Procurement & Tendering Flashcards
What is procurement?
The overall process of acquiring construction work or services.
What is tendering?
A structured procedure for generating quotation from suppliers or contractors looking to obtain an award of business activity either under competition or via negotiation with a single contractor.
What should be considered when deciding on a procurement strategy?
- The specifics of the project.
- The client objectives regarding:
a. Cost
b. Time
c. Control
d. Quality
e. Risk
What are the 2 main processes of tendering?
- The bidding process
- Appointment
You mention single stage tendering, can you give an example where you have used this? And why it was chosen?
I have used single stage tendering on the UCB Link refurbishment as the client had a list of trusted and capable contractors from previous projects which were suitable to tender for the scheme.
You mention two stage tendering, can you give an example where you have used this? And why it was chosen?
I have used two stage tendering on the MTC Cell 4 project. As this project was of secure nature, specialist contractors and sub-contractors were required. Two stage tendering allowed early involvement of the contractor, allowing the client and design team to utilise their experience and buildability advice early.
You mention negotiated tendering; can you give an example where you have used this? And why was it chosen?
I have used negotiated tendering on the UCB Moss House project due to the client and contractor’s relationship having successfully carried out various smaller value projects.
What are the different types of procurement strategies?
- Traditional
- Design & Build
- Management contracting
- Construction management
How do you identify the Client requirements before recommending a procurement route?
I would hold detailed discussions with the client and design team to identify their priorities in terms of cost, time, quality, risk, control requirements and experience.
What procurement route if client wants an early start on site?
Depends on other client requirements. If cost is not key, CM or MC would be ideal as shorter to no tender period. If cost is key, D&B route.
What is traditional procurement?
- Where the design is completed by the client’s design team before a competitive tender is issued and the main contractor is appointed to build what the designers have specified.
- Contractor = takes responsibility and financial risk for the construction of the works to the design produced by the clients design team.
- Client = takes responsbilibyt and risk for the design and design team performance.
When might traditional procurement be appropriate?
- Employer has had the design prepared already.
- Design is substainally complete at the time of contractor selection.
- Client wishes to retain control over the design and specification.
- Cost certainty is important early (SoS).
- Shortest overall programme is not the clients main priority.
What are the benefits and drawbacks of traditional procurement?
- Benefits
a. Retaining control of design might lead to higher quality.
b. Offers increased levels of cost certainty before commencement on site.
c. Design changes are reasonably easy to arrange and value. - Drawbacks
a. Project duration may be longer due to no design/construction overlap.
b. No design and planning input by the contractor.
c. Strategy based on price completion may lead of adversarial relationships.
d. Dual point of responsibility (contractor = construction & client = design).
What is design & build procurement?
- Where the contractor is responsible for the design, planning, organisation, control, and construction of the works to the ERs.
- Employer gives tenderers the ‘ERs’ and contractors respond with their tender returns (CPs), including a price.
- Client transfers design responsibility to MC who holds contractual relationship with architect.
When might D&B be appropriate?
- Early start on site required (design/construction overlap).
- Client wishes to minimise their risk due to transfer of design responsibility to MC.
- For technical and complex projects that require contractors’ expertise.
- Employer does not want to retain control over design development.
Who carries out the design for the MC on a D&B?
- Outsourced to design company.
- Novated architect.
- In-house design team.
What are the benefits and drawbacks of design and build procurement?
- Benefits
a. Single point of responsibility.
b. Earlier start on site.
c. Early price certainty.
d. Use of contractor’s expertise during design. - Drawbacks
a. Clients may find it hard to prepare a sufficiently comprehensive brief.
b. Client has to commit to concept design early.
c. Variations from initial brief are hard to arrange and costly.
d. Harder to compare tenders and determine value for money.
What is management contracting?
- A management contractor is employed to contribute their expertise to the design and to manage construction with a management fee being paid to them for doing so.
- MC has direct contractual links to all sub-contractors.
- MC has responsibility for construction without carrying out work.
- MC selects work contractors through competitive open book tender.
- Client reimburses the cost of packages to the MC plus management fee.