Misc Definitions Flashcards

1
Q

Activity

A

Discrete unit of work to be performed. It should be measurable, one resource (i.e. painting not patching), specific, and no interruptions (meaning not reliant on someone/thing else like writing and publishing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Milestone

A

Measurement point or event. Have zero duration. Example - contract approved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Rolling wave planning

A

Used often in agile. Form of progressive elaboration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Risks

A

Potential positive or negative impacts to the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PMI Talent Triangle

A

Technical project management; Leadership; Strategic and business management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Analogous estimating

A

Used in preliminary estimating. Most common type. Top-down estimating that begins with information from prior project and supplements with information from the team and SMEs. Adjust for differences in new project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Parametric estimating

A

Used in preliminary estimating. Uses known values and multiples them by a variable. Known values could be published rates, number of gallons, etc. Works best with tangible outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Three-point estimating

A

Used in budgetary estimating. Three estimates: optimistic, pessimistic, most likely. Perform weighted calculation. PERT formula: PERT = (O + 4ML + P) / 6 where O = optimistic, ML = most likely, and P = pessimistic. Represent a 50% confidence level. Expected = 50% confidence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Delphi estimating

A

Used in budgetary estimating. Obtain one estimate, most likely, from multiple people. Mitigates estimator bias and is consensus based. Done over rounds to reach consensus, each round throw out high and low.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Definitive estimates

A

Bottom-up estimating technique performed immediately preceding the scheduled work, sometimes referred to as a two-week look-ahead. Most accurate. Associated with implementation phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Triple constraint (of quality)

A

Scope, time, cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Performance Measurement Baseline (PMB)

A

Another term for cost baseline used when using Earned Value Management (EVM). Time-scaled project budget. Can’t be changed without approval. Integrates scope, cost, and schedule baselines into one. Used to compare actual performance to planned performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

S-Curve

A

Projects generally start with low cost, then increase, then level out. When graphed, it looks like a lazy S shape

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Budget at Completion (BAC)

A

Budget completed in time (at 10 weeks) and by money ($10,000). Marks end point for completion. Represents the planned budget at completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Planned Value (PV)

A

The dollar value of work planned as of that point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Earned Value Analysis (EVA)

A

Determines how well project is progressing by measuring work plan, work performance, and actual spending. Includes 4 elements: Planned Value (PV), Budget at Completion (BAC) aka cumulative planned value, Earned Value (EV) aka how much work has been completed, Actual Cost (AC) aka how much was spent to complete the work

17
Q

Earned Value (EV)

A

How much work has been completed

18
Q

Actual Cost (AC)

A

How much was spent to complete the work

19
Q

Data date or time now

A

Point in time Planned Value, Earned Value and Actual Cost are measured. Before the time now, it does not have a planned value (history) after the time now it does have planned value

20
Q

Variance

A

Difference between planned and actual performance. Can be favorable or unfavorable

21
Q

Estimate at Completion (EAC)

A

Revised Budget at Completion (BAC) taking Time Now statuses into account

22
Q

Estimate to Complete (ETC)

A

Amount of additional funds needed to get to EAC based on how much spent so far and how much work remains

23
Q

Earned Schedule (ES)

A

Schedule equivalent of Earned Value. Look at EV compared to PV and where it falls on the schedule. For example may be at week 5 but only completed work equivalent to week 4. Minor concept.

24
Q

Prevention Costs

A

Money spent to avoid quality problems

25
Q

Appraisal Costs

A

Money spent on measuring and monitoring quality activities such as running tests or audits