Design Economics & Cost Planning Flashcards
What RICS documents are you aware of to assist with cost planning?
- NRM1 (Order of cost estimating and cost planning for capital building works).
- NRM1 (Contingency guidance).
What sources of cost data are you aware of?
- Previous tender submissions.
- Previous CSAs.
- In house benchmarking.
- BCIS.
- Building cost models.
- SPONS and other price books.
- Specialist sub-contractors and suppliers.
What is BCIS?
Building Cost Information Service – provides cost and price information through publications, online services and price books.
What is Tender Price Indices?
They reflect changes in the level of tender prices over a period of time. The price adjustments take into account the level of inflation depending on current and forecast market conditions.
You mention BCIS can re-base construction costs dependant on location. How and why?
Infation needs to be accounted for to anticipate the changes in prices of labour, plant and materials. Depending on the area, these 3 items may be affected differently. This is done to ensure accuracy of the estimate for the client.
When would you typically include TPI up too?
Typically, I would recommend TPI is taken up to the start on site date to the midpoint of construction.
During what RIBA stage would you expect to issue an Order of Cost Estimate?
Order of Cost Estimate: During RIBA Stage 0 to 1.
During what RIBA stage would you expect to issue a Formal Cost Plan?
Formal Cost Plans: From RIBA Stage 2 to 4.
When would you expect a Pre-Tender Estimate to be issued?
I would expect the RIBA Stage 4 cost plan to form the basis of a PTE.
You mention design metrics, can you give me an example of some of these?
- Wall to floor ratio
a. Shows the relationship between the wall area and floor area.
b. Used to show cost efficiency of the building.
c. Lower the ratio, cheaper the building is to construct as there is less external envelope in comparison to floor area. - Net to gross
a. A metric used to assess the efficiency of a building’s design.
b. Optimal if the number is less than 1.
What would you recommend to a client a good wall to floor ratio is?
Between 0.4 and 0.5.
What would you expect the cost difference to be between wall to floor ratios?
A variation of 0.1 in the wall-to-floor ratio can change overall construction costs by 4 to 5%.
What shape is the most efficient shape?
In theory, a circular floor plate would be the most efficient design, however this offers poor lettable floor area and is difficult to fit out. Therefore, a square would be the most efficient.
What are the key components of a cost plan?
- Construction costs.
- Preliminaries.
- Contractor on costs.
- Contingency.
- Inflation.
- Assumptions.
- Exclusions.
- Area schedule.
- Basis.
What is the purpose of an order of cost estimate?
To establish if the proposed building project is affordable, and if so, to establish a realistic cost limit. The cost limit will be the maximum the client is prepared to spend.