PMP Formulas Flashcards
1
Q
Earned Value (EV)
A
- As of today, what is the estimated value of the work actually accomplished?
- EV = earned value
- BAC = budget at completion
- EV = % complete x BAC
2
Q
Estimate at Completion (EAC)
Bottom-Up ETC Formula
A
- Forecasts the project budget while the project is in progress
- This formula uses bottom-up estimating to calculate a new ETC and then new EAC
- AC = actual cost
- ETC = bottom-up estimate to complete
- EAC = AC + bottom-up ETC
3
Q
Estimate at Completion (EAC) CPI and SPI
A
- Forecasts the project budget while the project is in progress modified by performance
- Used when current variances probably typical of future
- Schedule constraints will influence the completion
- AC = actual cost
- BAC = budget at completion
- EV = earned value
- CPI = cost performance index OR SPI = schedule performance index
- EAC = AC + ((BAC – EV) / (CPI x SPI))
4
Q
Estimate at Completion (EAC)
Current Cost Performance
A
- Forecasts the project budget while the project is in progress
- Calculates actual costs to date plus remaining budget based on current cost
- Used when current variances are thought to be atypical of the future
- AC = actual cost
- BAC = budget at completion
- EV = earned value
- EAC = AC + (BAC – EV)
5
Q
Estimate at Completion (EAC)
Standard or No Variance Formula
A
- Typical way forecasting the project budget while the project is in progress
- BAC = budget at completion
- CPI = cost performance index
- EAC (Standard) = BAC / CPI
6
Q
Estimate to Complete (ETC)
A
- From this point on, how much more do we expect it to cost to finish the project?
- EAC = estimate at completion
- AC = actual cost
- ETC = EAC – AC
7
Q
Beta Standard Deviation
A
- Standard deviation for PERT estimate
- There is a 68% chance of estimate falling +/- 1 σ
- There is a 95% chance of estimate falling +/- 2 σ
- There is a 99% chance of estimate falling +/- 3 σ
- σ = (P – O)/6
8
Q
Cost Performance Index (CPI)
A
- Closer to 1, the better we are performing on cost
- We are getting $? worth of work out of every $1 spent
- funds are or are not being used efficiently
- Greater than one is good; less than one is bad
- EV = earned value
- AC = actual cost
- CPI = EV / AC
9
Q
Schedule Performance Index (SPI)
A
- Closer to 1 is better
- We are progressing at ? percent of the rate originally planned
- Greater than one is good; lesser than one is bad
- EV = earned value
- PV = planned value
- SPI = EV / PV
10
Q
Variance at Completion (VAC)
A
- As of today, how much over budget or under budget do we expect to be at the end of the project?
- BAC = budget at completion
- EAC = estimate at completion
- VAC = BAC – EAC
11
Q
Present Value
A
- FV= future value
- i = interest rate
- n = number of time periods
- PV = FV / (1 + i)n
12
Q
Buy-or-Build Formula
A
- (build out of pocket - buy out of pocket) / (build monthly fees - buy monthly fees) = number of months it will take for the build it yourself to make sense
- if you keep it longer than that number, it’s better to build it yourself