Processes Flashcards
How many processes?
Seven
What is a process?
A structured set of activity ties designed to accomplish a specific objective
Directing a Project Process
Number one
Project board sets direction and makes key decisions
Starting up a project process
Number two.
Triggered by project mandate, verifies project is worthwhile and viable, writes project brief.
Project board reviews project brief and decides whether to initiate, states levels of authority
Initiating a project
Number three
Detailed planning. Project manager develops strategies and control, Business Case and means of reviewing benefits in the Project Initiation Documentation.
Managing a stage boundary - plans first stage from project plan.
Controlling a stage
Number four
Project Board delegates control on stage plan by stage plan basis to Project Manager. Project plan broke into stage boundaries.
Project Manager role - keep progress in line with stage plan and agreed tolerances, informs progress through highlight reports
Managing product delivery process
Number five
Team manager / members execute Work Packages and update Project Manager with Checkpoint Reports
Managing a stage boundary
Number six
Project Manager seeks permission for next stage by preparing the next Stage Plan, update on Business Case and Project Plan
Closing a project process
Number 7
Project board is satisfied with products, project can close. Documentation archives, assess project performance against original plan
Processes?
- Directing a project process
- Starting up a project process
- Initiating a project process
- Controlling a stage process
- Managing project delivery process
- Managing a stage boundary process
- Closing a project process