Programming And Planning Flashcards

1
Q

What is PERT?

A

PERT stands for Programme Evaluation Review & Technique and is a network planning technique.

The programme is created by establishing 3 different estimates for the duration:
1. Most optimistic (shortest time frame)
2. Most pessimistic (longest timeframe)
3. Most likely (an average of the two)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is CPM?

A

CPM stands for Critical Path Method. Critical path method establishes the longest sequence of activities that must be completed that must be completed for the programme to finish. From this you can calculate the length of the programme and the earliest date you will be able to reach practical completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a project programme?

A

The project programme is sequence of tasks that must be completed on time to achieve the project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can be identified from a project programme?

A
  1. Programme start date
  2. Programme completion date
  3. Activity start date
  4. Activity completion date
  5. Critical path
  6. Amount of float in the programme
  7. Tasks that must be completed sequentially.
  8. Tasks that must be completed simultaneously.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What must a project programme help you do?

A
  1. Plan tasks
  2. Monitor progress
  3. Monitor resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the different types of programme?

A
  1. Contractor’s Master Programme
  2. Client Overall Programme
  3. Design Team Programme
  4. IRS Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is included in a Contractor’s Master Programme?

A

The contractor’s master programme will schedule and sequence the construction activites.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is included in a Client’s Overall Programme?

A

The client’s overall programme will show the entire process from project inception, to design, construction and then handover.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is included in a Design Programme?

A

The design programme will schedule the design from inception through to Stage 4 Technical Design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is included in an IRS Schedule?

A

An IRS schedule details information required by specific dates to meet the project programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Gantt Chart?

A

A Gantt chart is a programme technique to visualise a project timeline. This is demonstrated by the use of bars which will demonstrate activity start date, completion date and duration. The Gannt chart demonstrates dependant activities or activities that can run simultaneously.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the critical path?

A

The critical path is the longest sequence of activities that must be completed to successfully conclude a project. Activities on the critical path are known as critical activities because if they’re delayed, the whole project will be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can critical path activities have float?

A

No, critical path activities have no float, as if a critical activity is delayed the whole project is delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is float?

A

Float is the amount of time an activity can be delayed without it delaying the overall programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is lag?

A

Lag is when there is delay between one activity finishing and the next activity starting, an example would be concrete curing time before the next activity starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a project milestone?

A

A project milestone is a predetermined task that has zero duration but shows a significant achievement in a project.
Examples:
1. Planning permission
2. RIBA Stage 3 complete
3. Contractor appointed
4. Start on site
5. The building being watertight

17
Q

What is jagged drop line on a programme?

A

A jagged drop line shows progress against each individual task by inputting a percentage complete against each activity. It details tasks behind, on time and ahead of schedule.

18
Q

What is a straight drop line on a programme?

A

After progress is entered, the drop line will reschedule tasks from the progress reporting date. This will detail impact on the critical path.

19
Q

How would you put together a programme for a new project?

A

To complete a programme I would establish the level of detail required before I proceed. I would establish key deliverables and key milestones; planning approval, design at RIBA Stage 3 and contractor appointment. I would then establish project activities and determine the duration. I would then establish relationships between activities and link accordingly. I would identify float and the critical path. I would issue the programme to the team to review and then use the programme to monitor progress.

20
Q

What is concurrent delay?

A

Concurrent delay is when two or more delays caused by different parties occur independent of each other, but at the same time.

21
Q

What is acceleration?

A

Acceleration is completing the project in a shorter period or mitigating some form of delay.

22
Q

How can you accelerate a programme?

A
  1. Resequencing activities
  2. Working longer hours
  3. Increasing the resources
  4. Reducing the scope
  5. Changing construction methods
  6. Changing design or specification
23
Q

What payment schedule provides the most accurate cashflow forecast?

A

Stage payments - payments made in instalments that do not necessarily reflect progress.

24
Q

What are the different types of float on an NEC programme?

A
  1. Total float
  2. Time risk allowance
  3. Terminal Float
25
Q

What is the contractual status of the programme for your projects?

A

As i work under JCT the construction programme has no contractual status apart from identifying the weeks required on site which prelims are priced in accordance with.

26
Q

What is an activity schedule?

A

An activity schedule, used on NEC contracts, is when a cost is allocated to activities and payment is made once them activities are complete.

27
Q

How does a programme show key milestones?

A

A key milestone is a bar with no time duration, usually highlighted in another colour and a diamond symbol.

28
Q

Who owns terminal float on your contracts?

A
  • NEC contractor owns terminal float
  • Also on a JCT a contractor owns the float as if they have a start and finish date and 2 weeks float that is theirs however there is an argument it is who uses it first. If the design team delay information release by two weeks the float has been used.
29
Q

How do you use a programme to prepare your cash flows?

A

Use a programme to identify start date, completion date and duration of project. Also identifies subcontract dates which will identify stage and monthly payments. Can also work out staff costs, resource costs, site set up costs etc.

30
Q

What techniques are there to monitor progress?

A

Jagged drop line
Straight drop line

31
Q

How can you use a programme to identify resource requirements?

A
32
Q

What are the different types of float?

A

Total Float - time by which an activity can be delayed without effecting the completion date
Free Float - time by which an activity can be delayed without affecting follow on activities

33
Q

What is a flow diagram?

A

Construction flowchart is a series of flowchart symbols which connect the detailed steps of construction. It uses graphic symbols to visualise the complicated process step by step through construction.

34
Q

What is a project execution plan?

A

The project execution plan (PEP) is the governing document that establishes the means to execute, monitor, and control projects. The plan serves as the main communication vehicle to ensure that everyone is aware and knowledgeable of project objectives and how they will be accomplished.

35
Q

What is a project handbook?

A
36
Q

What roles does a PM have during commissioning and handover?

A
37
Q

What are close out reports?

A