Process Groups Flashcards

1
Q

4 Project Integration Management (7)

A
  • Develop Project Charter (I)
  • Develop Project Management Plan (P)
  • Direct and Manage Project Work (E)
  • Manage Project Knowledge (E)
  • Monitor and Control Project Work (MC)
  • Perform Integrated Change Control (MC)
  • Close Project or Phase (C)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

5 Project Scope Management (6)

A
  • Plan Scope Management (P)
  • Collect Requirements (P)
  • Define Scope (P)
  • Create WBS (P)
  • Validate Scope (MC)
  • Control Scope (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

6 Project Schedule Management (6)

A
  • Plan Schedule Management (P)
  • Define Activities (P)
  • Sequence Activities (P)
  • Estimate Activities Durations (P)
  • Develop Schedule (P)
  • Control Schedule (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7 Project Cost Management (4)

A
  • Plan Cost Management (P)
  • Estimate Costs (P)
  • Determine Budget (P)
  • Control Cost (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

8 Project Quality Management (3)

A
  • Plan Quality Management (P)
  • Manage Quality (E)
  • Control Quality (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

9 Project Resource Management (6)

A
  • Plan Resource Management (P)
  • Estimate Activity Resources (P)
  • Acquire Resources (E)
  • Develop Team (E)
  • Manage Team (E)
  • Control Resources (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

10 Project Communication Management (3)

A
  • Plan Communications Management (P)
  • Manage Communications (E)
  • Monitor Communications (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

11 Project Risk Management (7)

A
  • Plan Risk Management (P)
  • Identify Risk (P)
  • Perform Qualitative Risk Analysis (P)
  • Perform Quantitative Risk Analysis (P)
  • Plan Risk Responses (P)
  • Implement Risk Responses (E)
  • Monitor Risks (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

12 Project Procurement Management (3)

A
  • Plan Procurement Management (P)
  • Conduct Procurements (E)
  • Control Procurements (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

13 Project Stakeholder Management (4)

A
  • Identify Stakeholders (I)
  • Plan Stakeholder Engagement (P)
  • Manage Stakeholder Engagement (E)
  • Monitor Stakeholder Engagement (MC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly