Practices (AI) Flashcards
What is the purpose of the 7 Practices in PRINCE2 7th Edition?
The purpose of the 7 Practices is to provide a structured approach to project management that ensures projects are successfully delivered.
True or False: The 7 Practices in PRINCE2 are only applicable to IT projects.
False
Fill in the blank: One of the 7 Practices is _____ which focuses on the continuous justification of the project.
Continued Business Justification
What does the Practice ‘Learn from Experience’ emphasize?
It emphasizes the importance of capturing lessons learned and applying them to future projects.
Which Practice is concerned with defining and maintaining the project’s scope?
Define and Control the Project
Multiple Choice: Which of the following is NOT one of the 7 Practices? A) Focus on Products B) Manage by Exception C) Risk Management D) Tailor to Suit the Project
C) Risk Management
What is the role of the Practice ‘Manage by Stages’?
It involves breaking the project into manageable stages for better control and monitoring.
True or False: The ‘Focus on Products’ Practice ensures that project deliverables are clearly defined and agreed upon.
True
Short Answer: What does ‘Tailor to Suit the Project’ refer to in PRINCE2?
It refers to adapting the PRINCE2 methodology to fit the specific needs and context of the project.
Which Practice encourages proactive identification of risks?
Manage Risks
What is the key output of the ‘Continued Business Justification’ Practice?
A justification for the project’s ongoing viability and alignment with business objectives.
Fill in the blank: The Practice ‘Manage by Exception’ allows for _____ decision-making.
delegated
What does the Practice ‘Focus on Products’ aim to achieve?
It aims to ensure that the project’s outputs meet the needs of the stakeholders.
Multiple Choice: Which Practice is primarily concerned with stakeholder engagement? A) Learn from Experience B) Manage by Stages C) Focus on Products D) Continued Business Justification
D) Continued Business Justification
True or False: ‘Learn from Experience’ is only relevant at the end of a project.
False
What is a primary benefit of ‘Manage by Stages’?
It allows for regular assessment of progress and necessary adjustments to the project plan.
Short Answer: How does ‘Manage Risks’ contribute to project success?
It helps to identify potential threats and opportunities, allowing for informed decision-making.
What is the significance of tailoring PRINCE2 practices?
Tailoring ensures that the methodology is appropriate for the project’s size, complexity, and risk.
Fill in the blank: The Practice ‘Define and Control the Project’ ensures that the _____ is clearly articulated.
project scope
Multiple Choice: Which Practice focuses on ensuring that the project is justified throughout its lifecycle? A) Manage by Exception B) Continued Business Justification C) Focus on Products D) Learn from Experience
B) Continued Business Justification
True or False: Each of the 7 Practices can be applied independently of one another.
True
What is the overall goal of the 7 Practices in PRINCE2?
To provide a framework that enhances project management effectiveness and efficiency.
Short Answer: What does the ‘Focus on Products’ Practice require from project teams?
It requires teams to prioritize deliverables and ensure they meet quality standards.
Fill in the blank: The Practice ‘Learn from Experience’ involves documenting _____ and applying them to future projects.
lessons learned