Module 26 Terms Flashcards
1
Q
critical path
A
Critical path is the longest path through the network.
2
Q
float (or slack)
A
Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.
3
Q
critical chain
A
A last thought is to consider the critical chain which builds on the critical path method by going a step further adding time buffers to account for limited resources. All projects have limited resources and a project manager must insure resources are well managed.