Predictive PMP Terms Flashcards

1
Q

8/80 Rule

A

each work package should take between 8 hours and 80 hours in order to avoid work packages being too narrow or too broad

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accelerated Depreciation

A

depreciates faster than straight-line depreciation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Acceptance Response

A

passively accepting a threat or opportunity (risk) by doing nothing other than creating a contingency plan and allocating time and cost reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acceptance Terms and Conditions

A

in a contract, how you will know work is acceptable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acceptance Test

A
  • represents some expected result from the system
  • customers are responsible for verifying the correctness of the acceptance tests and reviewing test scores to decide which failed tests are of highest priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Acknowledgement

A
  • in the communication model, confirmation of receipt of a message
  • does not indicate agreement with message
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Active Job Shadowing

A

shadow employee and ask questions or try work to gather requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity

A
  • a particular piece of work scheduled for a project
  • you should expect to manage to the activity level as a project manager
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity-on-Node (AON)

A
  • type of network diagram that shows flow of project with precedence diagramming method
  • predecessors are upstream and successors are downstream
  • activities are nodes that are connected with arrows
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Actual Cost

A

as of today, what is the actual cost incurred for the work accomplished?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Administrative Closure

A
  • when closing a project, make sure
    • deliverables are signed off on
    • close project accounts
    • reassign personnel
    • deal with excess material
    • reallocate facilities and other equipment
    • create final reports
    • index lessons learned and other historical records
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Affinity Diagrams

A
  • ideas generated by other requirements gathering techniques grouped by similarity
  • each group is given a title which makes it easier to see additional areas of scope or risk that have not yet been identified
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Agent Terms and Conditions

A

in a contract, who is an authorized representative of each party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Agreement

A
  • documents or communications that outline internal or external relationships and their intentions
  • not all agreements are contracts
  • the charter and project management plan are examples of agreements that aren’t contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Ambiguity Risks

A
  • risks caused by lack of understanding
  • type of non-event based risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Analytical Management Style

A
  • depends on manager’s own technical knowledge and ability project managers often make the technical decisions for the project and then communicate those decisions to their team
  • effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Apportioned Effort Activities

A

activities that support the project, such as quality assurance and integrated change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Arbitration Terms and Conditions

A
  • in a contract, method to resolve disputes by third parties
  • usually paid for by the parties and generally faster and cheaper than the courts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Assignable Cause (Special Cause Variation)

A

a data point or series of data points require the project manager to investigate the cause of the variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Assignment Terms and Conditions

A

in a contract, refers to the circumstances under which one party can assign its rights or obligations under the contract to another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Assumption Testing

A
  • in identify risks, use what-if analysis to determine if assumption is valid or not
  • will assumption cause delay or extra costs?
  • is the information the assumption is based on reliable?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Assumptions

A
  • what is believed to be true about the project but is not a fact; incorrect assumptions introduce risk and thus they are recorded in the assumption log
  • examples are team member availability and that they will do a good job
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Authority Terms and Conditions

A

in a contract, who has the authority to do what

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Autocratic Management Style

A
  • top-down approach; manager may coach or delegate, but everyone does what the manager says
  • can create challenges for project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Autocratic Voting

A

single person is assigned to make decision for entire group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Avoiding Power

A

project manager refuses to act or get involved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Balanced Matrix

A
  • power is shared between functional manager and project manager
  • project manager is often part-time and manages a part-time team
  • team members report to project manager and functional manager
  • may have part-time administrative help
  • project manager and functional manager share authority over staff and budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Barriers

A
  • in the communication model, anything that completely blocks communication
  • more than just noise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Beneft to Cost Ratio

A
  • in project selection, compares the cost of the project to the expected benefit (revenue) it could bring
  • greater than one = benefit outweighs the cost
  • less than one = cost outweighs the benefit
  • the ratio is how many times over the revenue outweighs (or does not) the cost
    • example: a benefit to cost ration of 1.7 means the revenues brought in by the project are 1.7 times the cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Bid (Quotation)

A
  • from seller to buyer
  • price is the determining factor in the decision making process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Bidder Conference

A
  • meeting in which the seller gets to ask questions of the buyer and gather information about the buyer
  • all questions and answers are documents and added as addenda to bid documents.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Bonds Terms and Conditions

A
  • in a contract, payment or performance bonds that must be purchased
  • ex: a payment bond would protect the buyer from claims of nonpayment by the seller
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Breach/Default Terms and Conditions

A
  • in a contract, occurs when any obligation of a contract is not met
  • a breach on the seller’s part cannot be fixed by a breach on the buyer’s part
  • for example failure to complete an item in the SOW cannot be handled by the buyer stopping all payments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Budget at Completion (BAC)

A

how much did we budget for the total project effort?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Budget Estimate

A
  • based on scope
  • more accurate than ROM but not as accurate as definitive estimate
  • narrowed range before you begin iterating the plan
  • typically in the range of -10% to +25%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Bureaucratic Management Style

A
  • following procedures exactly
  • effective for work in which details are critical or when specific safety or other regulations must be strictly adhered to
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Business Requirements

A

higher-level needs of the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Ceiling Price

A

in a contract, the highest price a buyer will pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Centralized Contracting

A
  • there is one procurement department and procurement manager reports organizationally to the head of the procurement department and not the project manager
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Change Control System

A
  • part of PMIS
  • standardized forms, reports, processes, procedures, and software for managing change requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Changes Terms and Conditions

A

in a contract, how changes will be made, what forms will be used, and what are the timeframes for notice and turnaround

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Charismatic Management Style

A
  • energize and encourage their teams in project work
  • in this style, project success may become dependent on the presence of a charismatic leader, with the team relying on the leader for motivation
  • can create challenges for project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Checklists

A

when the same work is done repeatedly, checklists ensure the work is done the same way each time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Coaching Management Style

A

project manager advises and makes recommendations, helping the team and other stakeholders achieve their goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Code of Accounts

A

numbering system assigned to control accounts in the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Collaborative Problem Solving

A
  • team members will work together to resolve conflict
  • it does not matter who is right or who is wrong
  • win/win situation
  • preferred method for PMI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Commercial Risks

A
  • customer stability, terms, and conditions within the project vendors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Communication Blockers

A
  • factors that cause miscommunication and can lead to disagreement, such as noisy surroundings, distance between those trying to communicate, improper encoding, language differences, cultural differences
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Communication Channels

A
  • when you add one more person to the team, there is a substantial increase in communication channels, not just one
  • n = the number of stakeholders
  • n(n – 1 ) / 2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Composite Organization

A
  • made up of multiple organizational structures
  • an example is one where the organization is mostly functional but creates a project team where the project manager has the authority to accomplish a temporary result
  • do not confuse with hybrid organization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Compromising/Reconciling Problem Solving

A
  • neither party gets what they want
  • lose/lose situation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Confidentiality Terms and Conditions

A

in a contract, what information should not be given to third parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Configuration Identification

A

identification and documentation of the product and its components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Configuration Status Accounting

A
  • documentation of the product information
  • includes the metrics and specifications that the customer will inspect against
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Configuration Verification and Auditing

A

concerned with performance and functional attributes of the product; is the functionality acceptable?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Connectivity Risk Parameter

A

indicates how one risk is connected to another risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Consensus Approach

A

achieves general agreement about a decision and those who prefer a different option are willing to accept the decision supported by most members of the group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Consensus Management Style

A
  • project manager encourages problem-solving in a group and makes decisions based on group agreement
  • effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Constraints

A
  • factors that limit options such as time, cost, risk, scope, quality, resources, customer satisfaction
  • can be policies and procedures, regulations, predetermined budgets and schedules, resource utilization, requirements, and approaches to work
  • use them to evaluate competing demands
  • management either directly or indirectly sets priority of constraints
  • consider how changing one constraint affects another
  • changes to the project generally impact multiple constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Consultative Management Style

A
  • bottom-up approach
  • uses influence to achieve results
  • project manager considers others’ opinions and acts as servant-leader to team
  • effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Context Diagram

A
  • used to define and model scope
  • shows boundaries of product scope by highlighting the product and its interfaces with people, processes, or systems
  • shows flow of data through a system and actors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Contingency Reserves

A
  • typically associated with cost
  • reserves allocated for the identified risks remaining after the Plan Risk Responses process – think of these as known unknowns
  • they are included in the project schedule (or cost) baseline
  • developed by looking at identified risks, multiplying the probability of the risk happening (decimal) by the financial impact (dollars), which yields the expected value of each risk
    • adding all of the expected values is the how the contingency reserve is calculated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Contingent Risk Responses

A
  • fall-back plan for worst-case scenario
  • document triggers for this contingency plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Contract

