Contract administration Flashcards
Have you valued a loss and expense claim, can you tell me how you’ve done that?
Start with Relevant Matter, check if this is correct, what are they submitted, heads of claims, check the contract - what does that allow for these heads of claims and its actuals
a) Prolongation (extra site overheads i.e. preliminaries)
b) Thickening of preliminaries (e.g. extra supervision required due to variations)
c) Disruption (causing plant / labour to be underemployed – hard to prove)
d) Increases in labour / material costs during the period of delay
e) Head office overheads
f) Loss of profit (commonly combined with head office overheads)
g) Finance charges (i.e. interest)
h) Acceleration costs
i) Claim preparation costs
“RICS guidance note - Interim valuations and payment
Can you briefly describe what areas this publication covers?
General principles, practical applications and considersations of interim valuations, certificates, notices, payment mechanisms, retention and the likes
You mention in our summary of experience that you have acted as an EA and have issued payment notices within the relevant timescales. Can you explain these timescales for an unamended SBCC D&B contract.
The contractor must submit their application for payment on the due date/ (interim valuation date 2016) then payment notice must be issued within 5 days of the due date then final date for payment is 14 days from the due date
What’s the difference between SBCC with Quants and D&B when looking at Due dates?
If the contractor doesn’t submit the QS has a duty to value the works.
What is in a PEP?
Description of the project Roles and responsibilities for all involved Communication procedures Change Control procedures Quality management procedures H&S procedures Risk Management
How would you assess an Extension of Time Claim? How long do you have to assess an EOT claim under the contract? If it has gone past the completion date, what do you do?
I would ascertain if the claim was aligned to a relevant event within the contract and then review the contract programme against the as-built programme accordingly and carry out a critical path analysis and then adjust the contract completion date if required. Under the contract you have 12 weeks to assess an EOT claim however if it has gone past the completion date you must issue a certificate of non-completion and assess the EOT as soon as practically reasonable.
What is the difference between PM / CA / EA ?
A PM is not named in SBCC contracts only NEC, however in these contracts a PM would be more involved with management and processes.
A CA administers the terms and conditions of the contract on behalf of the client and has a duty to act impartial.
An EA excecutes the contract on behalf of and acting as the Employer.
What are the main SBCC Contract suite?
JCT SBC with and without quantities JCT D&B JCT Intermediate JCT Major Works JCT Minor Works
Why use a standard contract?
Standard forms are contracts drafted with the intention of providing a set of standardised terms and conditions for employers and contractors to contract upon.
Using standard forms should save parties time and money because they are not drafting and negotiating bespoke contracts.
Another benefit of using a standard form is that a professional will become familiar with the terms and conditions over time, and understand the risk allocation within those contracts.
Tell me about the role of the contract administrator from when their involvement starts and finishes.
The role of the CA does not technically begin until a building contract is in place between the employer and the contractor.
The CA is responsible for administering the terms of the contract.
The CA will act as the agent of the employer in certain circumstances but when certifying or giving an assessment or decision, they should act in an impartial manner.
The key CA tasks are:
- Chairing meetings
- Inspecting the works
- Giving instructions, including variation and change orders
- Determining extension of time applications
- Authorising interim payments
- Certifying the date of completion
- Settling the final account
What are the various certificates that the Contract Administrator issues?
Interim Certificates Final Certificate Instructions Practical Completion Certificate Certificate of Making Good
What is the administrator of the contract called on SBCC D&B contract?
Employers Agent
What does the Practical Completion certificate trigger?
Certifying practical completion has the effect of:
- Releasing half retention
- Ending contractor’s liability for LAD
- Beginning the rectification period
What does the client/employer need to have in place once PC cert is issued?
Another key effect of PC is the liability to insure the project. Once PC is certified, the risk of loss or damage to the works passes from the contractor to the employer.
It is therefore necessary to insure the works.
What is classified as a defect?
Defects are aspects of the works that are not in accordance with the contract.