Predictive PMP Terms Flashcards
8/80 Rule
each work package should take between 8 hours and 80 hours in order to avoid work packages being too narrow or too broad
Accelerated Depreciation
depreciates faster than straight-line depreciation
Acceptance Response
passively accepting a threat or opportunity (risk) by doing nothing other than creating a contingency plan and allocating time and cost reserves
Acceptance Terms and Conditions
in a contract, how you will know work is acceptable
Acceptance Test
- represents some expected result from the system
- customers are responsible for verifying the correctness of the acceptance tests and reviewing test scores to decide which failed tests are of highest priority
Acknowledgement
- in the communication model, confirmation of receipt of a message
- does not indicate agreement with message
Active Job Shadowing
shadow employee and ask questions or try work to gather requirements
Activity
- a particular piece of work scheduled for a project
- you should expect to manage to the activity level as a project manager
Activity-on-Node (AON)
- type of network diagram that shows flow of project with precedence diagramming method
- predecessors are upstream and successors are downstream
- activities are nodes that are connected with arrows
Actual Cost
as of today, what is the actual cost incurred for the work accomplished?
Administrative Closure
- when closing a project, make sure
- deliverables are signed off on
- close project accounts
- reassign personnel
- deal with excess material
- reallocate facilities and other equipment
- create final reports
- index lessons learned and other historical records
Affinity Diagrams
- ideas generated by other requirements gathering techniques grouped by similarity
- each group is given a title which makes it easier to see additional areas of scope or risk that have not yet been identified
Agent Terms and Conditions
in a contract, who is an authorized representative of each party
Agreement
- documents or communications that outline internal or external relationships and their intentions
- not all agreements are contracts
- the charter and project management plan are examples of agreements that aren’t contracts
Ambiguity Risks
- risks caused by lack of understanding
- type of non-event based risk
Analytical Management Style
- depends on manager’s own technical knowledge and ability project managers often make the technical decisions for the project and then communicate those decisions to their team
- effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
Apportioned Effort Activities
activities that support the project, such as quality assurance and integrated change control
Arbitration Terms and Conditions
- in a contract, method to resolve disputes by third parties
- usually paid for by the parties and generally faster and cheaper than the courts
Assignable Cause (Special Cause Variation)
a data point or series of data points require the project manager to investigate the cause of the variation
Assignment Terms and Conditions
in a contract, refers to the circumstances under which one party can assign its rights or obligations under the contract to another
Assumption Testing
- in identify risks, use what-if analysis to determine if assumption is valid or not
- will assumption cause delay or extra costs?
- is the information the assumption is based on reliable?
Assumptions
- what is believed to be true about the project but is not a fact; incorrect assumptions introduce risk and thus they are recorded in the assumption log
- examples are team member availability and that they will do a good job
Authority Terms and Conditions
in a contract, who has the authority to do what
Autocratic Management Style
- top-down approach; manager may coach or delegate, but everyone does what the manager says
- can create challenges for project team
Autocratic Voting
single person is assigned to make decision for entire group
Avoiding Power
project manager refuses to act or get involved
Balanced Matrix
- power is shared between functional manager and project manager
- project manager is often part-time and manages a part-time team
- team members report to project manager and functional manager
- may have part-time administrative help
- project manager and functional manager share authority over staff and budget
Barriers
- in the communication model, anything that completely blocks communication
- more than just noise
Beneft to Cost Ratio
- in project selection, compares the cost of the project to the expected benefit (revenue) it could bring
- greater than one = benefit outweighs the cost
- less than one = cost outweighs the benefit
- the ratio is how many times over the revenue outweighs (or does not) the cost
- example: a benefit to cost ration of 1.7 means the revenues brought in by the project are 1.7 times the cost
Bid (Quotation)
- from seller to buyer
- price is the determining factor in the decision making process
Bidder Conference
- meeting in which the seller gets to ask questions of the buyer and gather information about the buyer
- all questions and answers are documents and added as addenda to bid documents.