A
  • a type of agreement that can be written or verbal
  • created with an external entity and involve exchange of goods or services for some type of compensation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Control Account

A
  • tool that allows you to collect and analyze work performance data regarding costs, schedule,and scope at a higher level than a work package
  • control account usually has more than one work package assigned to it, but a work package is assigned to only one control account
  • assigned unique identifiers with the code of accounts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Controlling PMO

A
  • provides support and guidance in the organization on how to manage projects
  • trains others in project management and related systems
  • assists with specific project management tools
  • ensures compliance to organizational practices and through framework and governance
  • can coordinate and prioritize all projects within the organization
  • moderate level of control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Corporate Knowledge Base

A
  • indexed historical records and lessons learned from previous knowledge and is available to all
  • a knowledge base is an OPA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Corrective Action

A
  • brings project performance in line with the baselines established in the project management plan
  • result of deviation from the project performance measurement baseline
  • requires a change request to implement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Corrective Action Change Requests

A
  • bring expected future project performance in line with project management plan
  • typically undertaken to adjust performance within the existing baselines but do not change the baselines
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Cost

A
  • how much an item costs the seller to create, develop, or purchase
  • buyer’s costs include the seller’s cost and profits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Cost Contract

A

cost-reimbursable contract that provides for payment to the seller of actual costs plus a negotiated fee fixed before work begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Cost of Prevention

A
  • what is the cost of preventing a risk versus the cost of the impact, considering also how likely it is for risk to happen and other possible costs of a risk such as schedule delays
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Cost of Quality (COQ)

A
  • ensuring project is not spending too much to achieve a particular level of quality
  • costs of conformance should be lower than costs of nonconformance; includes prevention, appraisal—time and money to audit and evaluate, and failure—the cost of non-conformance such as redoing work and fines
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Cost Plus Award Fee Contract (CPAF)

A
  • a type of incentive contract in which the buyer pays all costs and a base fee plus an award amount (bonus) based on performance
  • similar to CPIF but the incentive is a potential award and there is no possibility of a penalty
  • award amount is usually determined in advance and apportioned depending on performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Cost Plus Fee (CPFP)/Cost Plus Percent of Costs (CPPC) Contracts

A
  • require the buyer to pay for all costs plus a percentage of costs as a fee
  • generally not allowed for government contracts
  • bad for buyers because seller profit is based on a percentage of everything billed—no incentive to control costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Cost Plus Incentive Fee Contract (CPIF)

A

a cost-reimbursable contract that provides for seller to be paid for actual costs plus a fee that will be adjusted based on whether specific performance objects stated in the contract are met * original estimate is made (target cost) and a fee for work is determined (target fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Cost Variance (CV)

A
  • difference between the earned value and the actual cost
  • shows variance in cost; the negative is over budget
  • positive is under budget
  • EV = earned value
  • AC = actual cost
  • CV = EV – AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Cost-Reimbursable Contract (CR)

A
  • used when the exact scope of work is uncertain and thus costs cannot be estimated accurately enough to use a fixed-price contract
  • provides for the buyer to pay the seller allowable incurred costs to the extent prescribed
  • requires seller to have an accounting system that can track costs by project
  • buyer has the MOST risk because of the unknowns
  • seller provides an estimate but it’s not binding
  • research and development and information technology projects in which the scope is unknown are typical examples
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Crashing

A
  • adding or adjusting resources in order to compress the schedule while maintaining the original project scope
  • always results in increased cost, may result in increased risk
    trades time for money, and law of diminishing returns must be considered
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Critical Path

A
  • longest duration path or paths through a network diagram and thus determines the shortest time it could take to complete the project
  • there can be multiple criticals paths but that increases risk
  • activities on the critical path have zero float unless they are completed earlier OR they are behind and have negative float
    • cannot leave project with negative float – must compress schedule
    • if schedule cannot be compressed, must adjust baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Dangerous Stakeholders

A
  • in salience model of stakeholder assessment, dangerous stakeholders possess both power and urgency
  • type of expectant stakeholder
  • they can have disastrous impacts on a project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Decentralized Contracting

A
  • there is no procurement department and the project manager may be responsible for conducting and monitoring all work on procurements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Decoding

A
  • in the communication model, translating the message into meaningful thoughts and ideas
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Dedicated Teams

A
  • most of the team members work full-time exclusively for the project
  • easiest form of team to work with as team members can dedicate most of their energy to the project and often directly report to the project manager
  • most common in projectized organizations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Defect Repair

A
  • rework
  • modifies nonconformance to project requirements
  • requires a change request
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Defect Repair Change Requests

A

rework if component of project does not meet specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Definitive Estimate

A
  • most refined estimate as a result of planning process
  • typically +/- 10%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Delegating Management Style

A
  • project manager establishes goals and then gives the project sufficient authority to complete the work
  • for basic project management, the manager involves the team in the planning process and assigns or delegates planning and executing work to team members
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Urgent Stakeholders

A
  • in the salience model of stakeholder analysis, urgent stakeholders have significant interest but not legitimacy or power
  • type of latent stakeholder
  • often a squeaky wheel
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Demanding Stakeholders

A
  • in salience model of stakeholder assessment, they possess all three attributes – urgency, power, and legitimacy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Deming’s PDCA

A

Plan, Do, Check, Act in quality management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Democratic (Participative) Management Style

A
  • encouraging team participation in the decision-making process
  • team members “own” the decisions made by the group, resulting in improved team cooperation
  • effective for resolving conflicts, negotiating, prioritizing, and other decision-making activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Dependent Stakeholders

A
  • type of expectant stakeholder
  • in the salience model of stakeholder assessment, dependent stakeholders have legitimacy and urgency but not power
  • often depend on dominant stakeholders for their interests in project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Design Statement of Work

A
  • conveys exactly what work is to be done, including materials used and how work should be completed
  • often used for construction and equipment purchases
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Detectability Risk Parameter

A

indicates how easily the risk can be detected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Development Life Cycle

A
  • phases of the project associated with the producing the product, service, or result of the project
  • development life cycle performed within the project life cycle
    • predictive development life cycle/waterfall
    • iterative development life cycle
    • incremental development life cycle
    • hybrid development life cycle
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Direct Costs

A

costs that can be directly attributed to the work on the project, such as wages, materials, and team travel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Directing Management Style

A

project manager uses expertise to guide team members in what to do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Directive PMO

A
  • prioritizes projects
  • provides project managers and manages all projects throughout the organization
  • responsible for results of projects
  • high level of control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Discrete Effort Activities

A
  • activities that are required to complete the project scope
  • focused on creating the deliverable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Discretionary Stakeholders

A
  • in the salience model of stakeholder assessment, discretionary stakehodlers have legitimacy but not power or urgency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Discretionary Dependencies (Soft Logic)

A

activities for which order can be changed but there are generally best practices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Dispute Resolution Terms and Conditions

A

in a contract, how disputes regarding the contract will be settled; generally either courts or arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Distributive Negotiation

A

reach a deal through tactics so both parties receive the highest amount of value possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Dominant Stakeholders

A
  • type of expectant stakeholder
  • in the salience model for stakeholder analysis, dominant stakeholders have power and legitimacy
  • they will have an impact on your project so you will want to keep them very involved
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Dormant Stakeholders

A
  • in the salience model of stakeholder assessment, dormancy is the idea that there are stakehodlers who have power but do not have interest in your project
  • dormant stakeholders are one of the three types of latent stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Dormancy Risk Parameter

A

anticipated time between when a risk occurs and its impact is felt on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Driver Management Style

A
  • manger with a driver style is constantly giving directions
  • competitive attitude drives team to win; can create challenges for project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Duration

A

how long an activity takes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Earned Value Management

A
  • measures project performance against the scope, schedule, and cost baselines
  • indicates whether there any potential deviations from the performance measurement baseline
  • forecasts future performance and project completion dates and costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Economic Value Added (EVA)

A

whether or not the project returns to the company more than the initiative costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Effort

A
  • billable time for labor
  • not the same time as duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Effort-Driven Activity

A
  • an activity that can be finished more quickly with additional labor
  • crashing can be used to speed up these activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Emergent Risks

A
  • risks which we are unable to see because they are outside our experience or mind set, so we don’t know that we should be looking for them
  • also known as unknown unknowns which are things that we do not know but where we are unaware of our ignorance
  • require project resilience
  • frequent reviews can reveal triggers for emergent risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Encoding

A

in the communication model, translating ideas into language, usually written or verbal language

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Enterprise Environmental Factors

A
  • generally outside control of the project team
  • governmental and other rules and regulations
  • internal factors
    • structure
    • culture
    • systems
    • location
    • available resources such as documentation of skills and preapproved external resources
    • resource management system
    • quality management system
    • procurement system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Enterprise Environmental Factors (EEFs)

