PRINCE 2 Set 1 Flashcards
In PRINCE2 all potential changes to baselines are dealt with as …
a) Highlight Reports
b) Off-specifications
c) Configuration items
d) Project issues
d) Project issues
Controlling a Stage handles which part of the project?
a) The close of one stage and the planning of the next
b) Day-to-day management of the project
c) The implementation of Work Packages
d) Directing the Project
b) Day-to-day management of the project
The project approach is defined in which process?
a) Initiating a Project
b) Starting up a Project
c) Managing a Stage Boundary
d) None of the above
b) Starting up a Project
Where a management stage ends part way through one or more elements of specialist
work, deciding whether the stage has completed successfully can be a problem. Which
PRINCE2 product helps to solve this problem?
a) Highlight Report
b) Product Description
c) Change Control Approach
d) Quality Register
b) Product Description
Which of the following subjects must be described in the Project Brief?
a) Product-based planning
b) Project Definition
c) Risk Register
d) Quality Management Approach
b) Project Definition
Which of the following statements is FALSE?
a) A PRINCE2 project has defined tolerances for each project objective
b) Tolerances are the permissible deviation from a plan which do not require specific
notification to the next higher level of management
c) Separate tolerances figures should be given for time and cost
d) The Project Board sets tolerances for Work Packages
d) The Project Board sets tolerances for Work Packages
Who would recommend future action on the project to corporate or programme
management if the project tolerance is forecast to be exceeded?
a) The Project Manager
b) The Senior User
c) Project Assurance
d) The Project Board
d) The Project Board
In which situation might the Controlling a Stage process be used?
a) Managing a long initiation stage of a complex project
b) Managing the activities of a complex programme
c) Managing support activities following the handover of the products to the operational
environment
d) Creating an Exception Plan to replace the current Stage Plan
a) Managing a long initiation stage of a complex project
What takes place within the Managing a Stage Boundary process?
a) Periodic review of progress against the Stage Plan
b) Approval and acceptance of all products create during the current stage
c) Escalation of Issue Reports and risks captured during the current stage
d) Review of the business justification for the project
d) Review of the business justification for the project
Which of the following three statements are true of a PRINCE2 project?
1. There is no standard approach to a project.
2. Activities down to the level of Work Package are identified during Project Initiation.
3. A project is a temporary structure.
a) Only 1 and 2
b) Only 1
c) 1, 2, and 3
d) Only 3Which of the following
d) Only 3
What is established within the Initiating a Project process?
a) How the project is going to be approached
b) How the required quality will be achieved
c) All the information to develop the Project Brief is available
d) Any constraints that could affect the project have been removed
b) How the required quality will be achieved
What should be reviewed as part of Authorize a Work Package?
a) The Issue Register
b) The appropriate Product Descriptions
c) Project Board authorisation to proceed
d) Timesheets
b) The appropriate Product Descriptions
Which process ensures that there is a controlled link between the Project Manager and the
Team Manager(s)?
a) Work Packages
b) Managing a Stage Boundary
c) Managing Product Delivery
d) Directing a Project
c) Managing Product Delivery
The PRINCE2 manual talks of balancing a number of elements in describing how to define
stages. Which if the following is NOT one of them?
a) How far ahead in the project it is sensible to plan
b) Where the key decision points need to be on the project
c) The number of Team Plans
d) Too many short stages versus too few lengthy ones
c) The number of Team Plans
Which product does the Project Board use throughout the project to monitor actual costs
and project progress?
a) Project Plan
b) Product Breakdown Structure
c) Project Approach
d) Programme Plan
a) Project Plan
PRINCE2 provides which of the following?
a) A project management method
b) A programme management method
c) Line management techniques
d) All of the above
a) A project management method