Bonds Terms and Conditions
- in a contract, payment or performance bonds that must be purchased
- ex: a payment bond would protect the buyer from claims of nonpayment by the seller
Breach/Default Terms and Conditions
- in a contract, occurs when any obligation of a contract is not met
- a breach on the seller’s part cannot be fixed by a breach on the buyer’s part
- for example failure to complete an item in the SOW cannot be handled by the buyer stopping all payments
Budget at Completion (BAC)
how much did we budget for the total project effort?
Budget Estimate
- based on scope
- more accurate than ROM but not as accurate as definitive estimate
- narrowed range before you begin iterating the plan
- typically in the range of -10% to +25%
Bureaucratic Management Style
- following procedures exactly
- effective for work in which details are critical or when specific safety or other regulations must be strictly adhered to
Business Requirements
higher-level needs of the organization
Ceiling Price
in a contract, the highest price a buyer will pay
Centralized Contracting
- there is one procurement department and procurement manager reports organizationally to the head of the procurement department and not the project manager
Change Control System
- part of PMIS
- standardized forms, reports, processes, procedures, and software for managing change requests
Changes Terms and Conditions
in a contract, how changes will be made, what forms will be used, and what are the timeframes for notice and turnaround
Charismatic Management Style
- energize and encourage their teams in project work
- in this style, project success may become dependent on the presence of a charismatic leader, with the team relying on the leader for motivation
- can create challenges for project team
Checklists
when the same work is done repeatedly, checklists ensure the work is done the same way each time
Coaching Management Style
project manager advises and makes recommendations, helping the team and other stakeholders achieve their goals
Code of Accounts
numbering system assigned to control accounts in the WBS
Collaborative Problem Solving
- team members will work together to resolve conflict
- it does not matter who is right or who is wrong
- win/win situation
- preferred method for PMI
Commercial Risks
- customer stability, terms, and conditions within the project vendors
Communication Blockers
- factors that cause miscommunication and can lead to disagreement, such as noisy surroundings, distance between those trying to communicate, improper encoding, language differences, cultural differences
Communication Channels
- when you add one more person to the team, there is a substantial increase in communication channels, not just one
- n = the number of stakeholders
- n(n – 1 ) / 2
Composite Organization
- made up of multiple organizational structures
- an example is one where the organization is mostly functional but creates a project team where the project manager has the authority to accomplish a temporary result
- do not confuse with hybrid organization
Compromising/Reconciling Problem Solving
- neither party gets what they want
- lose/lose situation
Confidentiality Terms and Conditions
in a contract, what information should not be given to third parties
Configuration Identification
identification and documentation of the product and its components
Configuration Status Accounting
- documentation of the product information
- includes the metrics and specifications that the customer will inspect against
Configuration Verification and Auditing
concerned with performance and functional attributes of the product; is the functionality acceptable?
Connectivity Risk Parameter
indicates how one risk is connected to another risk
Consensus Approach
achieves general agreement about a decision and those who prefer a different option are willing to accept the decision supported by most members of the group
Consensus Management Style
- project manager encourages problem-solving in a group and makes decisions based on group agreement
- effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
Constraints
- factors that limit options such as time, cost, risk, scope, quality, resources, customer satisfaction
- can be policies and procedures, regulations, predetermined budgets and schedules, resource utilization, requirements, and approaches to work
- use them to evaluate competing demands
- management either directly or indirectly sets priority of constraints
- consider how changing one constraint affects another
- changes to the project generally impact multiple constraints
Consultative Management Style
- bottom-up approach
- uses influence to achieve results
- project manager considers others’ opinions and acts as servant-leader to team
- effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
Context Diagram
- used to define and model scope
- shows boundaries of product scope by highlighting the product and its interfaces with people, processes, or systems
- shows flow of data through a system and actors
Contingency Reserves
- typically associated with cost
- reserves allocated for the identified risks remaining after the Plan Risk Responses process – think of these as known unknowns
- they are included in the project schedule (or cost) baseline
- developed by looking at identified risks, multiplying the probability of the risk happening (decimal) by the financial impact (dollars), which yields the expected value of each risk