A

company culture and existing systems that the project will have to deal with or can make use of; think of company baggage; outside of control of the team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Escalation Response

A

responding to a threat or opportunity (risk) by moving it up the chain of responsibility when it is outside of the scope of the project or beyond the project manager’s authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Escaped Defects

A

defects reported after the delivery by the customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Exceptional Management Style

A

reward the top employees and punish the bottom employees but don’t treat everyone equally; not preferred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Expectant Stakeholders

A
  • in the salience model of stakeholder assessment, expectant stakeholders have two of the three attributes
  • power + legitimacy = dominant
  • power + urgancy = dependent
  • legitimacy + urgency = dangerous
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Expert Power

A
  • power comes from being the technical or project management expert
  • team members look to past record for authority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Explicit Knowledge

A
  • fact-based
  • easily communications
  • lessons learned are part of this knowledge category
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

External Dependencies

A

activities for which sequencing depends on an external constraint, such as waiting on a vendor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

External Risks

A
  • risks originating from outside the project
    • regulatory, environmental, or governmental issues
    • market shifts
    • weather problems with project sites
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Facilitating Management Style

A

project manager enables communication and helps remove roadblocks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Fast-Tracking

A
  • taking critical path activities that were originally planned in a series and doing them instead in parallel (overlapping)
  • increases risk
  • sometimes results in rework
  • requires more attention to communication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Feasibility Study

A
  • often the first phase of a waterfall project
  • can determine whether the project is
    • worth undertaking
    • will be profitable
    • will meet safety regulations
  • completion of feasibility study and subsequent approval triggers beginning of requirements phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Feedback/Response

A
  • in the communication model, after the communication has been received and understood
  • the receiver may send a message with thoughts and ideas about the message
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Finish-to-Finish Activity

A
  • an activity must finish before successor can finish
  • example: must finish interface testing so you can finish documentation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Finish-to-Start Activity

A
  • activity must finish before successor can start
  • example: you must finish digging a hole before you plant a tree
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Five Cs of Communication

A
  • these enhance the likelihood that communications will be correctly interpreted
    • correct grammar and spelling
    • concise and well-crafted
    • clear and purposeful
    • coherent and logical
    • controlled flow of words and ideas
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Fixed Cost

A

cost that does not change with production or work, such as setup, rent, and utilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Fixed-Duration Activity

A

activity that cannot be done more quickly even if more labor is added, like testing or paint drying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Fixed-Price Contracts (FP)

A
  • should be used for acquiring goods, products, or services will well-defined specifications
  • if costs are more than the agreed upon amount, the SELLER bears the additional cost * least risk to buyer
  • seller most concerned about statement of work because it helps determine their bid to make a profit
  • profit not revealed to seller
  • seller might try to reduce scope of work if profit is threatened
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Fixed-Price Incentive Fee Contracts (FPIF)

A

fixed-price contract with incentives so the profit can be adjusted based on the seller meeting specific performance criteria, such as getting the work done faster, cheaper, or better

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Fixed-Price with Economic Price Adjustments Contract

A

fixed-price contract with a long life because the future cost of supplies and equipment might be unpredictable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Force Majeure Terms and Conditions

A
  • in schedule, an assumption that it won’t happen but it could
  • in a contract, what acts of nature are allowable excuses for either party not meeting contract requirements
  • considered to be neither party’s fault
  • who pays for the cost of items destroyed in force majeure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Forcing/Directing Problem Solving

A
  • authority makes the decision
  • win/lose situation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Formal (Legitimate/Positional) Power

A

power based on your position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Formal Verbal Communication Type

A
  • planned meetings and stakeholder briefings
  • can be face-to-face or remote
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Formal Written Communication Type

A
  • project management plan and other formal documents such as charter
  • can be both physical and electronic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Four Types of Emotional Intelligence

A
  • inboud
    • self-management
    • self-awareness
  • outbound
    • social awareness
    • relationship management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

Free Float

A
  • amount of time an activity can be delayed without the start date of its successor(s) and still adhering to any imposed schedule constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Fringe Benefits

A

standard benefits given to all employees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

Functional or Resource Manager

A
  • manager who is responsible for human and physical resources in a department
  • works with the project manager to meet the needs of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Functional Organizational Structure

A
  • most common form of organization
  • grouped by areas of specialization
  • projects generally occur in single department
  • employees go through department heads to transmit requests from other departments
    • otherwise communication stays within the project
  • project team members complete normal work and project work
  • functional manager controls the budget and resources
  • project manager is part-time and often called a coordinator or expeditor
  • advantages
    • easier management of specialists
    • team members only report to one supervisor
    • similar resources are centralized
    • there are clearly defined career paths in specialization areas
  • disadvantges
    • people place more emphasis on their functional speciality to the detriment of the project
    • limited career path in project management
    • project manager has little to no authority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

Functional Requirements

A

solution requirements such as new features, bug fixes, and new or different behavior for a product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

Functional Statement of Work (SOW)

A
  • conveys the end purpose or result rather than the specific procedures or approach
  • example: “design a car with 10 cup holders”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Funding Limit Reconciliation

A
  • reconcile the planned versus the actual costs
  • if they don’t match, we have cost variances and we need to request changes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Generalizing Specialists

A

individuals do many different roles on a team in an adaptive environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Gold-Plating

A

adding extra features not originally in the scope of project because money is left over at the end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Governance Frameworks

A

defines what you can and cannot do in an organization such as the rules and policies, procedures for activities, cultural norms, and systems and processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

Grade

A
  • refers to a general category or classification of a deliverable or resource that indicates common function, but varying technical specification
  • low grade products can be of acceptable quality to meet quality requirements and high grade products can be of unacceptable quality if it does not meet standards
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Graduated Fixed-Price Contract

A
  • commonly used in adaptive environments
  • no sandbagging; focus on results and not hourly rate
  • both parties share the risk and reward
    • on-time, they get paid their hourly rate
    • early delivery means a higher hourly rate
    • late delivery means a lower hourly rate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Guilt-Based Power

A

project manager makes the team feel guilty to gain compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

Halo Effect

A

tendency for positive impressions of a person, company, brand or product in one area to positively influence one’s opinion or feelings in other areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Herzberg’s Two-Factor Theory of Motivation

A
  • motivators
    • recognition
    • varied work
    • sense of achievement
  • demotivators
    • poor pay
    • company policies
    • continual pressure
  • motivation is influenced by hygiene factors
  • poor hygiene destroys motivation but improving them does not improve motivation
    • working conditions
    • salary
    • personal life
    • wor
    • relationships
      security
    • status
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Heuristics

A

in estimating, it’s a generally accepted rule, such as the 80/20 rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

High-Uncertainty Work

A
  • subject matter experts collaborate and solve problems to create a new design or solution
  • exploratory work with high rates of change, complexity, and risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

Hybrid Life Cycle

A
  • combination of predictive and adaptive life cycles
  • often predictive is used to manage project requirements that are well-defined while adaptive is to manage requirements that are less clear
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Hybrid Organization

A
  • uses a mix of predictive and agile development techniques
  • teams might be using predictive processes but then put incremental delivery goals in the processes
  • do not confuse with composite organization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Incentives Terms and Conditions

A

in a contract, possible benefits seller might receive for meeting buyer’s objectives in risk, cost, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Incremental Life Cycle

A
  • early planning of high-level scope sufficient to allow for preliminary estimate of time and cost
  • scope is developed a little more with each iteration
  • delivers a complete, usable portion of the product for each iteration
  • detailed scope is elaborated for each iteration
  • example: a project to build a website would involve prioritizing requirements into iterations that deliver a fully functioning part of the site at the end of each iteration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

Indemnification (Liability) Terms and Conditions

A

in a contract, who is liable for personal injury, damage, or accidents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Independent Contractor

A

in a contract, the seller is not an employee of the buyer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Indirect Cost

A

overhead cost such as taxes, fringe benefits, janitorial services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

Individual Project Risks

A

specific risk events on a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q
  • Influence Management Style
A

project manager emphasizes teamwork, team building, and team decision-making, and works with their team to influence collaborative, successful project implementation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

Influencing

A
  • project manager actively listens to differing viewpoints expressed by team members
  • acknowledging viewpoints helps project develop mutual trust with team and eventually agreement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

Informal Verbal Communication Type

A

unscheduled meetings and conversations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Informal Written Communication Type

A

email, handwritten notes, text messages, instant messaging, social media, and websites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Informational Power

A

control of data and distribution of information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

Ingratiating Power

A
  • project manager uses flattery to motivate the team
  • wears down over time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Inspection Terms and Conditions

