Process and Knowledge Area Mapping (Belong to) Flashcards
What process group does 4.1 DEVELOP PROJECT CHARTER belong to?
Initiating
What process group does 4.2 DEVELOP PROJECT MANAGEMENT PLAN belong to?
Planning
What process group does 4.3 DIRECT AND MANAGE PROJECT WORK belong to?
Executing
What process group does 4.4 MANAGE PROJECT KNOWLEDGE belong to?
Executing
What process group does 4.5 MONITOR AND CONTROL PROJECT WORK belong to?
Monitoring and Controlling
What process group does 4.6 PERFORM INTEGRATED CHANGE CONTROL belong to?
Monitoring and Controlling
What process group does 4.7 CLOSE PROJECT OR PHASE belong to?
Closing
What process group does 5.1 PLAN SCOPE MANAGEMENT belong to?
Planning
What process group does 5.2 PLAN SCOPE MANAGEMENT belong to?
Planning
What process group does 5.3 DEFINE SCOPE belong to?
Planning
What process group does 5.4 CREATE WBS belong to?
Planning
What process group does 5.5 VALIDATE SCOPE belong to?
Monitoring and Controlling
What process group does 5.6 CONTROL SCOPE belong to?
Monitoring and Controlling
What process group does 6.1 PLAN SCHEDULE MANAGEMENT belong to?
Planning
What process group does 6.2 DEFINE ACTIVITIES belong to?
Planning
What process group does 6.3 SEQUENCE ACTIVITIES belong to?
Planning
What process group does 6.4 ESTIMATE ACTIVITY DURATIONS belong to?
Planning
What process group does 6.5 DEVELOP SCHEDULE belong to?
Planning
What process group does 6.6 CONTROL SCHEDULE belong to?
Monitoring and Controlling