- adding all of the expected values is the how the contingency reserve is calculated
Contingent Risk Responses
- fall-back plan for worst-case scenario
- document triggers for this contingency plan
Contract
- a type of agreement that can be written or verbal
- created with an external entity and involve exchange of goods or services for some type of compensation
Control Account
- tool that allows you to collect and analyze work performance data regarding costs, schedule,and scope at a higher level than a work package
- control account usually has more than one work package assigned to it, but a work package is assigned to only one control account
- assigned unique identifiers with the code of accounts
Controlling PMO
- provides support and guidance in the organization on how to manage projects
- trains others in project management and related systems
- assists with specific project management tools
- ensures compliance to organizational practices and through framework and governance
- can coordinate and prioritize all projects within the organization
- moderate level of control
Corporate Knowledge Base
- indexed historical records and lessons learned from previous knowledge and is available to all
- a knowledge base is an OPA
Corrective Action
- brings project performance in line with the baselines established in the project management plan
- result of deviation from the project performance measurement baseline
- requires a change request to implement
Corrective Action Change Requests
- bring expected future project performance in line with project management plan
- typically undertaken to adjust performance within the existing baselines but do not change the baselines
Cost
- how much an item costs the seller to create, develop, or purchase
- buyer’s costs include the seller’s cost and profits
Cost Contract
cost-reimbursable contract that provides for payment to the seller of actual costs plus a negotiated fee fixed before work begins
Cost of Prevention
- what is the cost of preventing a risk versus the cost of the impact, considering also how likely it is for risk to happen and other possible costs of a risk such as schedule delays
Cost of Quality (COQ)
- ensuring project is not spending too much to achieve a particular level of quality
- costs of conformance should be lower than costs of nonconformance; includes prevention, appraisal—time and money to audit and evaluate, and failure—the cost of non-conformance such as redoing work and fines
Cost Plus Award Fee Contract (CPAF)
- a type of incentive contract in which the buyer pays all costs and a base fee plus an award amount (bonus) based on performance
- similar to CPIF but the incentive is a potential award and there is no possibility of a penalty
- award amount is usually determined in advance and apportioned depending on performance
Cost Plus Fee (CPFP)/Cost Plus Percent of Costs (CPPC) Contracts
- require the buyer to pay for all costs plus a percentage of costs as a fee
- generally not allowed for government contracts
- bad for buyers because seller profit is based on a percentage of everything billed—no incentive to control costs
Cost Plus Incentive Fee Contract (CPIF)
a cost-reimbursable contract that provides for seller to be paid for actual costs plus a fee that will be adjusted based on whether specific performance objects stated in the contract are met * original estimate is made (target cost) and a fee for work is determined (target fee)
Cost Variance (CV)
- difference between the earned value and the actual cost
- shows variance in cost; the negative is over budget
- positive is under budget
- EV = earned value
- AC = actual cost
- CV = EV – AC
Cost-Reimbursable Contract (CR)
- used when the exact scope of work is uncertain and thus costs cannot be estimated accurately enough to use a fixed-price contract
- provides for the buyer to pay the seller allowable incurred costs to the extent prescribed
- requires seller to have an accounting system that can track costs by project
- buyer has the MOST risk because of the unknowns
- seller provides an estimate but it’s not binding
- research and development and information technology projects in which the scope is unknown are typical examples
Crashing
- adding or adjusting resources in order to compress the schedule while maintaining the original project scope
- always results in increased cost, may result in increased risk
trades time for money, and law of diminishing returns must be considered
Critical Path
- longest duration path or paths through a network diagram and thus determines the shortest time it could take to complete the project
- there can be multiple criticals paths but that increases risk
- activities on the critical path have zero float unless they are completed earlier OR they are behind and have negative float
- cannot leave project with negative float – must compress schedule
- if schedule cannot be compressed, must adjust baseline
Dangerous Stakeholders
- in salience model of stakeholder assessment, dangerous stakeholders possess both power and urgency
- type of expectant stakeholder
- they can have disastrous impacts on a project
Decentralized Contracting
- there is no procurement department and the project manager may be responsible for conducting and monitoring all work on procurements.
