Pre-Assessment Flashcards
A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project.
Which aspect of project management applies to this firm’s project?
Independent operations
Interdependent tasks
Regulatory concept
External environment
Interdependent tasks
A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness.
What can be identified as a strategic business initiative for this firm?
Timely payment of liabilities
Liaison with regulatory agencies
Improvement in product design
Environmental scanning
Improvement in product design
A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers.
Which stakeholder would have triggered this strategic business initiative?
Director of operations
Production supervisor
Project sponsor
Financial controller
Project sponsor
Which group is included in the five process groups?
Risk process group
Closing process group
Communication process group
Quality process group
Closing process group
What does PRINCE2 stand for?
PRoject INsights for CompEtitiveness
PRojects IN a Competitive Environment
PRoject INsights and CompEtencies
PRojects IN a Controlled Environment
PRojects IN a Controlled Environment
Which PMBOK process group is described as the delivery part of project management where the main activity happens?
Planning
Executing
Controlling
Closing
Executing
Which advantage does the functional (departmentalized) organizational structure provide for a firm with multiple projects?
Lines of authority are clear.
The project customer is the only focus.
It is efficient for collaboration and cooperation between departments.
Each project is managed holistically.
Lines of authority are clear.
Which two organizations are examples of organizations with the functional organizational structure?
Choose 2 answers
Microsoft The U.S. Department of State The U.S. National Aeronautics and Space Administration (NASA) The U.S Department of Energy Google Inc.
The U.S. Department of State
The U.S Department of Energy
An organization expects to use a project management office (PMO) to support multiple projects that will be implemented within a projectized organizational structure.
Which implied effect is a benefit to this organization?
Project team members retain their functional responsibilities.
Project team members become full-time employees.
Project team members gain access to the newest technologies and skill sets.
Project team members gain access to historical data from other projects.
Project team members gain access to historical data from other projects.
Regardless of the organizational structure used to manage a project, an organization elects to use a project management office (PMO).
Which benefit will this organization gain?
Projects will coordinate resource usage by monitoring the status of shared resources.
Projects will define the organization’s corporate strategy in the project charter.
Projects will receive a 10% managerial reserve fund to cover warranty back charges.
Projects will eliminate the costs incurred from having to follow corporate procedures.
Projects will coordinate resource usage by monitoring the status of shared resources.
During a certain project phase, specific blueprints are drawn and approved, materials and labor costs are estimated, prototypes are created, and work activities and tasks are identified. Also, quality expectations, measurements, and costs are defined.
During which project phase do these activities occur?
Defining
Planning
Executing
Closing
Planning
Place the project activities in order of occurrence from first (1) to last (5).
Select your answer from the pull-down list.
Developing the work breakdown structure Capturing lessons learned Working to produce project deliverables Collecting customer requirements Customers evaluating the project outcomes
Collecting customer requirements Developing the work breakdown structure Working to produce project deliverables Customers evaluating the project outcomes Capturing lessons learned
During which life cycle phase is the vast majority of the actual work to produce the project’s deliverables completed?
Defining
Planning
Executing
Closing
Executing
What is the correct term for an intermediate outcome of project work, such as a signed contract or obtaining a construction permit?
Deadline
Procurement
Statement of work
Deliverable
Deliverable
Which deliverable from a work breakdown structure (WBS) is not specific enough to measure its completion at project closure?
User training
User documentation manuals
Payment processing hardware
Hardware setup
User training
The following table shows the Level 1 work breakdown structure (WBS) for Project A.
WBS ID Description 0.0 Project A 1.0 Project started 2.0 Feasiblity 3.0 Design 4.0 Development 5.0 Manufacturing 6.0 Distribution 7.0 Project completed Which approach did the project manager use to structure the WBS?
List of deliverables
Sequence of project phases
Enumeration of functional departments
List of project stakeholders
Sequence of project phases
For the following collapsed work breakdown structure (WBS) for Project O, the project manager must complete the scope baseline. In addition to the WBS, the scope baseline will contain two additional documents.
