Processes for Predictive Projects: 2 Planning Flashcards
Project Management Plan
(18 components)
14 plans:
1. Scope Management Plan
2. Requirements Management Plan
3. Schedule Management Plan
4. Cost Management Plan
5. Quality Management Plan
6. Resource Management Plan
7. Communications Management Plan
8. Risk Management Plan
9. Procurement Management Plan
10. Stakeholder Engagement Plan
11. Change Management Plan
12. Configuration Management Plan
13. Project Life Cycle Description
14. Development Approach
4 Baselines:
15. Scope Baseline
16. Schedule Baseline
17. Cost Baseline
18. Performance Measurement Baseline
Gold Plating
doing extra work not in the scope
Scope Management Plan
How the scope will be defined, developed, monitored, controlled and verified
Requirement Management Plan
How the requirements will be
analyzed, documented and managed
OUTPUT of “Plan Scope Management”
Requirement Traceability Matrix
A table that links requirements back to it source + goes into further detail + current status
OUTPUT of “Collect Requirements”
Requirements Documentation
How individual requirements are to be performed and why each requirement is important to the project.
OUTPUT of “Collect Requirements”
Project Scope Statement
Describes in detail the project deliverables
Where we get our deliverables!!
Output of “Define Scope”
WBS = Work Breakdown Structure
Decomposing deliverables from scope statement into more manageable components.
if it is not in the WBS, it is not part of the project
Project Name > Control Account > Work Package . Activities
WBS Dictionary details the
contents of the WBS (team member, time, cost, ID #, etc.)
3 Components of Scope Baseline
- Project Scope Statement
- WBS
- WBS Dictionary
Schedule Management Plan
How the schedule will be planned, developed, managed, executed, and controlled throughout the phase or project
OUTPUT of “Plan Schedule Management”
Rolling Wave Planning
Decomposing activities as you go/in waves
Near-term work packages can be defined in much greater detail. You shouldn’t plan for activities 2 years from now.
TOOL of “Define Activities”
Activity List
A complete list of all scheduled activities that is required to be perform on the project.
Work packages come from scope, and activities come from those work packages.
Activities are used to build the schedule.
Project Name > Control Account > Work Package > Activities –> Schedule
OUTPUT of “Define Activities”
Activity Attributes
Any additional information required to execute the Activity list
OUTPUT of “Define Activities”
Milestone List
Key dates of the projects
OUTPUT of “Define Activities”
Precedence Diagramming Method (PDM)
Precedence = order/sequence
Diagram that represents the flow of work packages
A > B > C > D
TOOL in “Sequence Activities”
When sequencing activities, there are 4 relationships between activities:
- Finish to Start - finish 1 activity, start the next
- Finish to Finish - you want 2 activities to finish at the same time
- Start to Start - you want 2 activities to start at the same time
- Start to Finish - start 1 activity, finish another
Sequencing activities - there are many ways 1 activity affects the next
Dependency Determination: Mandatory Dependencies (Hard Logic)
When one activity must be done for the other one to start
Ex: Paint must be purchased before painting the walls
Sequencing activities - there are many ways 1 activity affects the next
Dependency Determination: Discretionary Dependencies (Soft Logic)
Activity is not dependent on the completion of another; can be done simultaneously
Ex: Painting the walls of a room and laying carpet at the same time
Sequencing activities - there are many ways 1 activity affects the next
Dependency Determination: External Dependencies
activity is dependent on something outside the control of project team
Ex: The Home Improvement store down stocking the paint prior to you buyi
Sequencing activities - there are many ways 1 activity affects the next
Dependency Determination: Internal Dependencies
activity is dependent on something within the control of project team
Leads vs Lags when sequencing activities
A lead is an overlap; succeeding activity can start a little early
A lag is a delay for next activity to start
Project Schedule Network Diagrams
Drawings which shows the entire project work packages/activities from start to finish + their logical relationship
START > A > B/C > D > E > FINISH
Activity > Schedule Network Diagrams > Duration > Schedule
OUTPUT of “Sequence Activities”
In estimating activity durations and cost…
Analogous Estimating
(top-down)
Copy/paste from previous projects
Least accurate
Costs less
Using historical information to predict how long something will take
In estimating activity durations and cost…
Bottom-Up Estimating
More accurate
More time-consuming
Breaks down the work to the lowest levels and then aggregating the work back up to find an overall duration
In estimating activity durations and cost…
Parametric Estimating
Uses a statistical relationship between historical data and other variables (parameters); an algorithm
You have parameters to calculate an estimate.
Ex: 200 ft x 5 min/ft
In estimating activity durations…
3-Point Estimate
(AKA PERT)
Utilizes 3 values when calculating how long/much an activity should take:
Optimistic, Realistic, Pessimistic
PERT = Project Evaluation and Review Technique
3-Point/PERT Estimate:
Beta distribution
(O + R(4) + P) / 6
Optimistic, Realistic, Pessimistic
3-Point/PERT Estimate:
Standard Deviation
(P - O) / 2
Optimistic, Realistic, Pessimistic
(Ex. Estimate is plus or minus this value)
3-Point/PERT Estimate: Triangle distribution
(O + R + P) / 3
Optimistic, Realistic, Pessimistic
(Weighted average)
Reserve Analysis
Aka buffer time/cost
Schedule Network Analysis
Using several different techniques to determine the length of the schedule.
It is used to calculate the early start and early finish dates, late start and late finish dates
Techniques: Critical path, Critical Chain, What-if analysis, and resource optimization techniques
Resource Optimization Techniques
Ways of flattening/leveling the schedule so resources are distributed evenly/fairly
Schedule Network Analysis:
Critical Chain
A method of planning and managing projects that puts more emphasis on the resources required to execute project tasks developed