspect of project performance must be managed in order to have a clear understanding of
what the project is to deliver?
Scope
Which is one of the four integrated elements within PRINCE2?
Processes
What should be provided by corporate, programme management or customer before the ‘starting
up a project’ process commences?
Sufficient information to identify the prospective executive
How is the ‘manage by exception’ principle applied?
By setting controls to warn the higher level of management of potential problems
Which is a responsibility of the managing level within the project management team?
What is a risk cause?
Which is a purpose of the ‘closing a project’ process?
Which is a benefit of applying the ‘manage by stages’ principle?
Which is a benefit of using PRINCE2?