A

in a contract, does anyone have a right to inspect work during the execution of a project and when

176
Q

Inspection

A

keeping errors out of the customers’ hands by routinely auditing product and taking corrective action when quality is out of bounds

177
Q

Intangible Business Value

A

projects that add intangible business value do not create new things but instead new ideas, concepts, and experiences, such as goodwill, brand recognition, strategic alignment

178
Q

Intangible Reward

A

saying thank you, public recognition, training throughout the project life cycle

179
Q

Integrated Risk Management

A
  • risks are owned by each project within a program or portfolio
  • some risks might be escalated to higher levels
180
Q

Intellectual Property Terms and Conditions

A

in a contract, who owns the intellectual property used in connection with or developed as part of the contract

181
Q

Interactive Communication

A

reciprocal and involves two or more people; three main components: * the sender encodes the message and the receiver decodes the message * the receiver acknowledges receipt of the message * both the sender and receiver are responsible for confirming the message has been correctly interpreted by the receiver

182
Q

Internal Dependencies

A

type of hard logic which occurs when activities depend on something within the organization, such as waiting for a team member to return from vacation

183
Q

Internal Rate of Return (IRR)

A
  • used when organizations are evaluating which projects to do
  • tells which project is going to yield the highest return
  • discount rate that makes the net present value of all cash flows from a project equal to zero
  • choose projects with the highest IRR value
184
Q

Internal Risks

A

schedule, scope, or budget changes; inexperienced team members; issues with staffing or equipment

185
Q

Invitation for Bid (IFB)

A

requests a total price to do all the work; form of RFP where the work described in the procurement statement of work is detailed enough for the bidders to determine a total price

186
Q

Invoicing Terms and Conditions

A

in a contract, when invoices will be sent and specific documents required

187
Q

Joint Application Design (JAD) Sessions

A

facilitated sessions in software development involve eliciting input and requirements to enhance the processes of developing the software

188
Q

Just in Time (JIT)

A

a production strategy that strives to improve a business’ return on investment by reducing in-process inventory and associated carrying costs.” JIT was first developed and used by the Toyota Motor Corporation

189
Q

Kickoff Meeting

A
  • AFTER THE PROJECT PLAN IS APPROVED
  • last stage of developing the project management plan
  • meeting with all key parties involved
  • announce start of project
  • provide overview of details
  • ensure commitment from everyone
190
Q

Lag

A

positive time that extends the schedule; waiting time between activities; example: paint doesn’t dry a quickly as expected so exhedule has to be pushed out because other activities require dry paint; ADD

191
Q

Laissez-Faire Management Style

A

project manager is not directly involved with the work of the team but manages and consults as necessary; this can be appropriate for a highly-skilled team

192
Q

Latent Stakeholders

A
  • in the saliency model of stakeholder assessment, latency is the idea that there are stakeholders who hold only one of the three attributes – power, urgency, or legitimacy
    • dormant latent stakeholders have power but not urgency or legitimacy
    • discretionary latent stakeholders have legitimacy but not urgency or power
    • demanding latent stakeholders have urgency but do not have power or legitimacy and are often the squaky wheel
193
Q

Law of Diminishing Returns

A

after a certain point, adding more input (such as staff) will not produce a proportional increase in productivity

194
Q

Lead

A

negative time that occurs when we allow activities to overlap; an activity that can start before its predecessor finishes and allows schedule compression; example: priming the walls of one room while painting walls that have already been primed in another; SUBTRACT

195
Q

Leading

A

art of establishing direction aligning people, and motivating the project team to complete the project

196
Q

Learning Curve

A

time required to learn how to do new work; associated with estimating schedule and cost because learning curve for new technology should be added to schedule but once something has been learned you can subtract time when doing analogous estimating

197
Q

Legitimate Stakeholders

A
  • in the salience model of stakehodler assessment, stakeholders with legitimacy have a legitimate need or interest
198
Q

Lessons Learned

A

document that includes what was done right and what was done wrong and what would be done differently if the project could be redone; collect and review lessons learned before starting a new project; once project is underway you add lessons learned to the company database (OPAs)

199
Q

Letter of Intent

A
  • also known as memorandum of understanding
  • not a legally-binding contract, but a letter stating that the buyer intends to hire the seller
  • gives the seller confidence that the contract will be signed soon so they can hire people or order materials
200
Q

Level of Effort (LEO) Activities

A

support activities, such as reporting and budgeting, that don’t contribute to scope but are necessary to manage the project

201
Q

Life Cycle Costing

A

determine costs over the entire life of the product, not just the cost of the project to create the product; this includes maintenance costs and determining if a cheaper product will actually be more expensive to maintain over the life of the product

202
Q

Liquidated Damages Terms and Conditions

A

in a contract, estimated damages for specific defaults described in advance

203
Q

Logical Data Models

A

description of the quality needs of the project; use an entity relationship diagram—method of representing and analyzing data

204
Q

MacGregor’s Theory of X and Y

A

all workers fit into two categories; X is managers believe people need to be watched every minute as employees are incapable, avoid responsibility, and avoid work; Y is managers who believe people are willing to work without supervision and want to achieve; PMI encourages the Y perspective

205
Q

Majority Voting

A

group chooses the decision that more than half the members support

206
Q

Manageability and Controllability Risk Parameter

A

indicates level of difficulty involved in dealing with an identified risk, should it occur

207
Q

Management Requirements Terms and Conditions

A

in a contract, what attendance is required at meetings and who approves the staff assigned to a project

208
Q

Management Reserves

A
  • additional funds and time to cover unforeseen risks
  • excluded from schedule and cost baselines but part of overall project duration or budget
    • in the project budget, management reserves make up the difference between the cost baseline and budget
  • require approval of a formal change request to use them
209
Q

Management Reviews

A
  • milestones for when management and stakeholders will compare project progress to what was planned and ID needed changes to any of the plans
  • built into the project management plan
210
Q

Mandatory Dependencies (Hard Logic)

A

activities that must happen in a specific order

211
Q

Maslow’s Hierarchy of Need

A

employees are not motivated most by security or money but highest motivation in work is for people to contribute and use their skills; created the pyramid below * self-actualization is when workers achieve self-fulfillment, growth, learning * esteem is when there is accomplishment, respect, attention, appreciation * social is love, affection, approval, friends, and association * safety is security, stability, freedom from harm * physiological is need for air, water, food, housing, clothing

212
Q

Material Breach

A

breach of contract that is so large it may not be possible to complete the work

213
Q

Matrix Organizational Structure

A
  • an attempt to maximize the strengths of both functional and project-oriented structures
  • communication goes from team members to both managers
  • team members do project work in addition to normal department work
  • types of matrix organizations
    • strong: power rests with project manager
    • weak: power rests with functional manager
    • balance: power is shared between functional manager and project manager
  • advantages
    • highly visible project objectives
    • project manager has more control over resources than in functional organizations
    • more support from functional areas
    • better coordination
    • maximum utilization of scarce resources
    • better horizontal and vertical dissemination of information
    • team members maintain a “home”
  • disadvantages
    • extra administration is required
    • project team members have more than one manager
    • more complex to monitor and control
    • resource allocation is more complex
    • extensive policies and procedures are necessary
    • functional managers may have different priorities than project managers
    • higher potential for conflict
214
Q

McClelland’s Theory of Needs (Acquired Needs Theory)

A

people are motivated by one of three needs and they should all be managed differently * achievement: people who should be given projects that are challenging but reachable; they like recognition * affiliation: people who work best when cooperating with others; seek approval instead of recognition * power: people whose need for power is socially oriented, rather than personally oriented, are effective leaders and should be allowed to manage others; they like to organize and influence

215
Q

McGregor’s Theory of X and Y

A

as proposed by Douglas McGregor, Theory X and Theory Y describe two different types of workers and how they should be managed. Theory X states that management believes that workers will do as little as possible to get by, and thus need a great deal of direction. Theory Y states that management believes that workers are interested in doing their best and, given the freedom, will perform well.

