Contract Administration Flashcards

1
Q

What is the difference between a contract administrator and employer’s agent?

A

CA is the role in traditional forms of contract
EA is the role in Design and Build
EA’s normally start their appointment earlier and work on behalf of the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the legal basis for this difference?

A

EA’s the contract administration role within design and build contracts whereas the Contract Administrator performs the same contract administration role in traditional forms of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key duties of the contract administrator under the form of contract?

A
  1. Administering the contract
  2. Chair Meeting
  3. Issuing relevant certificates
  4. Administrating change control procedures
  5. Issuing certificates interim certificates for payment.
  6. Issuing practical completion certificates.
  7. Collating and issuing schedules of defects.
  8. Issuing the certificate of making good defects.
  9. Issuing the final certificate.
  10. Consider EOT claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can anyone else undertake any of these duties?

A

Yes the QS under the contract can undertake some of these duties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What duties does the contract administrator usually have, which are additional to those set out in the contract?

A

Preparing and issuing construction progress reports.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is an extension of time calculated?

A
  1. Review facts and relevant event
  2. Compare as planned versus as built
  3. Critical path analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the process for determining whether completion has been achieved?

A

Are works substantially complete, employer can use the building excluding snags and minor defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the role of the contract administrator following completion?

A

Following completion the CA must record a list of snags, issue a final completion certificate and agree final account. 12 months later it must review the snagging works and issue a making good certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What current challenges is Covid and/or Brexit bringing to Contract Administration?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a bond?

A

A bond is a promise (usually by deed) whereby the person giving the promise (the bondsman) promises to pay another person (the employer) a sum of money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the different types of bond in the industry?

A

Advance Payment Bond
Retention Bond
Performance Bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a performance bond?

A

Requested by the employer, and required from the contractor, who in turn obtains it from a bank or insurance company. The bond is usually 10% of the contract sum payable to the employer if the contract fails to complete the work in accordance with the building contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the two different types of bonds?

A
  1. On-demand bond
  2. Default bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the difference between the two types of bonds?

A

The essential difference is an employer does not have to prove a default has occurred under a ‘on demand’ bond. Where as with a default bond the employer must prove the conditions necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What must the employer prove with a default bond?

A
  1. That a breach under the primary contract has occurred
  2. The level of damage suffered by him/her as a result of that breach
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an on-demand bond?

A

Employer can call on the money even if a breach has not occurred.

If the contractor is wise they would factor this into their contract price, but contractors should resist this type of bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How can an on-demand bond be prevented?

A
  1. Fraud
  2. Bad faith
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a collateral warranty?

A

A collateral warranty is a contract which is ancillary to the principal contract and creates a contractual relationship that would not otherwise exist.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why do we have collateral warranties?

A

Under current law if there is no contract between party A and party B, the ‘necessary’ damage suffered must equate to a physical injury or damage to a property other than the property which is negligent. Therefore pure economic loss is irrecoverable in tort which is why collateral warranties exist.

20
Q

What is included in a collateral warranty?

A
  1. Duty of Care
  2. Copyright
  3. Prohibited materials
  4. Professional indemnity insurance
  5. Assignment
  6. Step-in rights
21
Q

What does a consultant promise under a collateral warranty?

A

They have performed their services in accordance with their appointment, exercising the requisite level of skill and care.

22
Q

What does a contractor promise under a collateral warranty?

A

They have carried out work in accordance with the contract in a proper and workmanlike manner (in accordance with clause 2.1 of JCT SBC 2016)

23
Q

Why does a collateral warranty include copyright?

A
  1. To ensure only a beneficiary license in granted (and not assignment of the copyright)
  2. An exclusive license is not given to the first beneficiary of a collateral warranty
  3. Include limitations to ensure the design is not used for the extension of that development or for a new development
24
Q

Why include PII?

A
  1. To ensure warrantor is protected against breach
  2. The warrantor must confirm level of PI insurance, and confirm they will have it for a minimum of 12 years
  3. PII must also be on a ‘each and every’ claim basis
25
Q

Why do collateral warranties have step-in rights?

A

To allow a third party to enter into the contract and act as the employer if the first employer is unable to continue its duties under the contractor.

26
Q

What are common amendments to collateral warranties?

A
  1. Net contribution
  2. No greater liability
  3. Cap on liability
27
Q

What is net contribution?

A

The warrantor is only liable for loss from their services and not third parties.

28
Q

What is cap on liability?

A

A warrantor will cap its liability usually to the level of their PII.

29
Q

What are third party rights?

A

The act provides an alternative to collateral warranties, and enable third party beneficiaries to enforce a term of a contract. The third party is given rights at the execution of the contract, tenants for example even if the names are unknown at the time.

30
Q

Why has uptake on third party rights been slow?

A
  1. Beneficiaries preference of physical warranty signed by the warrantor
  2. The warrantors reluctance to grant rights to unknown beneficiaries
31
Q

What is the advantages of third party rights over collateral warranties?

A
  1. Save time and money wasted drafting other contracts and chasing these up
32
Q

What is a parent company guarantee?

A

A guarantee provided by the contractor’s ultimate parent or holding company to answer for the debt, default or miscarriage of the contractor.

33
Q

What is the difference between a bond and a PCG?

A

A bond will protect a financial guarantee, where a PCG may be a performance guarantee or both.

34
Q

Why may a employer ask for a PGM?

A

When an employer is concerned by the financial viability, so a PCG provides an assurance. This may be requested if the company is new.

35
Q

What does a PGM guarantee?

A
  1. The contractor will performs its obligations, and failing to do so, the parent company will ensure the contract is completed.
  2. That it will protect the employers financial interests by promising to pay sums due under the contract if the contractor is unable to meet them.
36
Q

What happens to a PCG if their is a variation to the main contract?

A

Employer should ensure they can amend the contract without the consent of the PC, as if they do without this agreed the PC can no longer be liable for its obligations.

37
Q

When does a PCG liability finish?

A

If no date is specified the date is generally 12 years after PC.

38
Q

How does the liability time differ between performance bonds and PCG?

A

Performance bonds typically expire at practical completion or the certificate of making good. Whereas PCG will last to the end of the contract liability period.

39
Q

Does adjudication apply to PCG?

A

No, as it is not recognised as a construction contract.

40
Q

What contractual conditions must be met for Liquidated Damages to be deducted?

A
  • The CA must issue a non completion certificate
  • The employer must notify the contractor of its intention to deduct liquidated damages before the date of the final certificate
  • The employer must serve a notice to withhold payment no later than 5 days before the final date for payment
41
Q

What are the implications of writing £nil on the clause for liquidated damages?

A

If the liquidated damaged clause is not deleted itself but only £nil is inserted, the employer waives his rights to liquidated and unliquidated damages.

42
Q

What are the implications of inserting ‘N/A’ in the Liquidated damages clause?

A

Liquidated damages no longer apply to the contract, however, a claim for general damages could still be brought.

43
Q

What are the implications of removing relevant events with regard to Liquidated Damages?

A

If there is no mechanism for a contractor to apply for an Extension of Time, the ‘prevention principle’ applies and the employer will lose its right to apply liquidated damages.

44
Q

What are the benefits of liquidated damages?

A
  1. Certainty
  2. Limitation of liability
  3. Saves time and expense
  4. Incentive
45
Q

How do you calculate Liquidated Damages?

A

They must be a predetermined estimate of financial loss suffered by the innocent part if the event the contractor breached the contract by not completing on time. This can be:
1. Loss of capital
2. Direct loss
3. Extended financing costs