Cost Management Flashcards
Plan Cost Management
2.4.1 (Planning Process, Cost Mgmt KA)
The process that establishes the policies, procedures, and documentation for planning, managing, expending and controlling costs.
Inputs: Project Charter, Project Management Plan, EEF, OPA
Tools & Techniques: Expert Judgement, Data Analysis, Meetings
Outputs: Cost Management Plan
Cost Management Plan
2.4.1 Plan Cost Management Output
Component of the project management plan and describes how the project costs will be planned, structured, and controlled.
Can establish:
- Units of measure
- Level of precision
- Level of accuracy
- Organizational procedures link
- Control thresholds
- Rules of performance measurement
- Reporting formats
- Process descriptions
Estimate Costs
2.4.2 (Planning Process, Cost Mgmt KA)
The process of developing an approximation of the monetary resources needed to complete project activities.
Inputs: Project Management Plan, Project Documents, EEF, OPA
Tools & Techniques: Expert Judgement, Analogous Estimating, Parametric Estimating, Bottom-up Estimating, Three-point Estimating, Data Analysis, Project Management Information System, Decision Making
Outputs: Cost Estimates, Basis of Estimates, Project Document Updates
Bottom-Up Estimating
2.4.2 Estimate Costs TT
Cost of individual work packages is estimated to the greatest level of specified detail. The detailed cost is then summarized or ‘rolled up’ to higher levels for subsequent reporting and tracking purposes.
Analogous Estimating
2.4.2 Estimate Costs TT
Uses the values such as scope, cost, budget, and duration and measures of scale such as size, weights, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project.
Parametric Estimating
2.4.2 Estimate Costs TT
Uses a statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work.
Three-Point Estimating
2.4.2 Estimate Costs TT
Uses three estimates to define an approximate range for an activity’s cots
M - Most likely
O - Optimistic
P - Pessimistic
Triangular Distribution = average of all three
Beta Distribution or PERT = (4M + O + P) / 6
Rough Order of Magnitude (ROM)
2.4.2 Estimate Costs TT
Also known as ballpark estimate
When you make an estimate really early in the project and you don’t know much about it
-25% to +75%
Reserve Analysis
2.4.2 & 2.4.3 Estimate Costs TT
Setting aside cash to mitigate any future risks that cause expenditures.
Can establish both contingency and management reserves for the project
Cost of Quality
2.4.2 Estimate Costs TT
How much money it takes to do the project right
Benefit Cost Ratio
2.4.2 Estimate Costs TT
The amount of money a project is going to make versus how much it will cost to build it.
Net Present Value (NPV)
2.4.2 Estimate Costs TT
The actual value at a given time of the project minus all of the costs associated with it.
Opportunity Costs
2.4.2 Estimate Costs TT
The money you do not get because you chose not to do a project
Internal Rate of Return
2.4.2 Estimate Costs TT
The amount of money the project will return to the company that is funding it.
Depreciation
2.4.2 Estimate Costs TT
Rate at which your project loses value over time.