Procurement And Tendering Flashcards
How do you develop an effective procurement strategy?
- Understand the client’s requirements with regards to time, quality, cost and risk.
- Project requirements
- Client experience
Are there other options beyond traditional and D&B?
Management Contracting
Construction Management
When would you choose CM over MC
- Client’s construction experience
- Client’s risk profile
When would you advise the use of two-stage tendering?
- Buildability input, contractor is involved during the design phase
- Early start on site
- Employer wants to be involved in subcontractor selection
- Increased opportunity to value engineer
- Cost is not the main priority
What are the disadvantages of two-stage?
- No cost certainty until final package is let
- PCSA fee for the contractor
- Potential for negotiation stage to fail and time wasted
How does management contracting differ from construction management?
With Management contracting the Main contractor appoints all trades directly for a pre-agreed management fee or time related allowance. They are responsible for the management of all trade packages with regards to time cost and quality. CM the main contractor acts as a consultant and is in charge of the programme and health and safety.
In what situation would construction management be appropriate?
When the client has previous building experience and would have the resources to manage all the trade contractors otherwise it should be Management Contracting.
What is your understanding of PFI as a form of procurement?
Private finance initiatives (PFIs) allow governments and the private sector to join forces to finance and implement projects that benefit the public sector. Usually the private second will design, construct and facilities manage the building which it will lease to the government for a set period (say 30 years), after this the ownership transfers to the government.
What are the factors that would be considered in deciding the most appropriate procurement route for a project?
- The expertise of the client
- The client’s preferred risk profile
- The stage of the design
- How quick they would like to start on site
- What is the client’s preference on cost certainty?
What current challenges is Covid and/or Brexit bringing to Procurement & Tendering?
Change from OJEU to FTS.
Can you give a brief overview of the tender process?
- Take brief from employer
- Choose suitable strategy
- Prepare tender documentation and issue
- Deal with tender queries
- Open and analyse returns
- Report and recommend
What is the difference between procurement and tendering?
Procurement is the overall act of obtaining goods and service depending on client’s objective to time, cost, quality and risk. Whereas tendering a process within procurement to obtain a price and appoint a contractor.
What are the 3 tendering strategies?
- Single Stage Tendering
- Two Stage Tendering
- Negotiated Tendering
What is PPP (Public - Private Partnership)?
What is Early Contractor Involvement?
What is BS 11000-1?
What is PAS 91 2013?
What is the risk of negotiated tendering?
Price is too far apart from pre-tender estimate
Does the client have to proceed with this subcontractor?
No, the client is not obliged to proceed with the contractor as they need value for money
What is a design checking period?
A period between appointment and contract signing to review all documentation and ensure they are correct with tender queries added.
What are the stages of BIM?
Stage 0
2D Drawing
Stage 1
Add 3D model
Stage 2
Add multiple trade BIM Model
Stage 3
Add shared BIM model
Stage 4
Add Planning and Scheduling
Stage 5
Add cost estimation
Stage 6
Add sustainability
What is the purpose of BIM?
To reduce risk
What is serial tendering?
- Combination of two stage and negotiated tendering
- For clients with similar work
- Original competitive tender
- Agreed schedule of rates for future work
- Competitiveness reduces over time
What is a measured term contract?
- Made for maintenance
- Continued supply of similar work
- Schedule of rates
- Value for money
What is framework?
- Open tendering
- Companies apply and if successful are placed on the tender
- Reduce procurement costs
- Two options; supplier called off based on fees or small mini tenders
What if the client likes a VE option from an unsuccessful bidder?
- Ethic issue?
- Do they have patent rights?
- Be open and transparent
- Pay them for their time
At what RIBA stage should you go out to tender for each route?
D&B: Stage 2 onwards
Traditional: Stage 4 onwards
Two Stage Traditional: Stage 2 onwards