PMP Formulas Flashcards

1
Q

Earned Value (EV)

A
  • As of today, what is the estimated value of the work actually accomplished?
  • EV = earned value
  • BAC = budget at completion
  • EV = % complete x BAC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimate at Completion (EAC)

Bottom-Up ETC Formula

A
  • Forecasts the project budget while the project is in progress
  • This formula uses bottom-up estimating to calculate a new ETC and then new EAC
    • AC = actual cost
    • ETC = bottom-up estimate to complete
    • EAC = AC + bottom-up ETC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Estimate at Completion (EAC) CPI and SPI

A
  • Forecasts the project budget while the project is in progress modified by performance
  • Used when current variances probably typical of future
  • Schedule constraints will influence the completion
  • AC = actual cost
  • BAC = budget at completion
  • EV = earned value
  • CPI = cost performance index OR SPI = schedule performance index
  • EAC = AC + ((BAC – EV) / (CPI x SPI))
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate at Completion (EAC)

Current Cost Performance

A
  • Forecasts the project budget while the project is in progress
  • Calculates actual costs to date plus remaining budget based on current cost
  • Used when current variances are thought to be atypical of the future
  • AC = actual cost
  • BAC = budget at completion
  • EV = earned value
  • EAC = AC + (BAC – EV)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate at Completion (EAC)

Standard or No Variance Formula

A
  • Typical way forecasting the project budget while the project is in progress
  • BAC = budget at completion
  • CPI = cost performance index
  • EAC (Standard) = BAC / CPI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimate to Complete (ETC)

A
  • From this point on, how much more do we expect it to cost to finish the project?
  • EAC = estimate at completion
  • AC = actual cost
  • ETC = EAC – AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Beta Standard Deviation

A
  • Standard deviation for PERT estimate
  • There is a 68% chance of estimate falling +/- 1 σ
  • There is a 95% chance of estimate falling +/- 2 σ
  • There is a 99% chance of estimate falling +/- 3 σ
  • σ = (P – O)/6
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A
  • Closer to 1, the better we are performing on cost
  • We are getting $? worth of work out of every $1 spent
  • funds are or are not being used efficiently
  • Greater than one is good; less than one is bad
  • EV = earned value
  • AC = actual cost
  • CPI = EV / AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index (SPI)

A
  • Closer to 1 is better
  • We are progressing at ? percent of the rate originally planned
  • Greater than one is good; lesser than one is bad
  • EV = earned value
  • PV = planned value
  • SPI = EV / PV
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Variance at Completion (VAC)

A
  • As of today, how much over budget or under budget do we expect to be at the end of the project?
  • BAC = budget at completion
  • EAC = estimate at completion
  • VAC = BAC – EAC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Present Value

A
  • FV= future value
  • i = interest rate
  • n = number of time periods
  • PV = FV / (1 + i)n
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Buy-or-Build Formula

A
  • (build out of pocket - buy out of pocket) / (build monthly fees - buy monthly fees) = number of months it will take for the build it yourself to make sense
  • if you keep it longer than that number, it’s better to build it yourself
How well did you know this?
1
Not at all
2
3
4
5
Perfectly