Contract Practice Flashcards
What are the two methods of contact execution?
- Under hand (a ‘simple contract’ that is just signed by the parties).
- Under seal (signed by the parties, witnessed and most importantly made clear that they are executed as a deed).
What is the difference between these methods of execution?
Limitation periods are different. Under hand offers 6 years from cause of action and under seal (deed) offers 12 years. Timescales come from the Limitation Act 1980.
What is the limitation period?
The limitation of action is a statutory remedy which prevents a claimant from bringing proceedings after the expiration of said time limit. The Latent Damage Act highlights the timescales for the limitation period. Collateral warranties are a key consideration for how the contract is executed.
Are you aware of any case law associated with the limitation period?
Oxford Architects v Cheltenham Ladies College 2006
The claimant college engaged the defendant architects in relation to a new block. The appointment stated that no action should be commenced after 6 years from the date of practical completion. Practical completion was certified on 25 November 1998, and on 24 November 2004 the college served an arbitration notice in relation to a number of defects. The arbitrator held that none of the heads of claim were statute-barred and the architects appealed.
The court found that where the issues that gave rise to the heads of claim had occurred before practical completion and been known about at the time, time for limitation purposes started to run on the date when the breaches occurred. It followed that if the breaches happened before practical completion, they were statute-barred.
What other contracts are there under the JCT suite?
- Design and build
- Minor works
- Intermediate
- Standard building contract
- Prime cost
- W/Quants, W/Out Quants
- w/CDP, W/Out CDP
Are you aware of any other contracts outside of the JCT suite?
- NEC4 (New engineering contract)
- FIDIC (International Federation of Consulting Engineers)
- ACA (Association of Consultant Architects)
What are the most typical amendments you have seen when preparing a contract?
- Passing to the contractor the responsibility for errors, ambiguities, and inadequacies in the ERs.
- Adding/omitting relevant events or matters.
- Change to the payment timescales.
- Third party rights.
What is included in the Employer’s Requirements?
- Set out the client’s requirements for the project (size, function, etc).
- Level of details depends on design completed to date.
- Includes status of planning permission if applicable.
- Outline design, structure and spec of info provided.
What is a performance bond?
- Typically provided by banks or insurance companies.
- They give the employer a guarantee of payment up to a stated amount should they suffer a loss as a result of the contractor’s breach of his contractual obligations.
- Typically 10% of the contract value.
- Premium for taking out the bond is added to the contract sum.
How can the employer call for payment?
The employer has the prove that the contractor has defaulted in their obligations under the main contract and that loss has been suffered.
What are alternatives to using a performance bond?
- Parent Company Guarantees.
- Reducing % of PB from the typical 10% to 7% with remaining in escrow for example.
- Increasing retention (consider contractors cashflow).
- Collateral warranties from key subcontractors/consultants including step in provisions.
- Latent defects insurance.
What are the benefits of using a performance bond?
- Offer an extra layer of financial security for the employer.
- Reduced risk of project failure.
- Encourages best practice through incentivizing the contractor to adhere to best practices.
What are the drawbacks of using a performance bond?
- Contractors must pay a premium for performance bonds which is typically passed onto employer.
- Time consuming – could delay project start dates.
- Some contractors may struggle to obtain PBs due to history of claims or financial difficulties.
What are collateral warranties?
- Create contractual relationships between main parties of a contract with an external third party.
- Would not exist with 3rd party due to privity of contract.
What are/is the purpose of collateral warranties?
- Used due to ‘privity of contract’.
a. Rights & obligations under a contract can only be enforced by a party to that contract.
b. CWs therefore give remedies to 3rd parties that would not otherwise happen.
Who may want a CW?
- Any 3rd party with financial investment but not a party to the main contract.
- Funding institutions, future tenants or purchasers.
- Employer – if MC goes into liquidation, they would have no contractual link for redress in case of defective workmanship.
What are the common clauses / terms in CWs?
- Obligations should mirror that of the main contract.
a. If a party breaches the main agreement, they also breach the warranty. - Common terms include:
a. Limitation of liability
b. Reasonable skill & care or fitness for purpose
c. Requirements for PI insurance
d. Assignment rights
e. Novation rights
Name some standard forms of collateral warranties?
- CWa/F = Standard form for a funder.
- CWa/P&T = Standard form for a future purchaser or tenant.