Practice: Progress Flashcards

1
Q

7 Tolerence types

A

Benefits
Time
Cost
Quality
Scope
Sustainability
Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 Types of PRINCE2 Controls

A
  1. Event-Driven
    Authorizing work packages
    Authrizing a stage
  2. Time-Driven
    Daily Checkpoints
    Weekly Highlight Reports
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity: Make decision on exception reports when stage level tolerances are forecast to be exceeded

A

Role: Project Executive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity: Define sustainability reporting requirements from the user perspective

A

Role: Senior User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activity: Ensure the progress towards the outcome is consisten from the supplier perspective

A

Role: Senior Supplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity: Produce exception reports for the Project Board when stage level or project level tolerances are forecast to be exceeded

A

Role: Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity: Confirm stage and project progress against tolerance

A

Role: Project Assurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity: Assist wit hthe compilation, dissemination and storage of reports (checkpoint report, exception reports, lessons report, end stage report, en project report)

A

Role: Project Support

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Inform Project Support of completed quality activities

A

Role:Team Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Progress Supporting techniques

A
  1. Dashboards
  2. DSU
  3. Earned Value Management
  4. Peer Review
  5. Burn Chart
  6. Retrospectives
  7. Kanban Board
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Senior Supplier:

A

The Senior Supplier is responsible for making sure the project remains focussed on the outcome from the supplier�s perspective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Senior User:

A

The Senior User is responsible for making sure any sustainability reporting requirements are defined from a user perspective, ensuring that evidential reporting on sustainability is a consequence of progress management, rather than an additional overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Manager:

A

The Project Manager is responsible for escalating a forecast to exceed the stages tolerances, as set by the Project Board when they authorised the stage, to the Project Board via the event-based exception report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project Executive:

A

The Project Executive, on behalf of, and in consultation with the Project Board, will decide whether to authorize the recommendation in an exception report if stage level tolerances are forecast to be exceeded, or provide another decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Team Manager:

A

When the team completes quality activities, Project Support will be informed so that the quality register can be maintained and if appropriate the product baselined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Assurance:

A

This is one of the Project Board�s assurance responsibilities and therefore undertaken by project assurance.

17
Q

Project Support:

A

Project Support help the Project Manager by undertaking these tasks, ensuring appropriate stakeholders, such as programme level, get access to progress reporting information.