216
Q

Medium

A

in the communication model, means of conveying the message; sometimes the medium is referred to as the channel

217
Q

Meeting Rules

A

* set a time limit and keep it * create an agenda with team input * distribute agenda beforehand * stick to agenda * let attendees know responsibility beforehand * bring the right people together * chair and lead the meeting with a set of rules * assign deliverables and time limits for all work assignments that result from meetings * document and publish meeting notes

218
Q

Memoranda of Agreement (MOA)

A
  • a written document describing a cooperative relationship between two parties wishing to work together on a project or to meet an agreed upon objective
  • serves as a legal document and describes the terms and details of the partnership agreement
  • more formal than a verbal agreement, but less formal than a contract
  • organizations can use an MOA to establish and outline collaborative agreements, including service partnerships or agreements to provide technical assistance and training
219
Q

Milestones

A

significant events within project schedule; have no duration; could be required checkpoint, phase gate, customer-imposed due date for interim deliverables

220
Q

Murder Board

A

In benefits measurement when deciding whether or not to do a project, it’s a committee that asks every possible question about a project to determine whether or not it should be selected

221
Q

Must Start/Finish On

A

most restrictive schedule constraint

222
Q

Near-Critical Path

A

path is closest in duration to the critical path; becomes critical if something shortens the critical path or lengthens the near-critical path; the closer in length they are, the most risk the project has

223
Q

Negative Risk Responses

A

escalate (management or someone higher up handles the risk), avoidance (don’t do that portion of the project; change the plan or reduce scope), transference (hire someone else to own the risk), mitigation (reduce the probability and/or the impact of the risk), acceptance (don’t take action; usually reserved for low-impact risks); documented in risk register

224
Q

Net Present Value (NPV)

A
  • total benefits (income or revenue) minus costs over many time periods
  • accept a project when NPV > 0
    reject a project is NPV is less than zero
  • while comparing two projects always select the project with a higher NPV
225
Q

Network Diagram

A
  • visualization of the flow of project activities and the order in which they will be performed
  • helps plan parallel activities, leads, and lags
  • helps justify project manager’s estimate for project
  • helps control project
  • shows interdependencies and thus risk
  • shows sequence of work for the team
  • helps identify opportunities for schedule progression
  • can be used for project progress in reporting
226
Q

Noise

A

in the communication model, anything that interferes with the transmission of the message, including static, distractions, preconceptions and stereotypes, cultural norms, malfunctioning transmitting equipment, or anything that deteriorates or causes a barrier to successful transmission

227
Q

Non-Functional Requirements

A

sometimes called quality attributes, they’re things expected in deliverables that aren’t features, such as performance, reliability, error handling, and ease of use

228
Q

Nondisclosure Agreement (NDA)

A

identifies the information or documents that should be kept confidential during procurement

229
Q

Nonfunctional Requirements

A

solution requirement that describes the environmental condition or qualities of the product or deliverable

230
Q

Notice Terms and Conditions

A

in a contract, to whom certain correspondence should be sent

231
Q

Observation

A

job shadowing or participating in work

232
Q

Oligopoly

A

marketplace is so tight that the actions of one seller affects the price and availability of others

233
Q

OPM3

A

organizational project management maturity model to help organizations determine their level of maturity

234
Q

Opportunity Cost

A
  • what is given up by selecting one project over another
  • equals the value of the project not selected
    • example: project A will bring in $95,000 in revenue and project B will bring in $45,000 in revenue
      • the opportunity cost for not selecting project B is $45,000
235
Q

Opportunity Responses

A

in risk management, you make the most of risks that are opportunities by exploiting, enhancing, or sharing; exploiting means adding work or change to make sure the opportunity occurs; enhancing means increasing the likelihood of the opportunity or positive impact of it; sharing means allocating ownership or partial ownership to whom is best able to achieve the opportunity

236
Q

Order of Ethical Responsibilities

A

1) laws of the country 2) company policies 3) customs 4) personal ethics

237
Q

Organic (Simple) Organizational Structure

A
  • work groups in organization are flexible
  • people work alongside each other despite roles
  • project manager has little or no authority over project
  • resources dedicated to project are low
  • owner in charge of budget
238
Q

Organizational Governance

A
  • the overall structure of an organization that supports its specific culture and attributes
  • includes the policies and procedures for how work will be performed to meet strategic goals and support organizational operations and decision-making
    • external governance: generally a board of directors ensures work comforms to government or regulatory standards
    • internal governance: the policies and procedures regarding portfolio, program, project, and operations work
239
Q

Organizational Hierarchy

A

typically organizations are organized by operational, middle management, and strategic

240
Q

Organizational Knowledge Repositories

A
  • one of the two types of OPAs
  • information that can be used to plan and manage projects to avoid mistakes from the past and standards and templates
    • activities
    • baselines
    • backlogs
    • benchmarks
    • configuration management
    • correspondences
    • documents
    • estimates
    • financia data
    • issues logs
    • lessons learned
    • metrics
    • plans
    • prototypes
    • WBSs
    • reports
    • retrospective findings
    • risks and risk response plans
241
Q

Organizational Process Assets (OPAs)

A
  • organizations’ information that provide direction and guidance in planning and help the project benefit from past company experience
  • two categories of OPAs
    • processes, policies, and procedures
    • organizational knowledge bases
242
Q

Organizational Project Management (OPM)

A

a framework for keeping the organization as a whole focused on the overall strategy and provides direction on how portfolios, programs, projects, and other organizational work should be prioritized, managed, executed, and measured to best achieve strategic goals

243
Q

Organizational Systems

A

define how work is done at your organization as defined by management; provides structure and governance; provides permissions such as the work authorization system

244
Q

Out of Control

A

process for creating deliverable is out of a state of statistical control and the deliverables show a lack of consistency and predictability in the process results; happens when 1) data point falls outside the upper or lower control limits or 2) there are outliers within upper and lower limits

245
Q

Overall Project Risk

A

overall project risk exposure; how risky the project is to an organization

246
Q

Ownership Terms and Conditions

A

in a contract, who owns the tangible items, such as materials and equipment, used in connection with or developed as part of the contract

247
Q

Paralingual Communication

A

communication beyond words; pitch, tone, and inflections

248
Q

Pareto Principle (80/20 Rule)

A

states that 80% of problems are due to 20% of the root causes

249
Q

Parking Lot

A

storage place for ideas that distract from the main goal during a meeting.

250
Q

Parkinson’s Law

A

states that work will expand to fulfill the time allotted to it; bloated tasks will take all the time allotted; use management reserve instead

251
Q

Part-Time Teams

A

team members spend a portion of their time working on the project while also working on other projects and/or their regular work; most often seen in functional organizations

252
Q

Participatory Decision Models

A

stakeholders involvement in decision making with techniques such as a simple vot

253
Q

Partnership Teams

A

teams come from multiple organizations participating in a project together plus the project manager for the organization taking the lead;

254
Q

Passive Job Shadowing

A

shadow employee to gather requirements without asking questions

255
Q

Payback Period

A
  • how long it takes for organization to recover the investment in a project before it starts accumulating a profit
  • does not consider the time value of money — cash coming in five years from now is worth less than it is today, which is why banks charge interest on loans
  • consider other factors in addition to payback period when performing project selection
256
Q

Payments Terms and Conditions

A

in a contract, when payments will be made, what are reasons for nonpayment; can include stop payments for certain parts of work

257
Q

Penalty (Coercive) Power

A

power stems from ability to penalize team members

258
Q

Performance Statement of Work

A

what final product should accomplish rather than how it should be built; ex: car that will go from zero to 120 km per hour in 4.2 second

259
Q

Performance Statement of Work (SOW)

A

describes what the final product should accomplish instead of how it will be built or the design characteristics; ex: build a car that will go 80 mph in 4.2 seconds

260
Q

Persuasive Power

A

project manager gives a sales pitch for a specific outcome

261
Q

Phase Gate (Kill Point)

A

required end of phase event during which results of the complete phase are analyzed by comparing the results with the business documents, the project charter, and project management plan; reviews the cost of that phase and if it was on track with the baseline; based on that, a decision is made with the options of * redoing the same phase * moving forward to the next phase * terminating the project

262
Q

Plan-Driven (Predictive/Traditional/Waterfall) Life Cycle

A

* scope, schedule, and cost are determined early in the project, before work begins to produce deliverables * know many aspects of the project up before work gets started * changes to scope are tightly controlled and thus change averse

263
Q

Planned Value

A

as of today, what is the estimated value of the work planned to be done? * PV = planned value * BAC = budget at completion * PV = % planned x BAC

264
Q

Planning Package

A

tool that allows you to collect and analyze work performance data regarding costs, schedule, and scope at a higher level than a work package

265
Q

Planning Process Group

A

* detailed analysis of whether the objectives in the project charter and expected benefits can be achieved * decide how objectives will be accomplished * determine what processes are appropriate and tailoring them * all stakeholders are involved in planning * project formally authorized when sponsor signs project charter * project management plan produced and approved by sponsor * projects can move back to planning throughout the project

266
Q

Plurality Voting

A

group chooses decision with most supporters; majority not necessary

267
Q

PMI Code of Ethics

A

* must be honest and truthful on the exam application and on test items * report PDUs honestly * report violations with clear and factual violations * cooperate PMI audits * disclose appearance of conflict of interest * truth in advertising and sales * comply with laws, regulations, and ethical standards of country where project is being held * respect intellectual property of others * customer is in charge in a project * confidentiality (privity) with customers * refrain from accepting inappropriate compensation