Decoding
- in the communication model, translating the message into meaningful thoughts and ideas
Dedicated Teams
- most of the team members work full-time exclusively for the project
- easiest form of team to work with as team members can dedicate most of their energy to the project and often directly report to the project manager
- most common in projectized organizations
Defect Repair
- rework
- modifies nonconformance to project requirements
- requires a change request
Defect Repair Change Requests
rework if component of project does not meet specifications
Definitive Estimate
- most refined estimate as a result of planning process
- typically +/- 10%
Delegating Management Style
- project manager establishes goals and then gives the project sufficient authority to complete the work
- for basic project management, the manager involves the team in the planning process and assigns or delegates planning and executing work to team members
Urgent Stakeholders
- in the salience model of stakeholder analysis, urgent stakeholders have significant interest but not legitimacy or power
- type of latent stakeholder
- often a squeaky wheel
Demanding Stakeholders
- in salience model of stakeholder assessment, they possess all three attributes – urgency, power, and legitimacy
Deming’s PDCA
Plan, Do, Check, Act in quality management
Democratic (Participative) Management Style
- encouraging team participation in the decision-making process
- team members “own” the decisions made by the group, resulting in improved team cooperation
- effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
Dependent Stakeholders
- type of expectant stakeholder
- in the salience model of stakeholder assessment, dependent stakeholders have legitimacy and urgency but not power
- often depend on dominant stakeholders for their interests in project
Design Statement of Work
- conveys exactly what work is to be done, including materials used and how work should be completed
- often used for construction and equipment purchases
Detectability Risk Parameter
indicates how easily the risk can be detected
Development Life Cycle
- phases of the project associated with the producing the product, service, or result of the project
- development life cycle performed within the project life cycle
- predictive development life cycle/waterfall
- iterative development life cycle
- incremental development life cycle
- hybrid development life cycle
Direct Costs
costs that can be directly attributed to the work on the project, such as wages, materials, and team travel
Directing Management Style
project manager uses expertise to guide team members in what to do
Directive PMO
- prioritizes projects
- provides project managers and manages all projects throughout the organization
- responsible for results of projects
- high level of control
Discrete Effort Activities
- activities that are required to complete the project scope
- focused on creating the deliverable
Discretionary Stakeholders
- in the salience model of stakeholder assessment, discretionary stakehodlers have legitimacy but not power or urgency
Discretionary Dependencies (Soft Logic)
activities for which order can be changed but there are generally best practices
Dispute Resolution Terms and Conditions
in a contract, how disputes regarding the contract will be settled; generally either courts or arbitration
Distributive Negotiation
reach a deal through tactics so both parties receive the highest amount of value possible
Dominant Stakeholders
- type of expectant stakeholder
- in the salience model for stakeholder analysis, dominant stakeholders have power and legitimacy
- they will have an impact on your project so you will want to keep them very involved
Dormant Stakeholders
- in the salience model of stakeholder assessment, dormancy is the idea that there are stakehodlers who have power but do not have interest in your project
- dormant stakeholders are one of the three types of latent stakeholders
Dormancy Risk Parameter
anticipated time between when a risk occurs and its impact is felt on the project
Driver Management Style
- manger with a driver style is constantly giving directions
- competitive attitude drives team to win; can create challenges for project team
Duration
how long an activity takes
Earned Value Management
- measures project performance against the scope, schedule, and cost baselines
- indicates whether there any potential deviations from the performance measurement baseline
- forecasts future performance and project completion dates and costs
Economic Value Added (EVA)
whether or not the project returns to the company more than the initiative costs
Effort
- billable time for labor
- not the same time as duration
Effort-Driven Activity
- an activity that can be finished more quickly with additional labor
- crashing can be used to speed up these activities
Emergent Risks
- risks which we are unable to see because they are outside our experience or mind set, so we don’t know that we should be looking for them
- also known as unknown unknowns which are things that we do not know but where we are unaware of our ignorance
- require project resilience
- frequent reviews can reveal triggers for emergent risks
Encoding
in the communication model, translating ideas into language, usually written or verbal language
