Formulas Flashcards
Schedule Variance (SV) Formula
SV = EV - PV (Schedule Variance = Earned Value - Planned Value)
EV>PV = ahead of schedule, favorable
EV
Cost Variance (CV)
CV = EV - AC (Cost Variance = Earned Value - Actual Cost)
EV>AC = under budget, favorable
EV
Schedule Performance Index (SPI)
SPI = EV/PV (Schedule Performance Index = Earned Value divided by Planned Value)
Greater than 1.0 = better than planned productivity
Less than 1.0 = worse than planned productivity
Expressed as decimal or percentage (i.e. 87% of planned productivity)
Cost Performance Index (CPI)
CPI = EV/AC (Cost Performance Index = Earned Value divided by Actual Cost)
Greater than 1.0 = better than planned spending efficiency
Less than 1.0 = worse than planned spending efficiency
Expressed as decimal (i.e. .96 means we are getting 96 cents in value on every dollar spent)
Estimate at Completion Cost (EAC) with Typical Variance (i.e. forces beyond PM control)
EAC = BAC / CPI (Estimate at Completion = Budget at Completion divided by Cost Performance Index)
Original compared to spending efficiency
Estimate at Completion Schedule (EAC) with Typical Variance (i.e. forces beyond PM control)
EAC = BAC / SPI (Estimate at Completion = Budget at Completion divided by Schedule Performance Index)
Original compared to productivity
Estimate at Completion Cost (EAC) with Atypical Variance (i.e. forces within PM control like learning curve or event unlikely to recur)
EAC = AC + (BAC - EV) (Estimate at Completion = Actual Cost + (budget at completion - earned value)) aka expenses incurred to date plus remaining expenses