268
Q

PMI Talent Triangle

A
  • technical: apply project management knowledge to deliver objectives of project and define critical success factors
  • strategic: describe business needs of project and understand how they align to organization’s goals
  • leadership: impart vision, gain consensus for strategic goals, establish direction, and motivate others
269
Q

Point of Total Assumption

A

amount above which the seller bears all the loss of a cost overrun * costs over the PTA are assumed to be due to mismanagement * only relates to fixed price incentive fee contracts * PTA = ((Ceiling Price – Target Price)/Buyers Share Ratio) + Target Cost

270
Q

Portfolio

A
  • a group of programs, projects, and other related operational work that are prioritized and implemented to achieve a specific business goal
  • portfolio approach can optimize the use of resources, enhance benefits, and reduce risk
  • all about ROI
271
Q

Portfolio Manager

A

responsible for governance at an executive level; get best return on resources invested; manage projects that might be largely unrelated to each other

272
Q

Positive Risk Response

A

escalate (management or someone higher up handles the risk), exploit (make everything right in a project to take advantage of a positive risk), share (partner with another organization to take advantage of a risk you could not handle on your own), enhance (put the odds in favor of the positive risk happening), accept; documented in risk register

273
Q

Power/Interest Grid Stakeholder Map

A

group stakeholders by level of power and their interest in the project’s outcome

274
Q

Precendence Diagramming Method

A
  • creating a network diagram that shows predecessors and successors; arrows represent relationship between activities and dependencies; where a = predecessor and b = successor
  • Finish-to-Start: activity a must finish so activity b can start
  • Start-to-Start: activity a must start so activity can start; two activities happen at the same time but typically a starts a little bit before b; example: start developing the training and once they are in training the software is pushed out
  • Finish-to-Finish: activity a must finish before activity b can finish; example: finish installing the network cable so the computers can be connected; two activities finish at about the same time; chase each other
  • Start-to-Finish: cyclic production; activity a must start for b to finish
275
Q

Precision

A

measure of exactness but does not mean accuracy; something can be precise but not accurate

276
Q

Prerequisites (Perks)

A

some employees receive special rewards

277
Q

Present Value

A

* value today of future cash flows * present value = future value / ((1 + interest rate) ^ number of time periods)

278
Q

Pressure-Based Power

A

project manager restricts choices for team to get them to do the work

279
Q

Prevention

A

keeping errors out of the project management and product development process to ensure quality requirements are met

280
Q

Preventive Action

A
  • action to deal with anticipated or possible deviations
  • ensures future project performance will not be compromised
  • requires a change request to implement
  • example: changing a resource because the resource’s last activity nearly failed to meet the acceptance criteria
281
Q

Preventive Action Change Requests

A
  • deal with anticipated or possible deviations from performance measurement baseline and other actions
  • typically do not change baselines
282
Q

Privity

A

a contractual relationship

283
Q

Procurement Statement of Work (SOW)

A

scope of work to be done on each procurement * break down the project scope baseline into the work the project team will do and the work purchased from the seller * include all work and activities the seller is to complete * finalized by the time the contract is signed and is considered part of the contract

284
Q

Product Backlog

A

product scope in an adaptive environment; always prioritized before the current sprint

285
Q

Product Scope

A

requirements that relate to the product, service, or result of project; also defined as product deliverables and their associated features and functions; derived from collect requirements; measured against project requirements; confirmed in validate scope

286
Q

Profit (Fee)

A

amount gained by the seller as a result of work; in a fixed-price and time and materials contracts, profit is defined but in cost-plus contracts the profit is negotiated by the buyer and seller

287
Q

Program

A
  • a group of related projects that is focused on the interdependencies between projects and may help achieve decreased risk, economies of scale, and improved management
288
Q

Program Manager

A

manages a group of related projects; there to provide control, support, and guidance

289
Q

Progressive Elaboration

A

start very broad in planning and use deductive reasoning to get more specific * start with a very broad idea * formulate the idea with information gathering * create the business case * perform a feasibility study * execute the project

290
Q

Project

A
  • a temporary endeavor (ends when project is closed) and creates a unique service or result
  • projects drive change (MACD)
    • move
    • add
    • change
    • delete
291
Q

Project Calendar

A

shows when project can take place

292
Q

Project Coordinator

A
  • similar to a project expediter but has some power to make decisions and reports to higher-level manager
  • most likely to be found in functional organizations
293
Q

Project Documents

A

any project-related documents that are not part of the project management plan; mostly created by project manager and are not shown to or approved by sponsor; must be updated frequently

294
Q

Project Expediter

A
  • acts as a staff assistant and communication coordinator
  • cannot personally make or enforce decisions
  • most likely to be found in functional organizations
295
Q

Project Float

A

amount of time a project can be delayed without delaying the externally imposed project complete date required by the customer or management

296
Q

Project Governance

A
  • an organization’s established criteria, procedures, and guidelines to make sure projects meet the organization’s strategic goals
    • predictive: typically involves formal documentation and upfront analysis and agreement
    • agile: less structured but still aligns with necessary policies and procedures
  • can be established and administered by a PMO
  • ECO task 14 in Process domain: establish project governance structure
297
Q

Project Information System (PMIS)

A

software, shared workspaces for file storage or distribution, and repositories for historical information; a PMIS is an EEF

298
Q

Project Life Cycle

A

what you need to do the work; an organization or department’s methodology for managing a project; logical breakdown of what needs to be done to produce the deliverables; either or plan or change driven

299
Q

Project Management

A

manages change in organizations and all of the logistics in the change

300
Q

Project Management Office (PMO)

A

is an office and not a single person * centralizes and standardizes the management of projects * manages interdepencies * integrates information * provides resources * recommends termination of project when appropriate * monitors compliance * gathers lessons learned * provides templates * provides centralized communication * provides project governance

301
Q

Project Manager

A

responsible for managing the project to meet the project objectives and deliver value and benefits to the organization

302
Q

Project Requirements

A

required actions, processes, or other conditions of the project

303
Q

Project Resilience

A

awareness of project unknowable unknowns – risks that can only be identified after they happened

304
Q

Project Scope

A

work the project team will do to deliver the product of the project; all of the required work and only the required work to obtain project objectives; defined at beginning in predictive environment and resistant to change but developed through iterations and changes are expected in adaptive; measured against the project plan at completion

305
Q

Project Sponsor/Initiator

A

provides financial resources for the project, provides support, protects project from unnecessary changes; approves changes in project deliverables; protect project from termination; approve additional work if it affects the schedule or cost

306
Q

Project-Based Organization (PBO)

A

organizations that create temporary frameworks around their projects that allow them to circumvent any obstacles inherent in their existing organizational structure

307
Q

Project-Oriented Organizational Structure

A
  • also known as “projectized”
  • entire company is organized by projects
  • project manager has control of the project
  • personnel are assigned and report to project manager
  • team members only complete project work and do not have a home department
    • assigned to a project ends, they are assigned to a new project
  • communication generally happens within the project
  • advanages
    • efficient project organization
    • team loyalty to project
    • more efficient communications in project
    • project manager has power to make decisions
  • disadvantages
    • no home for project team members when project ends
    • lack of specialization in disciplines
    • duplication of facilities and job functions
    • could result in less efficient use of resources
308
Q

Prompt Lists

A

list of categories that have been identified as possible sources of risk to the project

309
Q

Propinquity Risk Parameter

A

indicates how key stakeholders perceive the risk

310
Q

Proposal

A

from seller to buyer; contains more than just price; also includes ideas

311
Q

Prototypes

A

model of product presented to stakeholders for feedback

312
Q

Proximity Risk Parameter

A

indicated how long before the risk affects a project objective

313
Q

Pull Communication

A

the sender places the information in a central location and recipients are responsible for retrieving it from that location

314
Q

Purchase Order

A

fixed-price contract that is the simplest and most straightforward; only type of contract that is unilateral – signed by only one party – as opposed to bilateral – signed by both parties; becomes a contract when the buyer accepts the goods

315
Q

Pure (Insurable) Risks

A

risks of loss, such fire, theft, or personal injury; risk that only has a downside

316
Q

Push Communication

A

one-way stream of information; sender provides information to the people who need it but do not expect feedback; examples include status reports and company memos.

