Procurement Management Flashcards
Plan Procurement Management
2.9.1 Planning Process Area, Procurement Mgmt KA
The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers
Inputs: Project Charter, Business Documents, Project Management Plan, Project Documents, EEF, OPA
Tools & Techniques: Expert Judgement, Data Gathering (e.g. Market Research), Data Analysis, Source Selection Analysis, Meetings
Outputs: Procurement Management Plan, Procurement Strategy, Bid Documents, Procurement Statement of Work, Source Selection Criteria, Make-or-buy Decisions, Independent Cost Estimates (inside or outside the organization), Change Requests, Project Documents Update, OPA Updates
Fixed-Price Contracts
2.9.1 Plan Procurement Management TT
Setting a fixed total price for a defined product, service, or result to be provided.
May also incorporate financial incentives for achieving or exceeding selected project objectives. Sellers are legally obligated to complete such contracts, with possible financial damages if they do not
Firm Fixed Price Contracts
2.9.1 Plan Procurement Management TT
Most commonly used contract type
Price for goods is set at the outset and not subject to change unless the scope of work changes. Any cost increase due to adverse performance is the responsibility of the seller, who is obligated to complete the effort.
Firm Price Incentive Fee Contracts
2.9.1 Plan Procurement Management TT
Fix-price arrangement that gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed upon metrics.
Under FPIF contracts, a price ceiling is set, and all costs above that are the responsibility of the seller
Fixed Price with Economic Price Adjustment Contracts
2.9.1 Plan Procurement Management TT
Use whenever the seller’s performance period spans a considerable period of years, as is desired with many long-term relationships.
It’s a fixed-price contract, but with a special provision allowing for pre-defined financial adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specified commodities.
Cost-Reimbursable Contracts
2.9.1 Plan Procurement Management TT
Contract involves payments (cost reimbursements) to the seller for all legitimate actual costs incurred for completed work, plus a fee representing seller profit.
Provides the flexibility to redirect a seller whenever the scope of the work cannot be precisely defined at the start and needs to be altered, or when high risks may exist in the effort
Cost Plus Fixed Fee Contracts
2.9.1 Plan Procurement Management TT
Seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed-fee payment calculated as a percentage of the initial estimated project costs.
Fee is only paid for completed work and does not change due to seller performance.
Cost Plus Incentive Fee Contracts
2.9.1 Plan Procurement Management TT
Seller is reimbursed for all allowable costs for performing the contract work, and receives a predetermined incentive fee based on achieving certain performance objectives as set forth in the contract.
If final costs are less or greater than estimated, then both buyer and seller share costs from the departures based upon a pre-negotiated cost-sharing formula.
Cost Plus Award Fee Contracts
2.9.1 Plan Procurement Management TT
Seller is reimbursed for all legitimate costs, but the majority of the fee is earned only based on the satisfaction of certain broad subjective performance criteria defined and incorporated into the contract.
Time and Materials Contract
2.9.1 Plan Procurement Management TT
Hybrid type of contractual arrangement that contain aspects of both cost-reimbursable and fixed-price contracts.
Resemble cost-reimbursable contracts in that they can be left open ended and may be subject to a cost increase for the buyer.
Resemble fixed-fee arrangement when certain parameters are specified in the contract. Unit labor or material rates can be preset by the buyer and seller, including seller profit, when both parties agree on the values for specific resource categories.
Make-or-Buy Analysis
2.9.1 Plan Procurement Management TT
General management technique used to determine whether particular work can best be accomplished by the project team or should be purchased from outside sources.
Market Research
2.9.1 Plan Procurement Management TT
Examination of industry and specific vendor capabilities
Force Majeure
2.9.1 Plan Procurement Management TT
A clause you may see in a contract that says if something like a war, riot, or natural disaster happens, you’re excused from the terms of the contract
Point of Total Assumption
2.9.1 Plan Procurement Management TT
The point at which the seller assumes the costs.
In a fixed-price contract, this is the point where the costs have gotten so large that the seller basically runs out of money from the contract and has to start paying the costs.
Procurement Documents
2.9.1 Plan Procurement Management Outputs
The statement of work (SOW) for each procurement is developed from the project scope baseline and defines only that portion of the project scope that is to be included within the related contract.
Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results .