Enterprise Environmental Factors
- generally outside control of the project team
- governmental and other rules and regulations
- internal factors
- structure
- culture
- systems
- location
- available resources such as documentation of skills and preapproved external resources
- resource management system
- quality management system
- procurement system
Enterprise Environmental Factors (EEFs)
company culture and existing systems that the project will have to deal with or can make use of; think of company baggage; outside of control of the team
Escalation Response
responding to a threat or opportunity (risk) by moving it up the chain of responsibility when it is outside of the scope of the project or beyond the project manager’s authority
Escaped Defects
defects reported after the delivery by the customer
Exceptional Management Style
reward the top employees and punish the bottom employees but don’t treat everyone equally; not preferred
Expectant Stakeholders
- in the salience model of stakeholder assessment, expectant stakeholders have two of the three attributes
- power + legitimacy = dominant
- power + urgancy = dependent
- legitimacy + urgency = dangerous
Expert Power
- power comes from being the technical or project management expert
- team members look to past record for authority
Explicit Knowledge
- fact-based
- easily communications
- lessons learned are part of this knowledge category
External Dependencies
activities for which sequencing depends on an external constraint, such as waiting on a vendor
External Risks
- risks originating from outside the project
- regulatory, environmental, or governmental issues
- market shifts
- weather problems with project sites
Facilitating Management Style
project manager enables communication and helps remove roadblocks
Fast-Tracking
- taking critical path activities that were originally planned in a series and doing them instead in parallel (overlapping)
- increases risk
- sometimes results in rework
- requires more attention to communication
Feasibility Study
- often the first phase of a waterfall project
- can determine whether the project is
- worth undertaking
- will be profitable
- will meet safety regulations
- completion of feasibility study and subsequent approval triggers beginning of requirements phase
Feedback/Response
- in the communication model, after the communication has been received and understood
- the receiver may send a message with thoughts and ideas about the message
Finish-to-Finish Activity
- an activity must finish before successor can finish
- example: must finish interface testing so you can finish documentation
Finish-to-Start Activity
- activity must finish before successor can start
- example: you must finish digging a hole before you plant a tree
Five Cs of Communication
- these enhance the likelihood that communications will be correctly interpreted
- correct grammar and spelling
- concise and well-crafted
- clear and purposeful
- coherent and logical
- controlled flow of words and ideas
Fixed Cost
cost that does not change with production or work, such as setup, rent, and utilities
Fixed-Duration Activity
activity that cannot be done more quickly even if more labor is added, like testing or paint drying
Fixed-Price Contracts (FP)
- should be used for acquiring goods, products, or services will well-defined specifications
- if costs are more than the agreed upon amount, the SELLER bears the additional cost * least risk to buyer
- seller most concerned about statement of work because it helps determine their bid to make a profit
- profit not revealed to seller
- seller might try to reduce scope of work if profit is threatened
Fixed-Price Incentive Fee Contracts (FPIF)
fixed-price contract with incentives so the profit can be adjusted based on the seller meeting specific performance criteria, such as getting the work done faster, cheaper, or better
Fixed-Price with Economic Price Adjustments Contract
fixed-price contract with a long life because the future cost of supplies and equipment might be unpredictable
Force Majeure Terms and Conditions
- in schedule, an assumption that it won’t happen but it could
- in a contract, what acts of nature are allowable excuses for either party not meeting contract requirements
- considered to be neither party’s fault
- who pays for the cost of items destroyed in force majeure
Forcing/Directing Problem Solving
- authority makes the decision
- win/lose situation
Formal (Legitimate/Positional) Power
power based on your position
Formal Verbal Communication Type
- planned meetings and stakeholder briefings
- can be face-to-face or remote
Formal Written Communication Type
- project management plan and other formal documents such as charter
- can be both physical and electronic
Four Types of Emotional Intelligence
- inboud
- self-management
- self-awareness
- outbound
- social awareness
- relationship management
Free Float
- amount of time an activity can be delayed without the start date of its successor(s) and still adhering to any imposed schedule constraints
Fringe Benefits
standard benefits given to all employees
Functional or Resource Manager
- manager who is responsible for human and physical resources in a department
- works with the project manager to meet the needs of the project
Functional Organizational Structure
