Formulas Flashcards

1
Q

Earned value analysis (EVA)

A

Earned value analysis compares the performance measurement baseline to the actual schedule and cost performance. EVM integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline. EVM develops and monitors three key dimensions for each work package and control account:

Planned value (PV) is the authorized budget assigned to scheduled work.

Earned value (EV) is a measure of work performed expressed in terms of the budget authorized for that work.

Actual cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule variance (SV)

A

Schedule variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value.

SV = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost variance (CV)

A

Cost variance (CV) is the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost.

CV = EV – AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule performance index (SPI)

A

The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value.

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost performance index (CPI)

A

The cost performance index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost.

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

To-complete performance index (TCPI)

A

The to-complete performance index (TCPI) is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.

TCPI based on BAC: (BAC – EV) / (BAC – AC)

TCPI based on EAC: (BAC – EV) / (EAC – AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Budget at Completion (BAC)

A

The budget at completion (BAC) is the sum of all budgets established for the work to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate to complete (ETC)

A

The estimate to complete (ETC) is the expected cost to finish all the remaining project work.

ETC = EAC – AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at completion (EAC)

A

The estimate at completion (EAC) is the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

EAC = AC + BAC – EV

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Number of communication channels

A

n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly