Contract practice Flashcards
What is the difference between SBCC DB 2011 and 2016?
The default dispute resolution forum has changed from litigation to arbitration.
The payment provisions have been overhauled.
Loss and expense. If a contractor is making a loss and expense claim, it will now have to also inform the employer of any further amounts likely to be incurred.
Not only that, the contractor will need to update that assessment and vouching at monthly intervals until all information required to assess the total amount
of loss and expense has been supplied.
This change is accompanied by a requirement on the employer to notify the contractor of the ascertained amount within
28 days of the initial assessment and every 14 days following an update - so a quick process if unamended.
Performance bonds and guarantees. The 2016 edition contains provisions which allow for a performance bond or parent company guarantee (or both!) to be provided to the employer.
Have you ever had to advise a client on the guarantees and bonds they may want to implement on their project?
During a contracts workshop with my client I advised on the advantages and disadvantages of performance bonds and parent company guarantees
I explained that both can be used as a means of protection in the event of contractor insolvency
Performance bonds typically cover 10% of the Contract Sum and usually cost circa 1% of the Contract Sum
- on demand bond or conditional
Parent company guarantees are free and cover the Full Contract
- however theses are reliant on the parent company stepping in if the sister company becomes insolvent
- need to consider the financial standing of the parent company
I am a client who is procuring their project via a D&B contract, however, I’m not sure whether I want to introduce a schedule of amendments. How would you advise?
Schedules of amendments must drafted by a Legal advisor, however I would provide examples of amendments used on similar projects
What factors would you consider before advising a client what contract to use?
the scope of works, complexity of the design, how much control they want to have over the design, the clients
budget, how much cost certainty they need, the timescales, how quickly they need to get to site, risk, market conditions
Who would you typically expect to obtain collateral warranties from on a project?
Third party specialist design responsibility.
Collateral Warranties provide a contractual link where there would otherwise be none. For example where a party should suffer a loss, or a contractor should go bust.
privity of contract
How is a contract executed?
A contract is executed under hand or under deed.
Under hand is a simple contract where it is signed and limitation periods are 6 years.
Under deed is where it is signed and witnessed and stated that it is under deed with limitation periods of 12 years.
What is the difference between Construction Management and Management Contracting?
Construction Management is when the client employs a construction manager to manage the work however the client retains the contractual link with the CM and works contractors.
Management contracting is when the client employs a management contractor who has the contractual link with the works contractors.
What types of bonds are you aware of?
Performance Bonds (on demand, default) retention bond, road bond, materials off-site bond
Nominated / Named sub-contractors?
Nominated sub-contractors were removed from JCT/SBCC 2011, however the client could get round this by nominating them in the specification.
Named sub-contractors the client must provide a minimum of 3 options.
What are the different types of insurances required for a new build or a refurbishment?
Option A – Contractor takes out insurance for new build
Option B – employers takes out insurance for new build
Option C – employer takes out insurance for refurb
What other insurances would the parties to the contract be required to have?
"Design Liability - Limit of Contractor’s liability for loss of use etc. (if any)" "Insurance - Personal Injury and Property Damage" "Contractor's Insurance – Liability of Employer" "Insurance of the Works and Existing Structures" Professional Indemnity Insurance "Cover for pollution/ contamination claims" Collateral Warranties
What is included in a letter of intent?
Scope of Works, Contract sum, Contract Period, method of dispute resolution, what should happen should the contract not be executed
What is Assignment?
Assignment is the right to transfer ‘choses in action’ defined as ‘all personal rights of property which can only be claimed or enforced by action and not by taking physical possession’.
This definition includes benefits arising under a construction contract such as right to payment, but not burdens such as the obligation to pay.
What is Novation?
Novation is a process by which contractual rights and obligations are transferred from one party to another. Whilst the benefits of a contract can be transferred by assignment, if the parties wish to transfer both the benefits and the burdens then this must be done by a novation agreement.
This is common on design and build projects where the design team are appointed by a client to carry out initial studies or prepare a concept or detailed design, but then when a contractor is appointed to carry out or complete the design and construct the works, the design team (or part of it) is novated to work for them, as happened on Inverclyde.
This can be beneficial to clients as it maintains continuity between pre-tender and post-tender design whilst leaving sole responsibility for designing and building the project with the contractor.
How would your client appoint a design team
Whatever the process of selecting potential consultants, agreeing the scope of services and fee for the appointment will generally require that the client prepares some form of ‘request for proposals’.
Standard form of appointment include:
- JCT PCSA
- JCT Consultancy Agreement
- NEC PCSA
- RIBA Standard form of Appointment for an Architect