- most common form of organization
- grouped by areas of specialization
- projects generally occur in single department
- employees go through department heads to transmit requests from other departments
- otherwise communication stays within the project
- project team members complete normal work and project work
- functional manager controls the budget and resources
- project manager is part-time and often called a coordinator or expeditor
- advantages
- easier management of specialists
- team members only report to one supervisor
- similar resources are centralized
- there are clearly defined career paths in specialization areas
- disadvantges
- people place more emphasis on their functional speciality to the detriment of the project
- limited career path in project management
- project manager has little to no authority
Functional Requirements
solution requirements such as new features, bug fixes, and new or different behavior for a product
Functional Statement of Work (SOW)
- conveys the end purpose or result rather than the specific procedures or approach
- example: “design a car with 10 cup holders”
Funding Limit Reconciliation
- reconcile the planned versus the actual costs
- if they don’t match, we have cost variances and we need to request changes
Generalizing Specialists
individuals do many different roles on a team in an adaptive environment
Gold-Plating
adding extra features not originally in the scope of project because money is left over at the end of the project
Governance Frameworks
defines what you can and cannot do in an organization such as the rules and policies, procedures for activities, cultural norms, and systems and processes
Grade
- refers to a general category or classification of a deliverable or resource that indicates common function, but varying technical specification
- low grade products can be of acceptable quality to meet quality requirements and high grade products can be of unacceptable quality if it does not meet standards
Graduated Fixed-Price Contract
- commonly used in adaptive environments
- no sandbagging; focus on results and not hourly rate
- both parties share the risk and reward
- on-time, they get paid their hourly rate
- early delivery means a higher hourly rate
- late delivery means a lower hourly rate
Guilt-Based Power
project manager makes the team feel guilty to gain compliance
Halo Effect
tendency for positive impressions of a person, company, brand or product in one area to positively influence one’s opinion or feelings in other areas
Herzberg’s Two-Factor Theory of Motivation
- motivators
- recognition
- varied work
- sense of achievement
- demotivators
- poor pay
- company policies
- continual pressure
- motivation is influenced by hygiene factors
- poor hygiene destroys motivation but improving them does not improve motivation
- working conditions
- salary
- personal life
- wor
- relationships
security - status
Heuristics
in estimating, it’s a generally accepted rule, such as the 80/20 rule
High-Uncertainty Work
- subject matter experts collaborate and solve problems to create a new design or solution
- exploratory work with high rates of change, complexity, and risk
Hybrid Life Cycle
- combination of predictive and adaptive life cycles
- often predictive is used to manage project requirements that are well-defined while adaptive is to manage requirements that are less clear
Hybrid Organization
- uses a mix of predictive and agile development techniques
- teams might be using predictive processes but then put incremental delivery goals in the processes
- do not confuse with composite organization
Incentives Terms and Conditions
in a contract, possible benefits seller might receive for meeting buyer’s objectives in risk, cost, etc.
Incremental Life Cycle
- early planning of high-level scope sufficient to allow for preliminary estimate of time and cost
- scope is developed a little more with each iteration
- delivers a complete, usable portion of the product for each iteration
- detailed scope is elaborated for each iteration
- example: a project to build a website would involve prioritizing requirements into iterations that deliver a fully functioning part of the site at the end of each iteration
Indemnification (Liability) Terms and Conditions
in a contract, who is liable for personal injury, damage, or accidents
Independent Contractor
in a contract, the seller is not an employee of the buyer
Indirect Cost
overhead cost such as taxes, fringe benefits, janitorial services
Individual Project Risks
specific risk events on a project
- Influence Management Style
project manager emphasizes teamwork, team building, and team decision-making, and works with their team to influence collaborative, successful project implementation
Influencing
- project manager actively listens to differing viewpoints expressed by team members
- acknowledging viewpoints helps project develop mutual trust with team and eventually agreement
Informal Verbal Communication Type
unscheduled meetings and conversations
Informal Written Communication Type
email, handwritten notes, text messages, instant messaging, social media, and websites
Informational Power
control of data and distribution of information
Ingratiating Power
- project manager uses flattery to motivate the team
- wears down over time