Earned Value Management - Monitoring Cost & Schedule Flashcards

1
Q

BAC

A

Budget at Completion: Original budget of the project

No formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

Planned Value: amount of work that SHOULD be done at this point

PV = Planned % Complete x BAC

Ex: (⅗ days in) x $100 = $60

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV

A

Earned Value (EV): Amount of money worth of work you actually did on the project (not necessarily the money spent though)

EV = Actual % Complete x BAC

Ex: (actually 75% complete) x $100 = $75

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC

A

Actual Cost (AC): Amount of money you already spent on the project

No formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance (CV): Work done vs actual money spent

CV = EV - AC

Positive = under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

Cost performance index: spend rate %

CV = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

Schedule Variance: How much work we should have done vs. how much work you actually did

Positive = ahead of schedule

SV = EV - PV

Ex: $75 - $60 = $15 worth of work you’re ahead of sched by

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

Schedule Performance Index: The rate (%) of how we are meeting the project schedule.

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

Estimate at Completion: Forecasting the total cost of the project at the end based on the current spending rate of the project.

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC

A

Estimate to Completion: How much more $ will be needed to complete the current project

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

A

Variance at Completion: The difference between the original budget and new forecasted budget.

Postive = under budget!

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To-Complete Performance Index: How hard you have to work to finish the project within the budget. Over 1 = work harder

TCPI = (BAC – EV) / (BAC – AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly