Procurement and tendering Flashcards
What is OJEU?
OJEU stands for the Official Journal of the European Union (previously called OJEC - the Official Journal of the European Community).
This is the publication in which all tenders from the public sector which are valued above a certain financial threshold according to EU legislation, must be published.
What are the OJEU financial thresholds?
New Thresholds for 2020
The Public Contracts Regulations 2015
Supplies & Services (not subsidised services contracts)
Central Government bodies (large lots) £122,976
Others (large lots) £189,330
Supplies and services (small lots; all sectors) £70,778
Works (large lots, all bodies) £4,733,252
Works (small lots, all bodies) £884,720
What are the different OJEU routes?
Open Restricted Competitive dialogue Negotiated with OJEU advert Negotiated without OJEU advert
What would you advise a public sector client on a project where there was not enough time to carry out an open tender procedure?
Use a framework
Who adopts the responsibility for obtaining statutory approvals in design and build procurement?
It depends on what is prescribed in the contract
What is a framework? What are the benefits of a framework?
A framework is an umbrella agreement where parties (usually 4) have signed up to agreed terms & conditions / rates. The benefits of this are it provides cost certainty, it provides mass buying power, and it has been competitively tendered and reduces the overall tender process.
What are the most commonly used procurement routes in the construction industry?
Traditional, DB, Construction Management, Management Contracting, Partnering
How do you deal with errors in a tender?
Firstly I would refer to JCT Practice Note 2017 where there is Alternative 1 – the contractor must stand by price or withdraw, or alternative 2 – the contractor is allowed to correct genuine errors. This would need to be stated in the ITT.
What is the standard period that a tender will remain open for?
90 days
What are the advantages and disadvantages of D&B?
It allows for early contractor involvement and a quick start on site. It also transfers design risk from the client to the contractor.
D&B client changes can be expensive and it requires the client to commit to a concept design early on.
Why choose Traditional procurement?
The most common method of procurement in the construction industry.
It is seen as the ‘least risk’ approach, as there is a level of certainty about design, cost and duration inherent in the strategy if it is properly implemented.
Under this method, design should normally be completed before competitive tenders are invited and before the construction contract is let. (There may be limited amount of contractor design as part of works specifically identified)
Construction costs can be determined with reasonable certainty before construction starts, which can be particularly attractive to clients with a strictly limited budget.
The client is responsible for the accuracy of the quantities stated in the pricing document (BoQ), although the client can transfer this risk to the contractor through the contract.
The contractor assumes responsibility and financial risk for the construction of the building works to the design produced by the clients team, for the contract sum agreed, and within the contract period.
The client takes responsibility and risk for the design and for the performance of the design team.
Advantages:
- Quality - client had direct influence on design, facilitating a high level of performance and quality
- reasonable price certainty
- competitive fairness, transparent, well known procedures
Disadvantages:
- if an effort is made to speed up the process by producing tender documents from an incomplete design, this can result in less cost and time certainty
- overall project duration may be longer than other routes, as construction cannot be commenced until design is finished
- no input on design by the contractor
Why choose Design and Build?
Under this route, a contractor assumes the risk and responsibility for designing and building the project.
As this route integrates design and construction, construction can start before all the detailed design is completed, and the overall project duration is thus reduced.
It is clearly established legal duty that the contractor must provide the employer with a building that is fit for purpose, which is a significantly higher duty than required under the traditional method, which is one due skill and care.
Advantages:
- Client only has one firms to deal with, giving a single point of responsibility.
- Client risk is reduced, contractor responsible for design and construction
- Integrated constructor contribution to the design
- Price certainty is generally obtained before the construction starts
- Project duration should be reduced due to overlapping activities
Disadvantages
- Quality may be compromised as the client relinquishes control to design and build contactor
- Design liability is limited by standard documents
- May result in less aesthetic appeal where price and space dictate how the budget is spent
- Clients can face difficulty in preparing and adequate and sufficiently comprehensive brief or employer’s requirements
- Client is required to commit to a concept design at an early stage
- Bids are difficult to compare, each design will be different and programme may also vary
Why choose Construction Management (Direct contracts with trade contractors)?
How it works
Under a construction management route, the client does not allocate risk and responsibility to a single main contractor. Instead, the client employs the design team with a construction manager to manage, programme and co-ordinate the design and construction activities.
Construction work is carried out by trade contractors, often specialists, through direct contracts with the client for work packages.
A package is made up of work for which one of the trade contractors is responsible: for example, foundations, concrete, electrical installation or decorating. These packages are tendered individually, for a lump sum price.
As the client bears much of the construction risk with this route, it is prudent for the client to have adequate risk management capability.
Why and why not
It has particular benefits for projects where there is a high degree of design innovations, and where design flexibility is needed throughout the project process as changes in design can be accommodated later than with some other route
Trade contractors and the construction manager are able to contribute to the design and to project planning.
There is a relative time-saving potential for the overall project time as the arrangement enables the design process to overlap with the construction process, and is therefore usually adopted when the clients primary objective is speed, the “fast track” route.
However this strategy offers little cost certainty because the cost of the trade packages will be unknown until that work is let, price certainty is not achieved until design and construction have advanced to the extent that all of the construction (trade) packages have been let.
An informed, pro-active client is required to operate such a strategy and the route relies upon the client selecting a skilful and committed team.
Why choose Management Contracting? (MC and direct contracts with C)
How it works
A management contractor is engaged to manage the whole of the building process.
Construction works are carried out by firms employer by the management contractor, referred to as works contractors.
Unlike Construction Management, the management contractor has direct contractual links to the works contractors and is responsible for all the construction works.
There is no contractual link between the employer and the works contractor
The client employs the design team and, therefore, bears the risk of that team delaying construction for reasons, such as the late receipt of design information.
The design work will not be entirely complete before the first works contractors start work, although the design necessary for those packages must be finished. As design is completed, subsequent packages of work are tendered and let.
Why and why not
It has particular benefits for projects where there is a high degree of design innovations, and where design flexibility is needed throughout the project process as changes in design can be accommodated later than with some other route
As the client bears much of the construction risk with this route, it is prudent for the client to have adequate risk management capability.
Works contractors and the Management Contractor are able to contribute to the design and to project planning.
There is a relative time-saving potential for the overall project time as the arrangement enables the design process to overlap with the construction process, and is therefore usually adopted when the clients primary objective is speed, the “fast track” route.
However this strategy offers little cost certainty because the cost of the work packages will be unknown until that work is let, price certainty is not achieved until design and construction have advanced to the extent that all of the construction packages have been let.
What guidance is available for tendering procedures?
RICS Blackbook has a guidance note on Tendering Strategies.