317
Q

Qualitative Risk Probability Impact Matrix

A

lists each risk and then provides a rating of how likely the risk is to happen and how big of an impact there is if the risk happens; usually a scale or low, moderate, high or RAG; gives an overall risk score that’s also qualitative

318
Q

Quality Audit

A

document the best practices used, document variances, recommend best practices, implement recommendations for quality improvement, and document quality audit in lessons learned

319
Q

Quality Costs

A

prevention (quality assurance to ensure delivery of the exact project scope; appraisal (quality control to test, audit, and evaluate); failure (scrap and rework that results in loss of time and money)

320
Q

Quality Functional Deployment (QFD) Session

A

also known as Voice of the Customer (VoC), it’s a faciliated session to elicit and prioritize customer requirements in manufacturing

321
Q

Quality Management

A

creating and following the organizational policies and procedures and tailoring them to ensure the project also meets the needs of the customer

322
Q

Quality Process Map

A

alternative paths a process can take to help determine the cost of quality by mapping the expected monetary value of pursuing paths of conformance and nonconformance

323
Q

Quality Requirements

A

requirements to validate the successful completion of a project deliverable or fulfillment

324
Q

Quantitative Risk Probability Impact Matrix

A

Lists each risk event, numerical probability of the risk happening, monetary value of the impact, and then the expected value; sum the expected monetary value to get the contingency reserve

325
Q

RACI Chart

A

(Responsible, Accountable, Consult, Inform) a type of responsibility assignment matrix that clearly defines role assignments and designates people as one or more of the RACI; multiple people can be R, C, or I, but only one person is A

  • Responsible: responsible for doing the work
  • Accountable: accountable for the success of the task and is the decision-maker
  • Consulted: who needs to be consulted for details and additional info on requirements; typically the person (or team) to be consulted will be the subject matter expert.
  • Informed: who needs to be kept informed of major updates; typically senior leadership.
326
Q

Receiver

A

in the communication model, recipient of the message, responsible for decoding the message and providing feedback. The receiver is responsible for making sure that the entire message is received and understood by encoding a message back to the sender conveying that.

327
Q

Referent Power

A

power comes from another person liking or respecting you or wanting to be like you; power of charisma and fame

328
Q

Reporting Terms and Conditions

A

in a contract, what reports are required and when

329
Q

Request for Information (RFI)

A

might be used before bid documents are created; helps buyer identify which companies are qualified to handle the procurement or determine what work is possible

330
Q

Request for Proposal (RFP)

A

requests a detailed proposal with information on price, how work will be done, who will do it, and company experience

331
Q

Request for Quotation (RFQ)

A

request a price quote per item, hour, or other unit of measure

332
Q

Requirements

A

conditions or capabilities that must exist in a product, service, or result we create

333
Q

Residual Risk

A

new risk as a result of another risk response; for example, hiring a vendor to assume a risk

334
Q

Resource Breakdown Structure

A

shows organizational chart to assign resources for work packages

335
Q

Resource Calendar

A

different from the project calendar; shows what resources are available when

336
Q

Resource Leveling

A
  • produce a resource-limited schedule
  • lengthens the schedule and increases the cost to deal with a limited number of resources, resource availability, and other resource constraints
337
Q

Resource Smoothing

A
  • limits labor except for critical path
  • resources are leveled only within the float of their activities, so the complete dates of activities are not delayed
  • the goal is to adhere to the deadline
338
Q

Retainage Terms and Conditions

A

in a contract, amount of money, usually 5% to 10%, withheld from each payment and given when final work is complete

339
Q

Reverse Shadowing

A

a more senior team member teaches a more inexperienced team member how to do something by watching them and coaching them through a task. This is more than just on the job training because of the coaching aspect.

340
Q

Reward Power

A

power stems from ability to give rewards

341
Q

Rewarding

A

making team feel values and promote good performance and behavior because people feel motivated when they are rewarded; must be formal and achievable for team; power to reward the team must be given to the project manager; only good work should be work not sloppy team members

342
Q

Risk Appetite (Risk Tolerance)

A

general, high-level description of the level of risk acceptable to an individual or organization; high profile projects typically have lower risk appetite or tolerance; typically set at the launch of the project

343
Q

Risk Categories

A

ways to lump similar risks together to create risk breakdown structure

344
Q

Risk Efficiency

A

organization’s approach to identifying and dealing with risks

345
Q

Risk of Loss Terms and Conditions

A

in a contract, allocates risk between the parties in the event goods or services are lost or destroyed

346
Q

Risk Reviews

A

meetings to discuss the effectiveness of planned risk responses that have been implemented on the project may result in identification of new risks, secondary risks, and risks that are no longer applicable.

347
Q

Risk Threshold

A

refers to the specific point at which a risk becomes unacceptable

348
Q

Risk Triggers

A

events that trigger the contingency response

349
Q

Rough Order of Magnitude (ROM)

A

made during project initiating; typical range is -25% to +75%

350
Q

Rule of Seven

A

if there is a group of seven or more outliers (nonrandom data points) on a control chart, the process is out of control; more than seven shows the data points are not random

351
Q

Schedule Bar Chart

A

good for reporting to customers and for control, but not an effective planning tool

352
Q

Schedule Control Threshold

A

at what point does schedule variance become an issue?

353
Q

Schedule Variance (SV)

A

shows variance between earned value and planned values; difference between earned value and planned value; negative is behind schedule; positive is ahead of schedule * EV = earned value * PV = planned value * SV = EV – PV

354
Q

Scope Management

A

process of defining what work is required and then making sure all of that work and only that work is completed

355
Q

Secondary Risk

A

domino effect of risk response; one risk if it happens creates another not necessarily smaller risk

356
Q

Seller Proposal (Price Quote or Bid)

A

seller’s response to the bid documents

357
Q

Sender

A

in the communication model, person who conveys a message and is responsible for making the content clear and complete; also responsible for confirming that the receiver understands the message correctly.

358
Q

Service Level Agreement (SLA)

A
  • a contract between a service provider and its client
  • outlines how the service is going to be performed and provided, as well as what is to happen if the company fails to provide the service
  • often used in the IT industry
359
Q

Should-Cost Estimate

A

process of independent estimating; the independent estimate before taking bids is the mean used to compare vendors’ bids for the work

360
Q

Showing Ratio

A

in contracts, these incentives are typically expressed as a ratio such as 90/10; ratio described how cost savings or cost overrun will be shared; first number represents the buyer portion of the ratio and the second number represents the seller portion

361
Q

Single Source Procurement

A

buyer contracts directly with preferred seller without going through the bid process for procurement; buyer prefers to work with just one although there are multiple options

362
Q

Site Access Terms and Conditions

A

in a contract, requirements for access to site where the work will be completed

363
Q

Situational Leadership

A

a manager using different leadership styles based on the people and project work they are dealing with; project manager needs to be more directing at the beginning of the project and coaching, facilitating during executing

364
Q

Six Sigma

A

quality methodology for achieving organizational improvement and high levels of correctness with extremely reduced variances; standard deviation between 3 or 6 sigma

365
Q

Smoothing/Accommodating Problem Solving

A

downplay petty conflict and smooth them over

366
Q

Sole Source Procurement

A

there is only seller that can complete the work; ex: a company that owns a critical patent

367
Q

Solution Requirements

A

features, functions and characteristics of the product or service; can be functional or nonfunctional

368
Q

Special Provisions (Special Conditions)

A

additions, changes, or deletions for contracts determined by the project manager; result of meeting with procurement manager if there is one to determine final contract terms and conditions

369
Q

Stakeholder Engagement Levels

A

used in planning stakeholder engagement to create goals; unaware, resistant, neutral, supportive, leading

370
Q

Stakeholder Requirements

A

needs of a stakeholder or stakeholder group

371
Q

Stakeholder Stakes

A

ways in which stakeholders might a stake in a project * interest: how they are affected by the project * rights: legal and moral rights to the project * ownership: ownership of an asset used in the project * knowledge: knowledge that helps the project * contribution: funds or resources that support the project

372
Q

Stakeholders

A

any people or organizations whose interests may be positively or negatively impacted by the project or exert influence on the project * actively involved or have a more advisory role * internal or external to organization * keep stakeholders informed, solicit their input, and work to satisfy their needs and expectations

373
Q

Standard Contract

A

standard format for a contract that has been created by the buyer and used repeatedly; usually drafted or at least reviewed by lawyers; generally do not require additional review if used for the purpose for which they were intended

374
Q

Standard Deviation

A

distance from the normal bell curve; could be a way to measure possible range for the estimate; for example, an activity estimate of 30 hours that has a standard deviation of +/-2 is expected to take between 28 and 32 hours; also used in quality to determine the acceptable threshold for variation in quality

375
Q

Start-to-Finish Activity

A

an activity must start before the successor can finish

376
Q

Start-to-Start Activity

A

activity must start before the successor can start; example: must start designing and wait for two weeks’ lag in order to have enough of the design completed to start coding

377
Q

Statement of Work (SOW)

