PRINCE 2 Set 2 Flashcards

1
Q

Which statement about controls is CORRECT?
A. A highlight report is an event-driven control
B. An exception report is a time-driven control
C. A daily log is an event-driven control
D. A checkpoint report is a time-driven control

A

D. A checkpoint report is a time-driven control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which document is used to identify interested parties that need to be informed of project closure?
A. Change control approach
B. End project report
C. Communication management approach
D. Project brief

A

C. Communication management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Any change to the products agreed at the start of a stage is monitored as part of the [ ? ] process,
on a day-to-day basis.
A. directing a project
B. controlling a stage
C. managing a stage boundary
D. closing a project

A

B. controlling a stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. The business justification for a project should be documented.
  2. The project manager should be responsible for the business justification.
  3. A project must be stopped if the business justification changes.
  4. Compulsory projects still require business justification.
    A. 1 and 2
    B. 2 and 3
    C. 3 and 4
    D. 1 and 4
A

D. 1 and 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PRINCE2 mandates that the project board represents the primary stakeholder interests. Which
principle does this follow?
A. Manage by stages
B. Focus on products
C. Defined roles and responsibilities
D. Learn from experience

A

C. Defined roles and responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is it confirmed whether a project’s objectives have been achieved?
A. During the ‘closing a project’ process
B. During the final end stage assessment
C. During the ‘controlling a stage’ process
D. During the ‘managing product delivery’ process

A

A. During the ‘closing a project’ process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which statement correctly describes project assurance and quality assurance?
A. Project assurance provides assurance to the project’s stakeholders whereas quality
assurance provides assurance to the wider corporate, programme or customer organization
B. They are both the responsibility of the project board, but project assurance may be delegated
C. They are both independent of the project management team
D. Project assurance and quality assurance are both the responsibility of corporate, programme
management or the customer

A

A. Project assurance provides assurance to the project’s stakeholders whereas quality
assurance provides assurance to the wider corporate, programme or customer organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If a baselined product requires modification, the recommended [ ? ] procedure, or equivalent
procedure should be used.
A. risk management
B. exception management
C. issue and change control
D. quality control

A

C. issue and change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is likely to be avoided by applying the ‘tailor to suit the project’ principle?
A. Unnecessary management effort
B. Project risks
C. Training
D. Procurement procedures

A

A. Unnecessary management effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In which situation might the ‘controlling a stage’ process be used?
A. To manage a long initiation stage of a complex project
B. To manage the activities of a complex programme
C. To organize support activities following the handover of products to operations
D. To create an exception plan to replace the current stage plan

A

A. To manage a long initiation stage of a complex project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which is an objective of the ‘initiating a project’ process?
A. To ensure that there is authority to initiate the project
B. To prepare the plans for the subsequent delivery stages
C. To summarize how the organization’s project management method will be tailored for the
project
D. To request authority from programme, corporate management or the customer to deliver the
project

A

C. To summarize how the organization’s project management method will be tailored for the
project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who is responsible for documenting any tailoring of work packages?
A. Executive
B. Project manager
C. Team manager
D. Project support

A

B. Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which is a minimum requirement for applying the quality theme?
A. To define the use and format of quality records
B. To define the project’s approach to quality assurance
C. To define proxy measures that indicate achievable benefits
D. To define the project’s approach to project assurance

A

D. To define the project’s approach to project assurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which product provides the version number of all products in a particular stage?
A. Issue register
B. Product status account
C. Product description
D. Configuration item record

A

B. Product status account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What must be recorded in the project initiation documentation to meet the minimum requirements
for applying the progress theme?
A. The overall approach to managing by exception
B. The tailoring required for progress reports
C. The tolerance areas that will not be controlled
D. The levels of management control that will be used

A

A. The overall approach to managing by exception

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which theme establishes mechanisms to monitor and compare actual achievements against
those planned?
A. Plans
B. Change
C. Progress
D. Quality

A

C. Progress

17
Q

What does applying the ‘manage by stages’ principle ensure?
A. That the customer’s quality expectations and acceptance criteria are captured and agreed
B. That the project is properly initiated before work begins on delivery of the project’s outputs
C. That the project management team understands what they are accountable for
D. That the project is only started and continued if it is desirable, viable and achievable

A

B. That the project is properly initiated before work begins on delivery of the project’s outputs

18
Q

In a customer/supplier context, which is a responsibility of a supplier?
A. To deliver the benefits of the project
B. To provide the project mandate
C. To deliver the outputs of the project
D. To provide the requirements for the products

A

C. To deliver the outputs of the project

19
Q

Which statement describes the ‘directing a project’ process?
A. It enables the project board to assure that there is continued business justification
B. It covers the day-to-day activities of the project manager
C. It ensures there are regular progress meetings
D. It begins on completion of the ‘initiating a project’ process

A

A. It enables the project board to assure that there is continued business justification

20
Q

Which is a minimum requirement for applying the business case theme?
A. To document the responsibility for defining the standards for the business case
B. To appoint a senior user from an area of the business impacted by the project
C. To have the benefits management approach approved by the participants of benefits reviews
D. To delegate the development of the business justification to the project manager

A

A. To document the responsibility for defining the standards for the business case

21
Q

Which process aims to ensure that during the project all parties understand the project
objectives?
A. Starting up a project
B. Directing a project
C. Initiating a project
D. Managing product delivery

A

C. Initiating a project

22
Q

When should the ‘managing a stage boundary’ process be undertaken?
A. Close to the end of each management stage
B. Close to the start of each management stage
C. At the end of the final stage
D. At the end of the ‘starting up a project’ process

A

A. Close to the end of each management stage

23
Q

Which management stages must a PRINCE2 project consist of, as a minimum?
A. Starting up, initiation, and at least one other stage for the rest of the project
B. At least one stage for developing products, and a closing stage
C. Initiation, and at least one other stage for the rest of the project
D. Initiation, at least one stage for developing products, and a closing stage

A

C. Initiation, and at least one other stage for the rest of the project

24
Q

Which statement about project stakeholders is CORRECT?
A. All stakeholders must be identified at the start of the project
B. All stakeholders are members of the project board
C. All stakeholders are external to the corporate organization
D. All three principle categories of stakeholder have their interests represented by the project
board

A

D. All three principle categories of stakeholder have their interests represented by the project
board

25
Q

Which is a purpose of a project brief?
A. To capture lessons from previous projects
B. To document a common understanding of the starting point for the project
C. To confirm that the project is able to deliver the detailed business case
D. To define the quality techniques to be applied during the project

A

B. To document a common understanding of the starting point for the project

26
Q

Which roles CANNOT be combined with the role of project assurance?
1. Project manager.
2. Project support.
3. Senior user.
4. Executive.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4

A

A. 1 and 2
1. Project manager.
2. Project support.

27
Q

Which is an objective of the ‘closing a project’ process?
A. To check that all the project’s products have been accepted by the users
B. To prepare for the final stage of the project
C. To capture the customer’s quality expectations
D. To ensure that all benefits have been achieved

A

A. To check that all the project’s products have been accepted by the users

28
Q

What must be recorded in the quality management approach, as a minimum requirement for
applying the quality theme?
A. The quality tools and techniques to be used
B. The project’s approach to quality planning
C. The approach to managing project assurance
D. The definition of the quality records required

A

C. The approach to managing project assurance

29
Q
A