Which statement about controls is CORRECT?
A. A highlight report is an event-driven control
B. An exception report is a time-driven control
C. A daily log is an event-driven control
D. A checkpoint report is a time-driven control
D. A checkpoint report is a time-driven control
Which document is used to identify interested parties that need to be informed of project closure?
A. Change control approach
B. End project report
C. Communication management approach
D. Project brief
C. Communication management approach
Any change to the products agreed at the start of a stage is monitored as part of the [ ? ] process,
on a day-to-day basis.
A. directing a project
B. controlling a stage
C. managing a stage boundary
D. closing a project
B. controlling a stage
- The business justification for a project should be documented.
- The project manager should be responsible for the business justification.
- A project must be stopped if the business justification changes.
- Compulsory projects still require business justification.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
D. 1 and 4
PRINCE2 mandates that the project board represents the primary stakeholder interests. Which
principle does this follow?
A. Manage by stages
B. Focus on products
C. Defined roles and responsibilities
D. Learn from experience
C. Defined roles and responsibilities
When is it confirmed whether a project’s objectives have been achieved?
A. During the ‘closing a project’ process
B. During the final end stage assessment
C. During the ‘controlling a stage’ process
D. During the ‘managing product delivery’ process
A. During the ‘closing a project’ process
Which statement correctly describes project assurance and quality assurance?
A. Project assurance provides assurance to the project’s stakeholders whereas quality
assurance provides assurance to the wider corporate, programme or customer organization
B. They are both the responsibility of the project board, but project assurance may be delegated
C. They are both independent of the project management team
D. Project assurance and quality assurance are both the responsibility of corporate, programme
management or the customer
A. Project assurance provides assurance to the project’s stakeholders whereas quality
assurance provides assurance to the wider corporate, programme or customer organization
If a baselined product requires modification, the recommended [ ? ] procedure, or equivalent
procedure should be used.
A. risk management
B. exception management
C. issue and change control
D. quality control
C. issue and change control
What is likely to be avoided by applying the ‘tailor to suit the project’ principle?
A. Unnecessary management effort
B. Project risks
C. Training
D. Procurement procedures
A. Unnecessary management effort
In which situation might the ‘controlling a stage’ process be used?
A. To manage a long initiation stage of a complex project
B. To manage the activities of a complex programme
C. To organize support activities following the handover of products to operations
D. To create an exception plan to replace the current stage plan
A. To manage a long initiation stage of a complex project
Which is an objective of the ‘initiating a project’ process?
A. To ensure that there is authority to initiate the project
B. To prepare the plans for the subsequent delivery stages
C. To summarize how the organization’s project management method will be tailored for the
project
D. To request authority from programme, corporate management or the customer to deliver the
project
C. To summarize how the organization’s project management method will be tailored for the
project
Who is responsible for documenting any tailoring of work packages?
A. Executive
B. Project manager
C. Team manager
D. Project support
B. Project manager
Which is a minimum requirement for applying the quality theme?
A. To define the use and format of quality records
B. To define the project’s approach to quality assurance
C. To define proxy measures that indicate achievable benefits
D. To define the project’s approach to project assurance
D. To define the project’s approach to project assurance
Which product provides the version number of all products in a particular stage?
A. Issue register
B. Product status account
C. Product description
D. Configuration item record
B. Product status account
What must be recorded in the project initiation documentation to meet the minimum requirements
for applying the progress theme?
A. The overall approach to managing by exception
B. The tailoring required for progress reports
C. The tolerance areas that will not be controlled
D. The levels of management control that will be used
A. The overall approach to managing by exception