A

describes the complete scope of a procurement; lays out all work and activities (including meetings, reports, and communications) the seller is to complete, acceptance terms; level of detail depends on the contract type

378
Q

Statistical Independence

A

probability of one event occurring does not affect the probability of another event occurring; mathematical tool to determine root cause

379
Q

Step Funding Requirements

A

represents funding at different phases of project added to cost baseline; shows infusions of money at each phase and then money spent in that phase

380
Q

Storytelling

A

team members and experts explain tacit knowledge during Manage Knowledge

381
Q

Straight-line Depreciation

A

same amount of depreciation is taken each year (item with a ten year useful life and no salvage value)

382
Q

Strategic Impact Risk Parameter

A

refers to the degree to which the occurrence of a risk would affect the strategic goals of the organization

383
Q

Strong Matrix

A
  • power rests with project manager but project team has functional manager also
  • project manager is full-time on projects
  • project manager has more power and authority than functional managers
  • often has full-time support staff
384
Q

Sunk Costs

A
  • costs already expended
  • should not be considered when deciding whether to continue with a troubled project
385
Q

Supporting Management Style

A

project manager encourages and provides assistance to team members and stakeholders in working through the situations they encounter

386
Q

Supportive PMO

A
  • provides the policies, methodologies, templates and lessons learned
  • attempts to promote consistency and streamline efforts
  • consultative
  • low level of control
387
Q

System Dynamics

A

relationship between components in an organization such as department, projects, people, bureaucracy, politics, and policies

388
Q

Tacit Knowledge

A
  • emotions, experience, and ability, which are more difficult to communicate clearly and require an atmosphere of trust
389
Q

Tangible Business Value

A

projects that add tangible business value create new products and things, such as new hardware or software, or even bring in new money

390
Q

Tangible Reward

A

money

391
Q

Target Price

A

in procurement process, used to compare the end result (final price) with what was expected (target price); a measure of success * don’t confuse target price with target cost or target fee * target cost plus target fee = target price

392
Q

Team-Building

A

guiding, managing, and improving the interactions of team members and is the project manager’s responsibility; creating the WBS is a team-building activity because it allows the team to actively engage in planning the project and helps them take ownership of it; training is team building; define rules to handle team disagreements

393
Q

Technical Risks

A

changes in technology, technical processes, or interfaces

394
Q

Termination

A

stopping work before it is completed

395
Q

Termination for Convenience

A

buyer terminates a contract before the work is complete because they no longer want the work to be done

396
Q

Terms of Reference (TOR)

A
  • for procurement of services rather than products
  • includes the work seller will perform
  • standards the seller is expected to achieve
  • data and services that will be provided to the buyer
397
Q

Testing

A

tests the product against the quality standards in your discipline; done throughout the project not just before scope validation because that could be costly

398
Q

Theory of Constraints

A

identify the most limiting factor in processes and improve it so it’s not longer the most limiting factor

399
Q

Threat Responses

A

in risk management, you try to avoid, mitigate, or transfer; avoid means attempt to eliminate the cause of a threat, and this is used for risk that is particularly high-impact; mitigate reduces the probability or impact and is also used for higher-impact risks; transfer means you make a party outside of the project responsible and can be done by purchasing insurance or warranties or outsourcing work

400
Q

Tight Matrix

A
  • co-located team
401
Q

Time and Material Contract (T&M)

A

buyer pays on a per-hour or per-item basis; used for time and materials in service efforts for which the level of effort cannot be defined when the contract is awarded; * * * has elements of fixed-price contract because hourly/per-item rate is fixed * has elements of cost-reimbursable contract in that materials and labor cost total is unknown * allows for quicker negotiations because terms and conditions are simpler * best used for small dollar amount work * seller’s profit is built into rate, so they have no incentive to get work done quickly or efficiently * often includes “not to exceed” clause * buyer has a MEDIUM amount of risk compared to cost-reimbursable or fixed-rate

402
Q

Time Is of the Essence Terms and Conditions

A

in a contract, delivery dates that are strictly binding; seller on notice that time is important and any delay is a material breach

403
Q

Time-Boxing

A

set a fixed deliver date for a project or release

404
Q

To Complete Performance Index (TCPI)

A

can you meet the BAC? can you meet the EAC? answers the question to stay within the budget, what rate do we need to meet for the remaining work? greater than one is bad; less than one is good * BAC = budget at completion * EV = earned value * AC = actual cost * TCPI = (BAC – EV) / (BAC – AC) * TCPI = (BAC – EV) / (EAC – AC)

405
Q

Tornado Diagram

A

shows the risks with the largest probability of happening and largest effects

406
Q

Total Float

A

asset that provides schedule flexibility; total float is the amount of time an activity can be delayed without delaying the project end or an intermediary milestone while still adhering to any imposed schedule constraints

407
Q

Transition Requirements

A

look at patterns that can predict future results; analyze delivery time, cost variance, and number of incorrect items; analyze whether or not corrective action has reduced errors

408
Q

Triangular (Simple Average) Estimating

A

(P + O + M)/3

409
Q

Tuckman Ladder Model

A

team-building happens in the following stages: * forming: people are brought together as team * storming: people position themselves to leaders or followers; disagreements as people learn to work together * norming: people accept their roles; project work begins; team members begin to build rapport * performing: team becomes efficient and works effectively together * adjourning: project ends and team is disbanded

410
Q

Uncertainty

A

lack of knowledge about an event that reduces confidence in conclusions drawn from data

411
Q

Unforseeable Risks

A

only a small portion of risks are truly unforeseeable, and then generally involve the customer, a lack of project management effort or knowledge, suppliers, or resistance to change

412
Q

Urgency Risk Parameter

A

indicates if the risk if likely to occur soon or if the risk requires a long time to plan a response; urgent risks may be moved directly into risk response planning

413
Q

Value Engineering

A

what’s the minimum amount of engineering or design to get the required value

414
Q

Variability Risks

A
  • risks caused by inability to predict future changes, such as defects, weather, malfunctioning equipment, new technology, new laws, the complexity of the project
  • type of non-event based risk
415
Q

Variable Cost

A

cost that changes with the amount of production or work, such as materials, supplies, and wages

416
Q

Virtual Team (Non-Collocated Team)

A
  • team scattered around the country or world
  • more inclusive because people with mobility issues can be on the project BUT communication is key
417
Q

Vroom’s Expectancy Theory

A

finding a less costly way to do the same work while maintaining scope

418
Q

Waivers

A

statements saying that rights under the contract may not be waived or modified other than express agreement of the parties

419
Q

Warranties

A

promises of quality for the goods or services delivered under the contract usually restricted to a certain time period

420
Q

Weak Matrix

A
  • power rests with functional manager and project manager is comparable to that of a coordinator or expediter
  • functional manager controls the budget
  • project manager and project team are part-time
421
Q

Whole Cost

A

consider the entire cost of resources for the project, including things like shipping

422
Q

Withdrawal (Avoidance) Style of Conflict Management

A

parties retreat or postpone decision on a problem; not usually the best choice on exam, although there may be situations where necessary

423
Q

Work Authorization System

A
  • component of the PMIS
  • coordinates when and in what order work is performed so that work and people may properly interface with other work and people
  • part of project management integration
424
Q

Work for Hire

A

work provided under the contract will be owned by the buyer

425
Q

Work Package

A

scope is broken down until each package can be realistically and confidently estimated including the activities, duration, and cost; advantages—can be completed quickly, can be completed without interruption or need for more information, may be outsourced; for example a particular function in a piece of software or a window in a room

426
Q

Work Performance Data

A

initial measurements and details about activities gathered during project work (executing)

427
Q

Work Performance Information

A

work performance data that have been analyzed to make sure they conform to the project management plan and to assess what they mean for the project (controlling)

428
Q

Work Performance Reports

A

work performance information that has been organized into reports and distributed to the various stakeholders (monitor and control)

429
Q

Work Shadowing

A

a knowledge management technique during which the learner follows the expert

430
Q

Working Capital

A
  • an organization’s current assets minus current liabilities
  • thus how much the organization has available to invest, including investing in projects
431
Q

Zero Sum Rewards

A

avoid these when developing a team; only one person can win zero sum awards

432
Q

Path Convergence

A
  • activity on a project schedule network diagram with two more activities directly preceding it
  • represents added risk to schedule
433
Q

Path Divergence

A
  • activity on a project schedule network diagram with two more activities directly succeeding it
  • represents added risk to schedule
434
Q

Specification Limits

A
  • customer’s requirements for quality and performance
  • unlike control limits, which are the organization’s quality standards
435
Q
A
436
Q

Four Main Sources fo Team Problems

A
  1. schedule
  2. project priorities
  3. resources
  4. technical opinions