WBS ID
- 0 Project O
- 0 Project Started
- 0 Feasibility
- 0 Design
- 0 Development
- 0 Manufacturing
- 0 Distribution
- 0 Project Completed
What are the other two documents that belong in the scope baseline?
Project charter and statement of work
Project contract and business case
WBS dictionary and project scope statement
Activity list and scope management plan
WBS dictionary and project scope statement
For the following collapsed work breakdown structure (WBS) for Project O, the project’s steering committee held a phase gate review of the Feasibility results. That review determined that the project’s proposed design would be obsolete before it would reach the marketplace.
WBS ID
- 0 Project O
- 0 Project Started
- 0 Feasibility
- 0 Design
- 0 Development
- 0 Manufacturing
- 0 Distribution
- 0 Project Completed
Which action should the project manager initiate?
Crashing the project’s schedule by asking for more resources
Fast-tracking the schedule by altering predecessor to successor relationships
Terminating the project as soon as possible and releasing the project’s resources
Looking for ways to make the design less costly
Terminating the project as soon as possible and releasing the project’s resources
A project is an operational necessity to repair a design flaw in the date field that constrains the year number to two digits, instead of permitting the year to be indicated with four digits. If the project is not completed before December 31, 1999, many legacy programs are expected to fail or produce unpredictable outcomes. The marketing department wants to upgrade its existing computer equipment and have the costs included in the budget for this project. The project team implemented the marketing department’s request without completing the formal change control procedures.
What has happened to the scope baseline in this scenario?
Scope updates have caused an unaffordable scope variance.
Scope creep has caused a scope variance.
Scope upgrade has caused a scope variance.
Scope risks have caused a smaller scope variance.
Scope creep has caused a scope variance.
A general contractor is managing a highway construction project that will repair a flood-damaged road. The project was documented in a cost-plus-incentive fee contract that specified a completion date of June 30. The Department of Transportation has offered an incentive for early completion of the repairs.
Which triple-constraint baseline remains unchanged by the effects of the incentive?
Scope
Time
Cost
Price
scope
In Project A, the contract specifies that time is very important. All of the scope must be completed, or the project will fail. The project’s objective requires the project team to work as quickly as possible.
Which triple constraint can be adjusted to permit the project team to work as quickly as possible?
Time
Cost
Price
Incentives
cost
In Project B, all of the scope must be completed, or the project will fail. The work is important but not urgent.
Which triple constraint can be adjusted if the project’s objective requires the project team to work at the lowest possible cost?
Time
Cost
Incentives
Penalties
time
A project manager is discussing the latest financial reports of a project to construct a grocery store and is approximately 90% into the planning phase. The project manager has been told by a project team member that other grocery stores in the area have an automated teller machine (ATM) for visitors. An ATM has not been discussed or incorporated into the planning of this project nor have any been incorporated into prior grocery store services. The leader calls for the immediate addition of an ATM into all prior grocery stores.
Which non-numeric model is this leader using?
Operating necessity
Competitive necessity
Sacred cow
Checklists
competitive necessity
An organization has a surplus of project dollars in the operating budget. The senior leader’s decision is to fund one more project with the remaining funds. Of the three projects proposed, one of the projects was selected without evaluation of feasibility or viability.
Which non-numeric model is this leader using?
Operating necessity
Competitive necessity
Sacred cow
Weighted factor
sacred cow
Each project team member generated a series of questions to evaluate three projects. The checklist was compiled into one list based on frequency of question content, such as personnel, materials, experience, and time. The more frequent the question content, the more likely the questions would be asked first.
Which two benefits result from this checklist approach?
Choose 2 answers
Operational impact has been built in.
Strategic impact has been integrated.
Biases have been reduced.
Priorities of senior leadership are met.
Operational impact has been built in.
Strategic impact has been integrated.